Mechanics Liens

Alaska Lien Law: Deadlines, Notices, Waivers and Bonds

The Alaska deadline to record a mechanics lien and the trigger that starts it, the suit deadline, the notice of right to lien, lien waiver rules and the public works payment bond threshold, with the statute for each.

On this page
  1. Alaska lien law at a glance
  2. Deadline to record an Alaska lien
  3. Deadline to sue to enforce an Alaska lien
  4. Alaska notice of right to lien
  5. Alaska lien waivers
  6. Alaska public-work payment bonds
  7. Paperwork that goes with it
  8. See every state
  9. Frequently asked questions

In Alaska you record a lien within 120 days from when you complete the contract or cease to furnish. If the owner records a notice of completion, the deadline can drop to 15 days after that recording, for a claimant who gave no notice of right to lien or who received the owner’s advance notice of the recording. You then have 6 months from recording to file suit, extendable 6 more by recorded notice.

Alaska lien law at a glance

Topic The rule in Alaska Statute
Record the lien 120 days from when the claimant completes the contract or ceases to furnish. If the owner records a notice of completion, 15 days after that recording for a claimant who gave no notice of right to lien or who received the owner’s advance notice of the recording, unless the claimant records a notice of right to lien before or within those 15 days AS 34.35.068, AS 34.35.080
Enforce it (suit) 6 months from recording, extendable 6 more by recorded notice AS 34.35.068, AS 34.35.080
Preliminary notice No. A notice of right to lien is protective rather than a precondition. None required. If given, the notice goes out before furnishing labor, material, service, or equipment (§ 34.35.064(a)). It may be recorded at any time after contracting or first furnishing (§ 34.35.067). Give it to the owner or owner’s agent. AS §§ 34.35.064, 34.35.068
Lien waivers Statutory form: none prescribed. Advance waiver by contract: barred, Alaska Stat. § 34.35.117(a). A waiver cannot cover work furnished after it is signed. Employee laborers cannot waive. Alaska Stat. §§ 34.35.050 to 34.35.120
Public-work payment bonds Over $100,000 (state and political subdivisions); a municipality may exempt qualifying contractors by ordinance on projects up to $400,000 Alaska Stat. §§ 36.25.010(a), 36.25.025

Deadline to record an Alaska lien

In Alaska the deadline to record the lien is 120 days from when the claimant completes the contract or ceases to furnish. The statutes are AS 34.35.068 and AS 34.35.080.

If the owner records a notice of completion, Alaska cuts the 120 days to 15 under AS 34.35.068(b) once the owner records it. That applies to a claimant who gave no notice of right to lien or who received the owner’s advance notice of the recording. A claimant who records a notice of right to lien before or within those 15 days keeps the full 120.

Deadline to sue to enforce an Alaska lien

Recording the lien only preserves the claim. In Alaska the deadline to file suit is 6 months from recording, extendable 6 more by recorded notice.

Alaska notice of right to lien

A preliminary notice is not required in Alaska. A notice of right to lien is protective rather than a precondition. If given, the notice goes out before furnishing labor, material, service, or equipment (§ 34.35.064(a)). It may be recorded at any time after contracting or first furnishing (§ 34.35.067). It goes to the owner or owner’s agent.

Without it, the claimant has the burden of proving the owner knew of and consented to the work in a foreclosure action (§ 34.35.064(a)). If the owner records a notice of completion, a claimant who gave no notice of right to lien must record a claim of lien or notice of right to lien within 15 days after that recording (§ 34.35.068(b)(1)).

Alaska lien waivers

Alaska prescribes no statutory lien waiver form (Alaska Stat. §§ 34.35.050 to 34.35.120). A contract clause that waives lien rights in advance is barred under Alaska Stat. § 34.35.117(a). A waiver cannot cover work furnished after it is signed, and employee laborers cannot waive.

Alaska is among the twenty-nine states where a statute voids or bars a contract clause that waives lien rights before labor or materials are furnished or before payment is received.

Alaska public-work payment bonds

On public work the bond replaces the lien. In Alaska the threshold is over $100,000 for the state and political subdivisions. A municipality may exempt qualifying contractors by ordinance on projects up to $400,000. The statutes are Alaska Stat. §§ 36.25.010(a) and 36.25.025.

Paperwork that goes with it

Templates for the documents behind a Alaska claim:

See every state

The same four topics for all 50 states:

Frequently asked questions

How long do I have to record a mechanics lien in Alaska?

120 days from when you complete the contract or cease to furnish. If the owner records a notice of completion, it is 15 days after that recording for a claimant who gave no notice of right to lien or who received the owner’s advance notice of the recording, unless you record a notice of right to lien before or within those 15 days (AS 34.35.068).

Does Alaska require a preliminary notice?

No. A notice of right to lien is protective rather than a precondition. Without it, you carry the burden of proving the owner knew of and consented to the work in a foreclosure action (§ 34.35.064(a)).

Can an Alaska contract waive lien rights in advance?

No. Alaska bars it at Alaska Stat. § 34.35.117(a). A waiver cannot cover work furnished after it is signed, and employee laborers cannot waive.

When does a public project in Alaska need a payment bond?

Over $100,000 for the state and political subdivisions. A municipality may exempt qualifying contractors by ordinance on projects up to $400,000 (Alaska Stat. §§ 36.25.010(a), 36.25.025).

Related: lien waiver software

This page is a summary of what four 50-state references say about Alaska, not legal advice. Check the statute, and a construction attorney licensed in Alaska, before relying on it for a specific job.