Mechanics Liens

Mechanics lien deadlines by state

The deadline to record a mechanics lien in each of the 50 states, the separate deadline to file suit to enforce it, and the trigger event that actually starts each clock.

On this page
  1. What is a mechanics lien deadline?
  2. What event actually starts the mechanics lien clock?
  3. Why is the deadline to enforce a lien different from the deadline to file it?
  4. Do prime contractors, subcontractors, and suppliers get the same deadline?
  5. Can the property owner shorten your deadline?
  6. What are the mechanics lien deadlines in all 50 states?
  7. How do public projects change the analysis?
  8. What happens if you miss a mechanics lien deadline?
  9. What does this page not cover?
  10. How does Contracts Connected help contractors track lien deadlines?
  11. Frequently asked questions

What is a mechanics lien deadline?

A mechanics lien deadline is the statutory window in which a contractor, subcontractor, or supplier must record a lien claim against improved private property, followed by a separate window in which it must file suit to enforce that lien. Both windows are jurisdictional. Miss either one and the lien right is gone. No state grants a general extension for good faith, and none of them care that the money is genuinely owed.

That last point is what makes this area of law unforgiving in a way most contract deadlines are not. A late change order request can be argued. A late lien cannot. The debt survives, and the contractor keeps every ordinary right to sue on the contract, but the security interest in the property, which is the only reason the lien mattered, is extinguished on the day the clock runs out.

The stakes scale with the industry. The U.S. Census Bureau’s Value of Construction Put in Place survey estimated construction spending in July 2026 at a seasonally adjusted annual rate of $2,157.6 billion, of which $1,614.2 billion was private construction. Private work is the ground where lien rights exist at all, and it is roughly three quarters of everything built in the country.

What event actually starts the mechanics lien clock?

The trigger event varies by state, and it matters as much as the number of days. Most states start the clock on the claimant’s own last furnishing of labor or materials. A substantial minority start it on completion of the entire improvement, which can fall months after a given trade leaves the site. A third group starts it on an event the owner controls, such as recording a notice of completion.

This is the single most common way a lien is lost by a party that knew the deadline. A credit manager who reads “90 days” and counts forward from the day the crew demobilized is correct in Florida, Michigan, and Washington, and wrong in Arizona and Tennessee, where the same 90 or 120 day period runs from completion of the improvement itself. The number is portable between states. The trigger is not.

California illustrates the problem cleanly, because the statute sets two clocks and makes the earlier one control:

“A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times: (a) Ninety days after completion of the work of improvement. (b) Sixty days after the owner records a notice of completion or cessation.”

Cal. Civ. Code § 8412

Read that carefully. The 90 day figure everyone quotes for California is a ceiling, not the operative deadline, and the owner can lower it to 60 days for a direct contractor under Cal. Civ. Code § 8412(b) and to 30 days for everyone else under § 8414(b)(2) simply by recording a document the claimant may never see. Six states use a similar structure. Oregon goes further and makes its 75 day period run from the earlier of the claimant’s own cessation or completion of construction under ORS 87.035(1), so a supplier who finishes early can watch the window close while the job is still running.

A few states use triggers that resemble neither. Missouri runs six months from when “the indebtedness shall have accrued” under Mo. Rev. Stat. § 429.080, a phrase the statute does not define. Vermont runs 180 days from when payment became due for the last labor or materials under 9 V.S.A. § 1921(c). Hawaii uses a defined “date of completion” tied to publication of a notice and the filing of an affidavit with the court under HRS § 507-43. In each case the intuitive date is the wrong date.

Why is the deadline to enforce a lien different from the deadline to file it?

Recording the lien only preserves the claim. A second statute, almost always in a different section, sets the window to file suit to foreclose it, and letting that one lapse destroys the lien just as completely as never recording it. Most states measure this second clock from the date the lien was recorded. A dozen or so do not, and those are the states where experienced claimants still get caught.

Colorado is the clearest example. C.R.S. § 38-22-110 runs its six month enforcement window from the last work performed or completion of the improvement, the same events that govern the four month filing deadline under C.R.S. § 38-22-109(5). A claimant who records on the last available day has consumed most of the time available to sue. Minnesota does the same thing under Minn. Stat. § 514.12, subd. 3, measuring one year from the last item of the claim. North Carolina runs 180 days from last furnishing under N.C.G.S. § 44A-13(a) against a 120 day filing deadline, leaving 60 days for a claimant who files late. South Carolina, Illinois, Maine, New Jersey, South Dakota, and Alabama all measure enforcement from something other than the recording date.

Texas measures from a date that is neither. Tex. Prop. Code § 53.158(a) requires suit “not later than the first anniversary of the last day a claimant may file the lien affidavit under Section 53.052,” which means the clock runs from the statutory deadline rather than from the day the affidavit was actually filed. Filing early does not shorten the enforcement window in Texas, which is the opposite of the Colorado result.

There is a reason these windows are short, and it is not administrative tidiness. Bureau of Labor Statistics Business Employment Dynamics data on establishment survival shows that of the 57,753 construction establishments that opened in the year ended March 2020, 56.5 percent were still operating five years later in March 2025. Roughly two in five were gone. A lien claim that sits unenforced is a claim against a counterparty whose continued existence is not guaranteed, and the statutes are written on that assumption.

Do prime contractors, subcontractors, and suppliers get the same deadline?

In most states yes, but in roughly a dozen the deadline turns on who you contracted with, and in several of those the trigger event changes too, not just the number of days. Assuming parity across tiers is a reliable way to lose a supplier’s lien in a state that treats suppliers differently.

Kansas splits the period outright. A claimant with an owner contract gets four months under K.S.A. § 60-1102(a), while a subcontractor or anyone below gets three months under K.S.A. § 60-1103(a)(1). Oklahoma does the same, four months under 42 Okla. Stat. § 142 against 90 days under § 143, and there the split turns entirely on whether the supplier’s contract ran to the owner or to anyone beneath. Wyoming gives contractors 150 days and every other claimant 120 under Wyo. Stat. § 29-2-106(a). Alabama runs three periods off the same trigger under Ala. Code § 35-11-215: six months for an original contractor, four months for most other claimants, and 30 days for a journeyman or day laborer, the shortest ordinary lien window in the country.

Several states change the trigger rather than the duration, which is harder to spot. New Mexico gives an original contractor 120 days from completion of its own contract and everyone else 90 days from completion of the building under NMSA § 48-2-6(A), so the two classes are counting from genuinely different events. Delaware gives a direct contractor 180 days from completion of the structure and everyone else 120 days from that claimant’s own last delivery under 25 Del. C. § 2711. West Virginia holds the period constant at 100 days for every class while moving the trigger for each one across W. Va. Code §§ 38-2-7 through 38-2-9: completion of the contract for a general contractor, completion of the subcontract for a subcontractor, last furnishing for a materialman, and last work for a laborer.

Tennessee separates the classes structurally. A prime contractor’s lien runs one year from completion or abandonment of the improvement under Tenn. Code § 66-11-106, while a remote contractor must serve a notice of lien within 90 days and then sue within 90 days of that service under Tenn. Code § 66-11-115. Two claimants on the same project can be working against deadlines that differ by nine months.

Can the property owner shorten your deadline?

In at least ten states, yes, by recording a document the claimant has no control over and may never receive. This is the structural feature that makes calendar tracking from the claimant’s own records insufficient on its own.

Arizona cuts its 120 day period to 60 days when the owner records a notice of completion under A.R.S. § 33-993(A). Nevada cuts 90 days to 40 under NRS § 108.226(1) when a notice of completion is recorded and served. Utah cuts 180 days to 90 under Utah Code § 38-1a-502(1)(a) when a notice of completion is filed in the State Construction Registry. Alaska cuts 120 days to 15 under AS 34.35.068(b) once the owner records a notice of completion, for a claimant who gave no notice of right to lien or who received the owner’s advance notice of the recording. A claimant who records a notice of right to lien before or within those 15 days keeps the full 120. California, Massachusetts, Montana, Oregon, Wyoming, and Louisiana all have versions of the same completion-notice mechanism.

The mirror image exists on the enforcement side, where an owner or other interested party can force the claimant into court early. Florida allows a Notice of Contest of Lien that collapses the one year suit window to 60 days under Fla. Stat. § 713.22(2). Ohio’s nominal six year enforcement period under Ohio Rev. Code § 1311.13(C) can be cut to 60 days by a notice to commence suit under § 1311.11. Indiana, Nebraska, North Dakota, Mississippi, and South Dakota all provide a comparable demand mechanism, most of them on a 30 day fuse. A lien with years left on paper can be 30 days from void the moment an envelope arrives.

What are the mechanics lien deadlines in all 50 states?

The table below gives, for each state, the deadline to record the lien claim on a private project with the trigger event it runs from, the separate deadline to file suit to enforce it with its own trigger, and the governing statute for each. Where a state sets different periods by claimant class, all classes are shown. Where a rule is conditional, the condition is stated rather than flattened to a single number.

StateDeadline to record the lien (trigger event)Deadline to file suit to enforceGoverning statutes
AlabamaOriginal contractor 6 months; journeyman or day laborer 30 days; every other claimant 4 months, all from that claimant's last item furnished6 months from maturity of the entire indebtedness, not from filingAla. Code §§ 35-11-215, 35-11-221
Alaska120 days from when the claimant completes the contract or ceases to furnish. If the owner records a notice of completion, 15 days after that recording for a claimant who gave no notice of right to lien or who received the owner's advance notice of the recording, unless the claimant records a notice of right to lien before or within those 15 days6 months from recording, extendable 6 more by recorded noticeAS 34.35.068, AS 34.35.080
Arizona120 days after completion of the improvement; 60 days after the owner records a notice of completion6 months from recording the lienA.R.S. §§ 33-993(A), 33-998(A)
Arkansas120 days after the claimant's last furnishing of labor or materials15 months after filing the lien, plus a lis pendens (hedged, see note)Ark. Code §§ 18-44-117(a)(1), 18-44-119
CaliforniaDirect contractor: earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion. All others: earlier of 90 days after completion or 30 days after that notice90 days from recording the claim of lienCal. Civ. Code §§ 8412, 8414, 8460
ColoradoDay or piece laborers 2 months after completion of the improvement; all other claimants 4 months after that claimant's last labor or materials6 months from last work or completion, not from recording, plus a recorded notice of commencement of actionC.R.S. §§ 38-22-109(4), 38-22-109(5), 38-22-110
Connecticut90 days after the claimant ceases to perform, then serve a copy on the owner within 30 days of lodging1 year from recording, plus a recorded lis pendensConn. Gen. Stat. §§ 49-34, 49-39
DelawareDirect contractor 180 days after completion of the structure; all other claimants 120 days after that claimant's last labor or deliveryNo separate deadline. The statement of claim is itself the Superior Court complaint25 Del. C. §§ 2711(a), 2711(b), 2712, 2714
Florida90 days after the lienor's final furnishing; 90 days after termination of the original contract if that comes first1 year from recording; cut to 60 days by a Notice of Contest of LienFla. Stat. §§ 713.08(5), 713.22
Georgia90 days after completion of the work or furnishing of the materials or design services365 days from filing the lien, plus a notice of commencement of action within 30 days of suit (hedged, see note)O.C.G.A. § 44-14-361.1(a)(2), (a)(3)
Hawaii45 days after the statutory date of completion, which is completion of publication of a notice of completion plus filing of the affidavit, not actual completion3 months from the court's order directing the lien to attachHRS § 507-43(b), (e), (f), (g)
Idaho90 days after completion of the claimant's labor or services or furnishing of materials6 months from filing the claim of lienIdaho Code §§ 45-507(2), 45-510(1)
Illinois4 months after completion to bind third parties; 2 years after completion as against the owner alone2 years from completion of the contract, not from recording770 ILCS 60/7(a), 60/9, 60/28
Indiana90 days after the claimant performs labor or furnishes materials; 60 days for a Class 2 residential structure1 year from recording; cut to 30 days by a notice to forecloseInd. Code §§ 32-28-3-3, 32-28-3-6(a), 32-28-3-10
Iowa2 years and 90 days after last furnishing to post to the state Mechanics' Notice and Lien Registry, but posting after day 90 limits recovery to the balance the owner then owed the general contractor2 years from expiration of the 90 daysIowa Code §§ 572.8, 572.9, 572.10, 572.11, 572.27
KansasOwner contract claimants 4 months after last furnishing; subcontractors and remote claimants 3 months. On non-residential work either class can extend to 5 months by filing a notice of extension within its original period. Filed with the clerk of the district court1 year from filing the lien statementK.S.A. §§ 60-1102(a), 60-1102(c), 60-1103(a)(1), 60-1103(e), 60-1105(a)
Kentucky6 months after the claimant ceases to labor or furnish materials, then mail a copy to the owner within 7 days of filing12 months from filingKRS §§ 376.080(1), 376.090(1)
LouisianaDefault 60 days after a notice of termination or, absent one, substantial completion or abandonment. Where a notice of contract was filed: subs and suppliers 30 days after notice of termination or 6 months after substantial completion; general contractor 60 days or 7 months. Residential nonpayment notice extends to 70 days1 year from filing the statement of claimLa. R.S. §§ 9:4822(A) through 9:4822(D), 9:4823
Maine90 days after the claimant ceases to labor or furnish. Claimants in direct contract with the owner are exempt from recording entirely120 days after last furnishing, not from recording10 M.R.S. §§ 3253(1), 3253(2), 3255(1)
Maryland180 days after the work is finished or materials furnished, by petition to establish the lien in circuit court. There is no recording step1 year from the day the petition was first filedMd. Code, Real Prop. §§ 9-105(a), 9-109
MassachusettsNotice of contract by the earliest of 60 days after a notice of substantial completion, 90 days after a notice of termination, or 90 days after last work. Then a statement of account by the earliest of 90, 120, or 120 days on the same events90 days after filing the statement of account, plus record an attested copy of the complaint within 30 daysM.G.L. c. 254, §§ 2, 4, 5, 8, 11
Michigan90 days after the claimant's last furnishing of labor or material1 year from recording the claim of lienMCL §§ 570.1111(1), 570.1117(1)
Minnesota120 days after last work or furnishing, and the claimant must record and serve the owner within that same period1 year after the date of the last item of the claim, not from recordingMinn. Stat. §§ 514.08 subd. 1, 514.12 subd. 3
Mississippi90 days after the claimant's last work, labor, services, or materials180 days from filing; cut to 90 days by a recorded notice of contestMiss. Code §§ 85-7-405(1)(b), 85-7-421(1), 85-7-423
Missouri6 months after the indebtedness accrued; 60 days for rental equipment measured from its removal from the property6 months after filing the lienMo. Rev. Stat. §§ 429.080, 429.170
Montana90 days after the claimant's final furnishing, or 90 days after the owner files a notice of completion2 years from filing the lienMont. Code §§ 71-3-535(1), 71-3-562
Nebraska120 days after the claimant's final furnishing of services or materials2 years after recording; cut to 30 days by written demandNeb. Rev. Stat. §§ 52-137(1), 52-140
Nevada90 days after the latest of completion of the work of improvement, the claimant's last delivery of material or equipment, or the claimant's last work; or 40 days after a recorded and served notice of completion6 months from recording the notice of lienNRS §§ 108.226(1), 108.233(1)
New HampshireNo recording step. The lien continues 120 days after the claimant's services or materials and must be secured by attachment within that periodThe same 120 days. The attachment is the enforcement stepRSA §§ 447:9, 447:10
New JerseyNon-residential 90 days after the last work, services, material, or equipment. Residential within 120 days of last work and no later than 10 days after receipt of the arbitrator's determination1 year from the date of last provision of work, not from filing; or 30 days after written demandN.J.S.A. §§ 2A:44A-6(a)(2), 2A:44A-14(a), 2A:44A-21(b)
New MexicoOriginal contractor 120 days after completion of its contract; every other claimant 90 days after completion of the building or improvement2 years from filing the claim of lienNMSA §§ 48-2-6(A), 48-2-10
New York8 months after completion of the contract or final performance or furnishing; 4 months where the property is a single family dwelling1 year from filing, extendable by filing for most property but only by court order for a single family dwellingN.Y. Lien Law §§ 10(1), 17
North Carolina120 days after the claimant's last furnishing of labor or materials at the site180 days after the claimant's last furnishing, not from filingN.C.G.S. §§ 44A-12(b), 44A-13(a)
North Dakota90 days after all the claimant's contribution is done. Late filing does not defeat the lien except against good faith purchasers and to the extent the owner already paid, with a 3 year outer bar3 years from recording; cut to 30 days by written demandN.D.C.C. §§ 35-27-13, 35-27-14, 35-27-25
Ohio75 days after the claimant's last labor or materials; 60 days for a one or two family dwelling or a residential condominium unit6 years from filing, but cut to 60 days by a notice to commence suitOhio Rev. Code §§ 1311.06(B), 1311.11, 1311.13(C)
OklahomaClaimants contracting with the owner 4 months after last furnishing or labor; subcontractors and those below them 90 days1 year from filing the lien42 Okla. Stat. §§ 142, 143, 172
Oregon75 days after the claimant ceases to provide labor, rent equipment, or furnish materials, or 75 days after completion of construction, whichever is earlier. Design professionals and benefit plan trustees run 75 days from completion of construction120 days from filing the claim of lienORS 87.035(1), 87.045, 87.055
Pennsylvania6 months after completion of the claimant's own work. A subcontractor must give the owner 30 days' formal written notice of intent before filing2 years from filing, with a 5 year outer bar to verdict or judgment49 Pa. Stat. §§ 1501(b.1), 1502(a), 1701(b), 1701(d)
Rhode Island200 days after the work or materials: mail a notice of intention to the owner and record it, both within the period. Architects and engineers get the later of 200 days or 10 days after visible commencement40 days from recording the notice of intention, by complaint plus lis pendensR.I. Gen. Laws §§ 34-28-4(a), 34-28-7, 34-28-10(a)
South Carolina90 days after the claimant ceases to labor or furnish, and the claimant must serve the owner and file within that period6 months after cessation of labor, not from filing, plus a notice of pendencyS.C. Code §§ 29-5-90, 29-5-120(A)
South Dakota120 days after the claimant's last work or furnishing6 years from the date of the last item of the claim, not from recording, subject to an owner's demand to sueSDCL §§ 44-9-15, 44-9-24, 44-9-26
Tennessee90 days after the improvement is complete or abandoned. Recording preserves priority; as against the owner a prime's lien is effective without recording. Remote contractors serve a notice of lien in the same 90 daysPrime 1 year from completion or abandonment; remote contractor 90 days from service of the notice of lien (hedged, see note)Tenn. Code §§ 66-11-106, 66-11-112(a), 66-11-115
TexasOriginal contractor: 15th day of the 4th month after the month work was completed, terminated, or abandoned; 3rd month on residential. Other claimants: 15th day of the 4th month after the later of last furnishing or normal delivery of specially fabricated materials; 3rd month on residential. Retainage claims run to the 3rd month after the original contract endedNot later than the first anniversary of the last day the claimant could have filed the affidavit, not from actual filingTex. Prop. Code §§ 53.052, 53.158(a)
Utah180 days after final completion of the original contract; 90 days after a filed notice of completion, and never later than 180 days after final completion180 days after the claimant files the lien, plus a recorded notice of pendencyUtah Code §§ 38-1a-502(1), 38-1a-701(2)(a)(ii), 38-1a-701(3)
Vermont180 days from when payment became due for the last labor performed or materials furnished180 days from filing the memorandum, or from when payment becomes due if later, plus attachment of the property9 V.S.A. §§ 1921(c), 1923, 1924
Virginia90 days from the last day of the month in which the claimant last performed or furnished, and in no event later than 90 days from completion or termination. Both limbs must be metThe later of 6 months from recording the memorandum or 60 days from completion or terminationVa. Code §§ 43-4, 43-17
Washington90 days after the claimant ceased to furnish labor, professional services, materials, or equipment8 calendar months after recording, plus service on the owner within 90 days of filing suitRCW 60.04.091, RCW 60.04.141
West Virginia100 days for every class, but the trigger differs: general contractor from completion of the contract; subcontractor from completion of the subcontract, serving the owner and recording; materialman from last furnishing; laborer from last work6 months after filing the noticeW. Va. Code §§ 38-2-7, 38-2-8, 38-2-9, 38-2-34(a)
Wisconsin6 months from the claimant's last labor, services, or materials, filed with the clerk of circuit court. A 30 day notice of intent must be served first2 years from filing the claim for lienWis. Stat. § 779.06(1), (2)
WyomingContractors 150 days; every other claimant 120 days, from the earlier of the claimant's last work or furnishing or substantial completion of the project180 days after filing the lien statementWyo. Stat. §§ 29-2-106(a), 29-2-109

By state. One page each, with the same figures for a single state:

How this table was verified, and where it is softer. Every row was read against the state’s own legislature or official code database wherever one is publicly reachable. Three rows are marked hedged because an official current-code source was not reachable at publication. Georgia’s O.C.G.A. is published under state authority behind a bot gate, so the Georgia row rests on two independent commercial reproductions of the statutory text that agree with each other. Arkansas publishes its official code through a gated commercial host, so the Arkansas filing deadline is verified against the enacted session law that set it while the 15 month enforcement figure rests on a secondary source. Tennessee’s official current code is likewise gated, so that row is verified against the enacted public chapter that rewrote the state’s lien statute rather than against the codified text. Mississippi and New Jersey rows are verified against official enacted session law, which means amendments after enactment were not independently ruled out. Treat all five as reliable starting points rather than as final answers, and confirm them with counsel before acting. In September 2026 every row was rechecked against official sources for amendments from the 2025 and 2026 legislative sessions. That recheck found no amendment that changed a period or trigger event in the table.

How do public projects change the analysis?

On public work there is usually no mechanics lien right at all. Public property cannot be sold at foreclosure to satisfy a private claim, so states substitute a claim against a payment bond posted by the prime contractor. The deadlines for that claim come from the bond statute, not from the lien statute, and they are almost never the same numbers.

This is not a marginal category. Of the $2,157.6 billion seasonally adjusted annual rate of construction spending the Census Bureau estimated for July 2026, $543.4 billion was public construction. About a quarter of all construction work in the country sits outside the lien system entirely, and a claimant who reaches for the wrong body of law has usually discovered the mistake too late to fix it.

On federal construction the governing regime is the Miller Act. 40 U.S.C. § 3131(b) requires a payment bond on contracts above a statutory threshold “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract.” The claim deadlines then come from 40 U.S.C. § 3133(b), which requires a subcontractor or supplier whose contract ran to one of the prime’s own subcontractors, rather than to the prime, to give written notice to the prime contractor within 90 days of its last furnishing, and provides that an action “must be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action.” Both of those clocks run from the claimant’s own last furnishing, which makes federal bond practice more predictable than most state lien practice, but they are unforgiving in the same way. A firm whose contract ran to an ordinary supplier, or to a subcontractor below the first tier, has no claim on the bond at all.

State and local public work runs on each state’s own payment bond statute, which is a separate matter from this page. For that ground, see the state by state payment bond reference: Payment bond requirements by state→.

What happens if you miss a mechanics lien deadline?

The lien right is extinguished, and courts generally treat these periods as conditions on the existence of the right rather than as ordinary limitations periods subject to tolling, equitable extension, or excuse. The statutes frequently say so in terms that leave no interpretive room. California provides that a lapsed claim of lien “expires and is unenforceable.” Utah makes an unenforced lien “automatically and immediately void.” Alabama’s filing statute states that unless the required statement is filed, “the lien shall be lost.”

What survives is the underlying debt. A contractor who misses the lien deadline keeps every ordinary contract remedy it had: a breach of contract claim, a claim under a payment bond if one exists, a prompt payment claim where the state provides one, and whatever pressure the commercial relationship still carries. What it loses is the security, which is to say the only remedy that did not depend on the counterparty having money or the will to pay.

That distinction is why the deadline matters more on troubled jobs than on healthy ones, and troubled jobs are exactly where the paperwork is most likely to slip. The projects that generate lien claims are the projects where someone upstream is already not paying, where the record of who furnished what and when is contested, and where the person who knew the dates has often already left the company. Reconstructing a last furnishing date from an inbox, six weeks after the fact, is not a reliable way to hit a 45 day deadline in Hawaii or a 30 day deadline for an Alabama day laborer.

Free resources: Mechanics lien filing checklist, state by state→ · Lien claim statutory deadline tracker→

What does this page not cover?

Preliminary and pre-lien notice requirements are outside the scope of this page, and they are frequently the real reason a lien fails. Many states condition the lien on a notice served long before any filing deadline arrives: a notice of furnishing, a notice of right to lien, a notice to owner, or a notice of nonpayment, often due within 20 to 75 days of first furnishing rather than last. Several of those regimes are noted in passing in the table above where they change the filing analysis, but this page does not attempt to state them. A claimant who hits every deadline on this page and missed a preliminary notice still has no lien.

Also outside scope: lien priority against mortgages and other encumbrances, the substantive content and form requirements of the lien document itself, bonding around or discharging a lien, lien waivers and their statutory forms, residential homestead protections, and the tribal, railroad, oil and gas, and agricultural lien statutes that several states maintain separately from their general mechanics lien law.

Two structural cautions. First, these statutes change. Texas rewrote large parts of its lien chapter effective January 1, 2022, and in 2025 extended its weekend and holiday rule, which had covered only periods counted in days, to every deadline in the chapter. A lien affidavit deadline that falls on a Saturday, Sunday, or legal holiday now rolls forward to the next business day (Tex. Prop. Code § 53.003(e)). States amend filing periods, notice requirements, and residential carve-outs regularly, and more changes are pending: New Jersey bill A889, introduced in January 2026, would stretch the 90 day non-residential filing period to 240 days. A table is a snapshot. Second, the hard questions in this area are rarely about the number of days. They are about what counts as last furnishing when a punch list item is completed months after demobilization, whether warranty or corrective work restarts the clock, which of several triggers controls when more than one has occurred, and whether a given project is residential within the statutory definition. Those questions are decided by case law that no matrix captures.

Get a construction attorney licensed in the relevant state involved before a deadline is close, not after it has passed. By the time the date is in dispute, the only remaining question is usually how expensive the answer will be.

How does Contracts Connected help contractors track lien deadlines?

Contracts Connected keeps the documents that establish a lien deadline attached to the project and the counterparty they belong to, so the date can be computed from a record rather than reconstructed from memory. Every deadline on this page runs from a fact: a last furnishing date, a completion date, a recorded notice, an invoice, a contract termination. The legal analysis is only as good as the ability to prove when that fact occurred.

That is the part most firms get wrong, and it is a document problem before it is a legal one. The statute is public and the same for everyone. What differs between the firm that files on time and the firm that does not is whether anyone can say, on demand and with support, what date the clock started. Our co-founder ran a large federal general contracting firm for 15 years, about 100,000 documents a year.

Product page: lien waiver software→

Frequently asked questions

What is the deadline to file a mechanics lien?

It depends entirely on the state, and the range is wide. Ohio gives 75 days for most commercial work and 60 days on a one or two family dwelling. Alabama gives a day laborer 30 days. Pennsylvania and Wisconsin give six months. New York gives eight months on most property and four on a single family dwelling. There is no national rule and no safe default, so the state statute governs every time.

What event starts the mechanics lien clock?

The trigger varies by state and matters as much as the number of days. Most states run the clock from the claimant’s own last furnishing of labor or materials. Others run it from completion of the entire improvement, which can be months later. A third group runs it from an owner recorded notice of completion, from termination or abandonment of the contract, or from the date payment became due.

Is the deadline to enforce a mechanics lien different from the deadline to file it?

Yes, and they are separate obligations in nearly every state. Recording the lien preserves the claim. A second statute then sets a window to file suit to foreclose it, often measured from the recording date but not always. In Colorado, Minnesota, North Carolina, and South Carolina the enforcement clock runs from the work itself, so recording late eats the time available to sue.

Do subcontractors and suppliers have the same lien deadline as the prime contractor?

Not in every state. Alabama, California, Delaware, Kansas, Louisiana, New Mexico, Oklahoma, Tennessee, Texas, West Virginia, and Wyoming all set different periods or different trigger events depending on whether the claimant contracted directly with the owner. Kansas gives an owner contract claimant four months and a subcontractor three. Wyoming gives contractors 150 days and everyone else 120.

Can you file a mechanics lien on a public project?

Generally no. Public property cannot be sold to satisfy a private lien, so states substitute a claim against a payment bond instead. On federal construction the Miller Act at 40 U.S.C. 3131 requires a payment bond above a contract threshold, and 40 U.S.C. 3133 sets its own notice and suit deadlines that have nothing to do with state lien law. Confirm which regime applies before the clock starts.

What happens if you miss the mechanics lien deadline?

The lien right is extinguished, and courts treat these periods as jurisdictional rather than as ordinary limitations periods that can be excused. Statutes say so directly. California provides that the claim of lien expires and is unenforceable. Utah makes an unenforced lien automatically and immediately void. The underlying debt usually survives, but the security for it does not.