In California a direct contractor records a lien before the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion. Everyone else has the earlier of 90 days after completion or 30 days after that notice. You then have 90 days from recording the claim of lien to file suit.
California lien law at a glance
| Topic | The rule in California | Statute |
|---|---|---|
| Record the lien | Direct contractor: earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion. All others: earlier of 90 days after completion or 30 days after that notice | Cal. Civ. Code §§ 8412, 8414, 8460 |
| Enforce it (suit) | 90 days from recording the claim of lien | Cal. Civ. Code §§ 8412, 8414, 8460 |
| Preliminary notice | Yes, from every claimant except laborers. A direct contractor gives notice only to the construction lender. Deadline: 20 days after the claimant first furnished work on the work of improvement. Late notice preserves rights only for work performed in the 20 days before service and thereafter. Compliance is a necessary prerequisite to a valid lien or stop payment notice. | Cal. Civ. Code §§ 8200, 8204 |
| Lien waivers | Statutory form: yes, four forms. Advance waiver by contract: void, Cal. Civ. Code § 8122. A waiver is void unless substantially in the statutory form. | Cal. Civ. Code §§ 8120 to 8138 |
| Public-work payment bonds | Over $25,000 (state and local public entities) | Cal. Civ. Code § 9550; Cal. Pub. Cont. Code § 7103 |
Deadline to record a California lien
California sets two clocks and makes the earlier one control. The statute reads:
“A direct contractor may not enforce a lien unless the contractor records a claim of lien after the contractor completes the direct contract, and before the earlier of the following times: (a) Ninety days after completion of the work of improvement. (b) Sixty days after the owner records a notice of completion or cessation.”
The 90 day figure everyone quotes for California is a ceiling, not the operative deadline. The owner can lower it to 60 days for a direct contractor under Cal. Civ. Code § 8412(b) and to 30 days for everyone else under § 8414(b)(2) simply by recording a document the claimant may never see.
For a direct contractor the deadline is the earlier of 90 days after completion or 60 days after the owner records a notice of completion. For all others it is the earlier of 90 days after completion or 30 days after that notice. The statutes are Cal. Civ. Code §§ 8412, 8414 and 8460.
California sets different periods or different trigger events depending on whether the claimant contracted directly with the owner.
Deadline to sue to enforce a California lien
In California the deadline to file suit is 90 days from recording the claim of lien. California provides that a lapsed claim of lien “expires and is unenforceable.”
California preliminary notice
California calls it a preliminary notice. It is required from every claimant except laborers. A direct contractor is relieved of notice to the owner but still has to serve the construction lender, if there is one. The statutes are Cal. Civ. Code §§ 8200 and 8204.
The deadline is 20 days after the claimant first furnished work on the work of improvement. California is one of the states with a true early-stage deadline running from first furnishing.
Send it to the owner or reputed owner, the direct contractor or reputed direct contractor, and the construction lender or reputed construction lender if any.
A late notice still works going forward. California uses a 20-day lookback: you keep lien rights for work furnished in the 20 days before service and everything after, and you lose everything earlier. Compliance is a necessary prerequisite to a valid lien or stop payment notice.
California lien waivers
California is one of eleven states that prescribe a lien waiver form in their statutes, and one of five that prescribe all four forms, conditional and unconditional across progress and final payment (Cal. Civ. Code §§ 8120 to 8138). A waiver is void unless substantially in the statutory form.
California is among the twenty-nine states where a statute voids or bars an advance waiver. Cal. Civ. Code § 8122 voids any contract term that purports to affect another claimant’s rights unless and until that claimant signs an actual statutory waiver.
California does not require notarization. Its waiver forms print no notary requirement.
California public-work payment bonds
On public work the bond replaces the lien. In California the payment bond threshold is over $25,000 for state and local public entities (Cal. Civ. Code § 9550; Cal. Pub. Cont. Code § 7103). Most states bar liens against publicly owned property, so a subcontractor’s main remedy for nonpayment on a public job is the payment bond claim process, not a lien on the property. Some states, such as California, also allow a claim against the unpaid contract funds.
Paperwork that goes with it
Templates for the documents behind a California claim:
- Lien waiver, conditional progress (50-state pack)
- Lien waiver, unconditional progress (50-state pack)
- Lien waiver, conditional final (50-state pack)
- Lien waiver, unconditional final (50-state pack)
- Preliminary notice template (50-state)
- Notice of intent to lien template
- Statutory deadline tracker for lien claims
- Mechanics lien filing checklist, state by state
See every state
The same four topics for all 50 states:
- Mechanics lien deadlines by state
- Lien waiver requirements by state
- Payment bond requirements by state
- Preliminary notice deadlines by state
Frequently asked questions
How long do I have to record a mechanics lien in California?
A direct contractor has the earlier of 90 days after completion of the work of improvement or 60 days after the owner records a notice of completion. Everyone else has the earlier of 90 days after completion or 30 days after that notice (Cal. Civ. Code §§ 8412, 8414).
Does California require a preliminary notice?
Yes, from every claimant except laborers, within 20 days after first furnishing work. A direct contractor gives notice only to the construction lender. A late notice preserves rights only for work performed in the 20 days before service and thereafter (Cal. Civ. Code §§ 8200, 8204).
Does California have statutory lien waiver forms?
Yes, four forms, at Cal. Civ. Code §§ 8120 to 8138. A waiver is void unless substantially in the statutory form, and Cal. Civ. Code § 8122 voids a contract term that waives lien rights in advance.
When does a public project in California need a payment bond?
Over $25,000 for state and local public entities (Cal. Civ. Code § 9550; Cal. Pub. Cont. Code § 7103).
Related: lien waiver software
This page is a summary of what four 50-state references say about California, not legal advice. Check the statute, and a construction attorney licensed in California, before relying on it for a specific job.