In Washington you record a lien within 90 days after you ceased to furnish labor, professional services, materials, or equipment. You then have 8 calendar months after recording to file suit, plus service on the owner within 90 days of filing suit.
Washington lien law at a glance
| Topic | The rule in Washington | Statute |
|---|---|---|
| Record the lien | 90 days after the claimant ceased to furnish labor, professional services, materials, or equipment | RCW 60.04.091, RCW 60.04.141 |
| Enforce it (suit) | 8 calendar months after recording, plus service on the owner within 90 days of filing suit | RCW 60.04.091, RCW 60.04.141 |
| Preliminary notice | Yes, with exemptions for those contracting directly with the owner, laborers, and subcontractors contracting directly with the prime, subject to a narrow residential repair exception. No fixed deadline: the notice protects what was supplied not more than 60 days before it is mailed or served, shortened to 10 days for a new single-family residence. | RCW § 60.04.031 |
| Lien waivers | Statutory form: none prescribed. Advance waiver by contract: not addressed by statute. RCW 60.04.035 penalizes coercion, it does not void waivers. | Wash. Rev. Code ch. 60.04 |
| Public-work payment bonds | No dollar minimum; required on every public works contract; on contracts of $150,000 or less the contractor may choose 10% retainage instead | RCW 39.08.010(1), (3) |
Deadline to record a Washington lien
In Washington the deadline to record the lien is 90 days after the claimant ceased to furnish labor, professional services, materials, or equipment. The statutes are RCW 60.04.091 and RCW 60.04.141.
The 90 days run from the claimant’s own last furnishing. A credit manager who reads “90 days” and counts forward from the day the crew demobilized is correct in Washington, as in Florida and Michigan. The number is portable between states. The trigger is not.
Deadline to sue to enforce a Washington lien
Recording the lien only preserves the claim. In Washington the deadline to file suit is 8 calendar months after recording, plus service on the owner within 90 days of filing suit.
Washington notice of right to claim a lien
Washington is one of the states that call it a notice of right to claim a lien or a notice of right to lien. It is required, with exemptions for those contracting directly with the owner, laborers, and subcontractors contracting directly with the prime, subject to a narrow residential repair exception. The statute is RCW § 60.04.031.
There is no fixed deadline. The notice protects what was supplied not more than 60 days before it is mailed or served, shortened to 10 days for a new single-family residence. Everything furnished before that lookback is unprotected.
Send it to the owner or reputed owner and, where the prime contractor has complied with RCW 19.27.095, 60.04.230, and 60.04.261, the prime contractor as well, unless the claimant contracted directly with the prime.
Washington lien waivers
Washington prescribes no statutory lien waiver form (Wash. Rev. Code ch. 60.04). Advance waivers by contract are not addressed by statute. RCW 60.04.035 penalizes coercion, it does not void waivers.
Washington public-work payment bonds
On public work the bond replaces the lien. Washington sets no dollar minimum. A bond is required on every public works contract, and on contracts of $150,000 or less the contractor may choose 10% retainage instead. The statute is RCW 39.08.010(1), (3).
Several states, Washington among them, require a bond on covered contracts of any size unless a waiver or exception applies. A single number shown for these states elsewhere is usually a waiver ceiling, a bidding threshold, or a figure set by rule or council.
Paperwork that goes with it
Templates for the documents behind a Washington claim:
- Lien waiver, conditional progress (50-state pack)
- Lien waiver, unconditional progress (50-state pack)
- Lien waiver, conditional final (50-state pack)
- Lien waiver, unconditional final (50-state pack)
- Preliminary notice template (50-state)
- Notice of intent to lien template
- Statutory deadline tracker for lien claims
- Mechanics lien filing checklist, state by state
See every state
The same four topics for all 50 states:
- Mechanics lien deadlines by state
- Lien waiver requirements by state
- Payment bond requirements by state
- Preliminary notice deadlines by state
Frequently asked questions
How long do I have to record a mechanics lien in Washington?
90 days after you ceased to furnish labor, professional services, materials, or equipment (RCW 60.04.091).
Does Washington require a notice of right to claim a lien?
Yes, with exemptions for those contracting directly with the owner, laborers, and subcontractors contracting directly with the prime. There is no fixed deadline, but it protects only what was supplied not more than 60 days before it is mailed or served, or 10 days for a new single-family residence (RCW § 60.04.031).
Does Washington void advance lien waivers?
Washington’s statute does not address advance waivers by contract. RCW 60.04.035 penalizes coercion, it does not void waivers. Washington prescribes no statutory waiver form.
When does a public project in Washington need a payment bond?
Always. There is no dollar minimum, and a bond is required on every public works contract. On contracts of $150,000 or less the contractor may choose 10% retainage instead (RCW 39.08.010(1), (3)).
Related: lien waiver software
This page is a summary of what four 50-state references say about Washington, not legal advice. Check the statute, and a construction attorney licensed in Washington, before relying on it for a specific job.