A preliminary notice is a written notice a contractor, subcontractor, or supplier sends near the start of a construction project to tell the property owner and others that the sender is furnishing labor or materials and may claim a mechanics lien if it is not paid. In most states that require one, it is a precondition to lien rights.
It goes by different names depending on where you are working. California and Arizona call it a preliminary notice. Ohio and Michigan call it a notice of furnishing. Washington, Montana, and Nevada call it a notice of right to claim a lien or a notice of right to lien. Utah requires it to be filed on a state-run registry rather than mailed, and Iowa does the same for residential construction. North Carolina requires it to be delivered to a designated lien agent. The name changes, the function does not: it puts the owner on notice that someone the owner may never have met is working on the property and has rights against it.
Three things it is not. It is not a lien. It is not an accusation of nonpayment. And it is not optional in the states that require it. Nevada’s statute makes the first point directly, saying the notice “does not constitute a lien,” and makes the second inside the form language it mandates, telling the owner that the notice “is not a notice that the undersigned has not been or does not expect to be paid, but a notice required by law.” That framing matters commercially, because the most common reason firms skip the notice is a fear of damaging the relationship, and the statute itself anticipates that fear.
The scale of what these statutes govern is not small. According to the U.S. Census Bureau’s monthly construction spending release for August 2026, construction spending was estimated at a seasonally adjusted annual rate of $2,203.1 billion, of which private construction accounted for $1,655.3 billion. Private work is where mechanics lien rights live, and preliminary notice is the entry ticket to those rights in about half the country.
Which states require a preliminary notice?
Roughly half the states require some form of notice near the start of work, and the requirement is designed differently enough in each that state-by-state checking is the only safe method. There is no regional pattern to lean on and no safe default.
It helps to sort the country into four groups rather than treating it as a binary.
States with a true early-stage deadline running from first furnishing. North Carolina at 15 days, Arizona at 20 days, California at 20 days, Michigan at 20 days, Montana at 20 days, Utah at 20 days, Ohio at 21 days, Mississippi at 30 days, Wyoming at 30 days for subcontractors and suppliers, Florida at 45 days, Minnesota at 45 days, Wisconsin at 60 days, and New Mexico at 60 days. This is the group most people mean when they say preliminary notice. Several apply only to some projects. North Carolina’s goes to a lien agent on projects that require one, Montana exempts commercial work, New Mexico reaches only claims over $5,000 from lower-tier claimants outside homes of four or fewer units, Wisconsin requires the notice only on residential work of four or fewer units, Minnesota exempts larger multifamily and nonresidential work, Mississippi uses a different notice on single-family homes, and Ohio requires it only where a notice of commencement was recorded. Massachusetts also runs 30 days from commencement of performance, but missing its notice of identification caps the lien rather than defeating it.
States where the notice is real but keyed to something other than first furnishing. Oklahoma runs 75 days from the last date of supply. Texas uses a monthly cadence tied to each month in which labor or materials were provided. Illinois runs 90 days from completion of the claimant’s work. Connecticut runs from commencement to no later than 90 days after ceasing to furnish. Maryland runs 120 days after doing the work. Rhode Island runs 200 days. Kentucky runs 75 or 120 days from the last item furnished, depending on the size of the claim. These are still notice obligations that can cost lien rights, but the clock does not start where you expect.
States where the notice obligation only switches on if the owner or contractor does something first. Georgia’s notice to contractor applies only on projects where a notice of commencement has been filed. South Carolina’s notice of furnishing applies only if a notice of project commencement was filed, and it caps rather than kills the lien. South Dakota also ties its notice of furnishing to a filed notice of project commencement, but a missed notice there bars the sub-subcontractor or supplier from filing the lien statement that keeps the lien alive, so its lien ends 120 days after the last work. Ohio requires its notice of furnishing only if a notice of commencement was recorded, and both Ohio and Michigan key the recipient list to the designee named in that notice. Pennsylvania’s Notice of Furnishing applies only on a project of $1,500,000 or more where the owner filed and posted a Notice of Commencement. In this group, the correct first question is not “what is the deadline” but “was a notice of commencement filed, and where.”
States with no preliminary notice at all. New York, Maine, Delaware, and Hawaii do not require one as a condition of perfecting a mechanics lien. Virginia requires none except on one- or two-family homes where the building permit names a mechanics’ lien agent, who must be notified within 30 days of first furnishing. Colorado and North Dakota require notice only shortly before a lien statement is recorded, which is a notice of intent rather than a preliminary notice. Alabama works the same way: every claimant except the original contractor must notify the owner before filing the lien statement. Nebraska’s notice of right to assert a lien is expressly permissive: the statute says a claimant “may give notice,” not must.
Who has to send a preliminary notice?
In most states, only claimants who have no direct contract with the property owner have to send one, because the owner already knows about the parties it hired directly. The purpose of the statute is to surface the people the owner cannot see: the second-tier subcontractor, the equipment lessor, the material supplier who never sets foot in a meeting.
That default has real exceptions, and they are the ones that catch experienced firms.
Arizona requires the preliminary twenty day notice from essentially every claimant furnishing labor, professional services, materials, machinery, fixtures, or tools, including the party with a direct contract with the owner. California takes a split approach: a direct contractor is relieved of notice to the owner but still has to serve the construction lender, if there is one. Wyoming requires a contractor to send notice before receiving any payment from the owner, including advances, and requires subcontractors and materialmen to send within 30 days of first providing services or materials. Missouri puts the duty on the original contractor to give the person it contracts with a specific notice in ten-point bold type at contract signing, delivery, commencement, or with the first invoice, and in any case before receiving any payment. Compliance is a condition precedent to that original contractor’s own mechanics lien.
Laborers are the most common exemption. California, Arizona, Nevada, Montana, and Washington all carve out people claiming for their own wages, on the reasonable theory that a worker owed a paycheck should not lose a remedy to a paperwork rule.
The number of firms that have to run this process is large. The Bureau of Labor Statistics Quarterly Census of Employment and Wages counts 953,703 private industry construction establishments (NAICS 23) in the first quarter of 2026. Most of those establishments sit somewhere below the prime contractor on at least one project, which is precisely the position the notice statutes were written to address.
When is a preliminary notice due, and what is the deadline measured from?
Most states measure the deadline from first furnishing of labor or materials, which is why the notice is called preliminary, but several measure from the last furnishing, from completion, or from a monthly cycle instead. Reading the wrong end of the job into the statute is one of the most common ways firms lose a right they thought they had.
Here is the operative language from the state most often used as the model, quoted directly:
“A preliminary notice shall be given not later than 20 days after the claimant has first furnished work on the work of improvement. … The claimant shall, however, be entitled to record a lien, give a stop payment notice, and assert a claim against a payment bond only for work performed within 20 days prior to the service of the preliminary notice, and at any time thereafter.”
Two rules are doing work in that passage, and they are worth separating. The first is the deadline. The second is the lookback, which is the more practically important of the two and the one most often misunderstood.
A related trap is the definition of first furnishing itself. Delivery of materials to the jobsite, mobilization, staging, and off-site fabrication are not always treated the same way, and a supplier who starts the clock at the date of the purchase order rather than the date of first delivery can be off by weeks. Where the statute does not define the trigger cleanly, the conservative practice is to run the clock from the earliest defensible date rather than the most convenient one.
A handful of states do not run on days at all. Nevada sets no deadline: the notice may be given at any time after first delivery or performance, and it simply protects the 31 days before it was given plus everything after. Iowa’s residential preliminary notice has no day count either. It is posted to the state’s Mechanics’ Notice and Lien Registry and is effective as to work furnished as long as it is posted before the balance due is paid to the general contractor or owner-builder. New Hampshire and Vermont do not set one. A claimant without a contract with the owner gets a lien only by giving the owner written notice. In Vermont the lien reaches only what the owner still owes its contractor when the notice arrives. New Hampshire works the same way unless the notice goes out before the labor or material is furnished, which secures the full lien. In all four states the question is not “am I late” but “how much have I already lost.”
Who has to receive a preliminary notice?
The owner is the near-universal recipient, and many states add the general contractor, the construction lender, or a state registry on top of that. Serving one party and not the others is a complete failure of the notice in most of the states that specify multiple recipients.
Arizona has the longest list: the owner or reputed owner, the original contractor or reputed contractor, the construction lender or reputed construction lender if any, and the person with whom the claimant contracted. California requires the owner or reputed owner, the direct contractor or reputed direct contractor, and the construction lender or reputed construction lender if any. Washington requires the owner or reputed owner and, where the prime contractor has complied with RCW 19.27.095, 60.04.230, and 60.04.261, the prime contractor as well, unless the claimant contracted directly with the prime.
Four states send the notice to a registry or a lien agent instead of the owner, at least on some jobs. Utah requires the preliminary notice to be filed with the State Construction Registry. For residential construction, Iowa requires posting to the Mechanics’ Notice and Lien Registry, and the registry administrator then sends notification to the owner. North Carolina requires delivery to a lien agent designated by the owner, with the lien agent requirement itself triggered where the costs of the undertaking are $40,000 or more, other than improvements to an existing single-family residence occupied by the owner. Pennsylvania runs a State Construction Notices Directory for larger jobs. In all four, mailing a beautifully drafted notice to the owner and stopping there accomplishes nothing.
Where a notice of commencement governs, the recipient list is inside that document rather than inside the statute. Ohio and Michigan both direct the notice of furnishing to the designee named in the notice of commencement, and to the contractor named there, at the addresses listed in it. That makes locating and reading the notice of commencement the actual first task, before any drafting begins.
How does a preliminary notice have to be delivered?
Delivery method is usually specified, and in the states that specify it, using a faster or more convenient method than the statute allows can invalidate an otherwise perfect notice. Certified or registered mail with return receipt is the most common requirement.
Nevada requires delivery in person or by certified mail. Rhode Island requires prepaid registered or certified mail with return receipt requested, and voids the lien if the mailed notice comes back undelivered unless the claimant files the notice with the returned envelope within 30 days of the return and no more than 200 days after mailing. Maryland requires registered or certified mail with return receipt or personal delivery. South Carolina and South Dakota require certified or registered mail. Georgia requires registered or certified mail or statutory overnight delivery. New Mexico allows certified mail with return receipt requested, facsimile with acknowledgement, or personal delivery.
Two practical consequences follow. First, keep the proof, not just the notice. The return receipt, the registry filing confirmation, or the affidavit of service is the document that will actually be produced if the notice is ever challenged, and it is the one most often missing from the file two years later. Colorado makes this explicit by requiring an affidavit of service to be recorded along with the lien statement as proof. Second, some states fix the moment of service by statute. Illinois provides that notice is considered served at the time the written notice is placed with the delivery service or in the mail, which means the mailing date, not the receipt date, is what you are tracking.
What do you lose by missing the preliminary notice deadline?
In some states you lose lien rights on the claim entirely, and in others you lose only the work performed before a short lookback window that runs backward from the day you finally send it. The difference between those two outcomes decides whether a late notice is a partial loss or a total one, and it is the single most valuable thing to know about your state.
Total forfeiture states. Florida is blunt: failure to serve the notice, or to timely serve it, is a complete defense to enforcement of a lien by any person. Maryland provides that a subcontractor who does not give notice within 120 days is not entitled to a lien. Wyoming provides that failure to send the notice within the time specified bars the right to assert a lien. Tennessee provides that a remote contractor on a covered project who does not serve the notice of nonpayment has no right to claim a lien, except as to retainage held to guarantee its performance.
Lookback states. California and Arizona use a 20-day lookback: send the notice late and you keep lien rights for work furnished in the 20 days before service and everything after, and you lose everything earlier. Ohio uses 21 days the same way and states directly that a late notice “does not revive any prior lien rights.” New Mexico uses 30 days. Montana’s text is narrower: a late notice makes the lien enforceable only for what was furnished within the 20 days before notice is given, or 45 days on certain lender-funded work. Nevada’s 31-day lookback works this way by design rather than as a penalty. Washington protects work supplied in the 60 days before the notice, shortened to 10 days for a new single-family residence. Utah’s late-filing rule is stricter than a lookback and runs the other direction. A late preliminary notice protects nothing before the fifth day after it is filed, and a notice filed more than 10 days after a notice of completion has no effect. Wisconsin and Virginia also run forward only. In Wisconsin, a late notice supports a lien only for work furnished after the owner actually receives it. In Virginia, on a one- or two-family home whose building permit names a mechanics’ lien agent, a late notice to the agent supports a lien only for work furnished on or after the day it is given.
Cap states. A third pattern reduces the size of the lien rather than eliminating it. South Carolina caps the lien of a sub-subcontractor or supplier at the amount the contractor owes the subcontractor unless the notice of furnishing was given. Massachusetts limits the lien of a claimant with no direct contract with the original contractor to the amount due or to become due under the original contractor’s subcontract that includes the claimant’s work, unless the claimant gave a notice of identification within 30 days of commencing performance. Alabama’s rule for materialmen without a direct owner contract works on similar logic.
The operational lesson is the same in all three groups. A late notice is almost always better than no notice, and an on-time notice is worth more than any negotiation you will have about it afterward.
What are the preliminary notice requirements in all 50 states?
The table below is the reference. Each row states whether the state requires a preliminary or pre-lien notice, the deadline and what it runs from, who must receive it, what missing it costs, and the governing statute by section number.
Read the row, then read the statute. This table is a starting point for a jurisdiction, not a substitute for the text of the law in it.
| State | Preliminary notice required? | Deadline, and what it runs from | Who must receive it | What missing it costs | Governing statute |
|---|---|---|---|---|---|
| Alabama | No early-stage notice is required. A supplier furnishing material to a contractor or subcontractor may notify the owner before furnishing to secure a lien for the full price, unless the owner then notifies the supplier in writing, before the material is used, that the owner will not be responsible for the price (§ 35-11-210). Every claimant except the original contractor must give the owner written notice of its lien claim before filing the lien statement (§ 35-11-218). | § 35-11-210 notice: before furnishing the material. § 35-11-218 notice: before filing the lien statement with the judge of probate. The § 35-11-218 notice is not needed for material covered by an advance § 35-11-210 notice. | Owner or proprietor, or the owner's agent. | Without the § 35-11-210 notice, a supplier's lien is limited to the unpaid balance due the contractor rather than the full price. The § 35-11-218 notice must be given before the lien statement is filed. | Ala. Code §§ 35-11-210, 35-11-218 |
| Alaska | No. A notice of right to lien is protective rather than a precondition. | None required. If given, the notice goes out before furnishing labor, material, service, or equipment (§ 34.35.064(a)). It may be recorded at any time after contracting or first furnishing (§ 34.35.067). | Owner or owner's agent. | Not a precondition to the lien. Without it, the claimant has the burden of proving the owner knew of and consented to the work in a foreclosure action (§ 34.35.064(a)). If the owner records a notice of completion, a claimant who gave no notice of right to lien must record a claim of lien or notice of right to lien within 15 days after that recording (§ 34.35.068(b)(1)). | AS §§ 34.35.064, 34.35.068 |
| Arizona | Yes, and from essentially every claimant, including one contracting directly with the owner. Wage laborers exempt. | 20 days after first furnishing labor, professional services, materials, machinery, fixtures, or tools to the jobsite. | Owner or reputed owner, original contractor or reputed contractor, construction lender or reputed construction lender if any, and the person the claimant contracted with. | Late notice preserves a lien only for what was furnished in the 20 days before service and thereafter. | A.R.S. § 33-992.01 |
| Arkansas | Yes, with different rules by project type. Residential real estate of four or fewer units: the residential contractor must give the owner the statutory notice before work begins, on behalf of all potential lien claimants, and any other claimant may also give it (§ 18-44-115(a)(3), (a)(5)(A)). Not required if the contractor supplies a performance and payment bond or the sale is a direct sale to the owner (§ 18-44-115(a)(8)). Commercial real estate (nonresidential, or five or more units): a subcontractor, service provider, material supplier, or laborer must give written notice that it is entitled to payment but has not been paid (§ 18-44-115(b)(4)). | Residential: before work begins (§ 18-44-115(a)(3)). Commercial: before 75 days have elapsed from the time the labor was supplied or the materials furnished (§ 18-44-115(b)(5)(A)). | Residential: the owner, the owner's authorized agent, or the owner's registered agent, by personal delivery or certified mail. Commercial: the owner, the owner's authorized agent, or the owner's registered agent, and the contractor. | Residential: no claimant has a lien unless the owner received at least one copy of the notice, and a residential contractor that fails to give it has no lien (§ 18-44-115(a)(4), (a)(5)(C)). A notice given by another claimant after work begins secures only work supplied after it (§ 18-44-115(a)(5)(B)(ii)). Commercial: no lien for the subcontractor, service provider, material supplier, or laborer (§ 18-44-115(b)(4)). | Ark. Code § 18-44-115 ‡ |
| California | Yes, from every claimant except laborers. A direct contractor gives notice only to the construction lender. | 20 days after the claimant first furnished work on the work of improvement. | Owner or reputed owner, direct contractor or reputed direct contractor, construction lender or reputed construction lender if any. | Late notice preserves rights only for work performed in the 20 days before service and thereafter. Compliance is a necessary prerequisite to a valid lien or stop payment notice. | Cal. Civ. Code §§ 8200, 8204 |
| Colorado | No preliminary notice. A notice of intent is required shortly before the lien statement is filed. | At least 10 days before filing the lien statement with the county clerk and recorder. | Owner or reputed owner or the owner's agent, and the principal or prime contractor or agent. | The lien is not preserved. An affidavit of service must be recorded with the statement. | C.R.S. § 38-22-109(3) |
| Connecticut | Yes, from any person other than the original contractor or a subcontractor whose written contract with the original contractor was assented to in writing by the other party to the original contract. | After commencing, and not later than 90 days after ceasing, to furnish materials or render services. | Owner of the building, lot, or plot of land, and the original contractor. The original contractor is entitled to notice only if it lodged an affidavit with the town clerk within 15 days after commencing work. With two or more owners or original contractors, each must be served. | No entitlement to claim the mechanic's lien. | Conn. Gen. Stat. § 49-35 |
| Delaware | No preliminary notice as a condition of the lien. | Not applicable. | Not applicable. | Not applicable; the operative deadlines are for filing the statement of claim. | 25 Del. C. §§ 2702, 2711 |
| Florida | Yes, from any lienor not in privity with the owner, excluding laborers. | Before commencing, or not later than 45 days after commencing, to furnish labor, services, or materials, and in any event before the owner's final payment after the contractor furnishes the final payment affidavit. | Owner. A sub-subcontractor or a materialman to a subcontractor or sub-subcontractor must also serve the contractor, and a materialman to a sub-subcontractor must also serve the subcontractor if it knows the subcontractor's name and address. If the owner's notice of commencement designates another person to receive a copy, that person must be served too, but missing that copy does not invalidate the lien. | Failure to serve, or to serve timely, is a complete defense to enforcement of a lien by any person. | Fla. Stat. § 713.06(2)(a), (b) |
| Georgia | Conditional. Required of a claimant without privity of contract with the contractor, and only where a notice of commencement has been filed. | Within 30 days from filing of the notice of commencement or 30 days following first delivery of labor, services, or materials, whichever is later. | Owner or agent of the owner, and the contractor, at the addresses in the notice of commencement. | The lien is not made good. | O.C.G.A. § 44-14-361.5 ‡ |
| Hawaii | No preliminary notice as a condition of the lien. | Not applicable. | Not applicable. | Not applicable. A lien is claimed by filing an Application for a Lien and a Notice of Lien in circuit court within 45 days after the date of completion, § 507-43(a), (b). | HRS § 507-43 |
| Idaho | No general preliminary notice. A general contractor must give a residential disclosure statement before entering a contract over $2,000 with a homeowner or residential purchaser. | Prior to entering the contract. | Homeowner or residential purchaser. | Failure is an unlawful and deceptive act under the Idaho Consumer Protection Act, § 45-525(4). A claim of lien for work subject to § 45-525 must also include the proof of disclosure and acknowledgment of receipt, § 45-507(3)(e). | Idaho Code §§ 45-525, 45-507(3)(e) |
| Illinois | Yes, for subcontractors and parties furnishing labor or materials, § 60/24. On an existing owner-occupied single family residence, a subcontractor must also notify the occupant, § 60/21(c). A separate contractor notice about sworn statements applies to owner-occupied single-family residences, § 60/5(b). | Within 90 days after completion of the work, or after completion of extra work or final delivery of extra material. Residential occupant notice: within 60 days from first furnishing. A later notice preserves the lien only to the extent the owner has not been prejudiced by payments made before receiving it. | Owner of record or the owner's agent, architect, or superintendent, and the lending agency if known. Residential occupant notice: the occupant or the occupant's agent, personally or by certified mail, return receipt requested. | A subcontractor may file and enforce its lien if it is not paid within 10 days after its notice is served, § 60/28. An owner is not liable to a claimant left off the sworn statement, or for more than the amount stated there, unless the claimant notified the owner before the owner paid the contractor, § 60/27. Notice is unnecessary where the contractor's or subcontractor's sworn statement already gave the owner notice of the amount due and to whom due. | 770 ILCS 60/5, 60/21(c), 60/24, 60/27, 60/28 |
| Indiana | Conditional, on owner-occupied one and two family dwellings only. No general commercial preliminary notice. | 30 days from first delivery or labor for alteration or repair; 60 days for original construction, which must also be filed with the county recorder. | Owner of the real estate; for original construction, also the county recorder's office. | Furnishing the notice is a condition precedent to the right to acquire a lien. | Ind. Code § 32-28-3-1(h), (i) |
| Iowa | Yes. Residential requires a preliminary notice posted to the state registry. Commercial requires a one-time notice from anyone furnishing to a subcontractor. | Residential: no day count. A notice posted before the balance due is paid to the general contractor or owner-builder covers all of the subcontractor's labor and materials, but the lien is enforceable only up to the balance due when the notice is posted. A notice of commencement must be on the registry first. Commercial: within 30 days of first furnishing. | Residential: the Mechanics' Notice and Lien Registry, which then notifies the owner. Commercial: the general contractor or owner-builder. | Residential: no lien and no remedy under the chapter. Commercial: no lien. | Iowa Code §§ 572.13B, 572.33 |
| Kansas | Conditional, for improvement of residential property. A warning statement is required. | Before claiming the lien; an affidavit that the warning statement was given must be attached to the lien statement. | Owner. | No lien. A lien on residential property may be claimed only if the claimant mailed the warning statement to an owner, or holds a statement signed by an owner that the warning was given, § 60-1103a(b). The owner's exposure beyond the contract price is limited to payments made after the owner received the warning, § 60-1103(d)(2). No warning is required where the total claim is $250 or less, § 60-1103a(d). | K.S.A. §§ 60-1103, 60-1103a |
| Kentucky | Yes, from a claimant who did not contract directly with the owner, the owner's agent, or the lessee. The deadline depends on the size of the claim and the type of property. | After the last item of material or labor is furnished: 75 days on claims of less than $1,000, and 120 days on claims of more than $1,000. On an owner-occupied single or double family dwelling, 75 days regardless of amount. | Owner, the owner's authorized agent, or the lessee, if applicable. Proof of mailing to the owner's last known address is sufficient. | No lien. On an owner-occupied dwelling, the lien also does not reach amounts the owner paid before receiving the notice. | KRS § 376.010(4), (5) |
| Louisiana | Limited. There is no general preliminary notice. Specific notices apply to professional consultants not hired by the owner, to lessors of equipment, and to sellers of materials to a subcontractor (§ 9:4804). On residential work with no timely notice of contract, an optional notice of nonpayment to the owner at least 10 days before filing extends the filing period to 70 days (§ 9:4822(D)). | Professional consultants: within 30 days after being engaged. Lessors: within 30 days after the leased equipment is first placed at the site. Sellers to a subcontractor: no later than 75 days after the last day of the month in which the materials were delivered, and only if a notice of contract was timely filed. | Professional consultants: the owner. Lessors: the contractor, and also the owner if a notice of contract was timely filed. Sellers to a subcontractor: both the owner and the contractor. | Professional consultants and sellers to a subcontractor: no claim or privilege. Lessors: a late notice limits the claim to rent accruing after the notice is given. | La. R.S. §§ 9:4804, 9:4822(D) |
| Maine | No required preliminary notice. A claimant without a contract with the owner may give the owner an optional written notice that limits the owner's payment defense (§ 3255(3)). | No deadline. The notice fixes the cap at the balance the owner owes its own contractor when the owner receives it. | Owner, or the owner's known agent where the property is located if the owner lives elsewhere. | Nothing as to the lien's existence. For a claimant without a contract with the owner, the lien cannot exceed the balance the owner owes its own contractor when the owner receives the notice or is served in a lien action, whichever is first. This limit does not apply to business, commercial, or industrial premises unless the owner resides there. Separately, that claimant must record a sworn statement within 90 days after ceasing work and mail the owner a copy, or the lien is dissolved (§ 3253). | 10 M.R.S. §§ 3253, 3255(3) |
| Maryland | Yes, from subcontractors. On a single family dwelling being built on the owner's land for the owner's own residence, there is also no lien if the owner paid the contractor in full before receiving the notice, and the lien cannot exceed what the owner still owes under the contract when the notice is given. | Within 120 days after doing the work or furnishing the materials. | Owner or the owner's agent, by registered or certified mail with return receipt or personal delivery. | A subcontractor who does not give notice is not entitled to a lien. | Md. Code, Real Prop. § 9-104 |
| Massachusetts | Conditional. A notice of identification applies to a claimant with no direct contract with the original contractor. | Within 30 days of commencement of performance, by certified mail, return receipt requested. | Original contractor. | Without it, the lien cannot exceed the amount due or to become due under the subcontract between the original contractor and the subcontractor whose work includes the claimant's work, as of the date the claimant files its notice of contract. | M.G.L. c. 254, § 4 |
| Michigan | Yes, from subcontractors and suppliers. A contractor with a direct owner or lessee contract is exempt. Laborers give a separate notice tied to unpaid wages and fringe benefits. | Within 20 days after furnishing the first labor or material. | The designee and the general contractor named in the notice of commencement, or the owner or lessee if no designee is named. | Late service does not defeat rights for work after the notice. For earlier work, it defeats rights only to the extent the owner or lessee paid the contractor under a contractor's sworn statement or a lien waiver. | MCL § 570.1109 |
| Minnesota | Yes, with major exceptions. A contractor that uses subcontractors or suppliers gives a contractor notice, and subcontractors and suppliers give a separate prelien notice. Neither applies to a wholly residential improvement with more than four family units. Neither applies to nonagricultural property in whole or partly nonresidential use where the work adds more than 5,000 total usable square feet of floor space, the existing property already has more than 5,000, or the work is site work on property over 5,000 square feet (§ 514.011, subds. 4b, 4c). | Contractor: in the written contract with the owner, with a copy to the owner. If there is no written contract, a separate notice within 10 days after the work is agreed upon. Subcontractor: not later than 45 days after first furnishing labor, skill, or materials. | Owner. | Contractor: no lien and no remedy under the chapter. Subcontractor: the notice is a necessary prerequisite to the validity of any claim or lien. A claimant who made a good faith effort to comply does not lose the lien for failing to comply strictly, unless the owner or another lien claimant proves damage as a direct result. | Minn. Stat. § 514.011 |
| Mississippi | Yes, from a claimant with no contract with the contractor, or with the owner where there is no contractor. This notice does not apply to single-family residential construction. There, a subcontractor, supplier, or design professional with no contract with the owner gives the owner a pre-lien notice instead. | Within 30 days following the first delivery of labor, services, or materials to the property. Single-family residential: at least 10 days before filing the claim of lien. | The contractor, or the owner if there is no contractor, by e-mail with a confirmed receipt, registered or certified mail, or statutory overnight delivery. Single-family residential: the owner, by any reliable means of delivery. | The claimant forfeits its right to a lien. Single-family residential: the pre-lien notice is a condition precedent to the lien, and the owner's payments to the contractor before receiving it are an absolute defense to the extent paid. | Miss. Code §§ 85-7-407(2), 85-7-409 ‡ |
| Missouri | Yes. Every original contractor gives a statutory notice under § 429.012, except on new residences where the buyer has title insurance lien protection. Every other claimant gives the owner 10 days' notice before filing a lien under § 429.100. Residential work has added rules in §§ 429.013 and 429.016. | Original contractor: at contract execution, when materials are delivered, when work commences, or with the first invoice, and in all cases before receiving payment in any form. Other claimants: at least 10 days before filing the lien. | Original contractor: the person with whom the contract is made, or the owner if there is no contract. Other claimants: the owner, owners, or agent. | Original contractor: compliance is a condition precedent to the creation, existence, or validity of that contractor's mechanic's lien. Other claimants: the statute requires the 10-day notice of anyone except the original contractor who wishes to use the lien statute. | Mo. Rev. Stat. §§ 429.012, 429.100 |
| Montana | Yes, with broad exceptions. Original contractors, wage laborers, dwellings for five or more families, and partly or wholly commercial improvements are all exempt. | Not later than 20 days after services or materials are first furnished. 45 days where a regulated lender funds the payment, excluding an owner-occupied residence. | Contracting owner, by certified mail or personal delivery with written acknowledgment. A copy must also be filed with the county clerk and recorder within 5 business days after the notice is given. | Late notice makes the lien enforceable only for services or materials furnished within the 20 days before the notice is given, or 45 days under the lender rule in § 71-3-531(4). No lien may be claimed unless the notice was sent by certified mail or delivered personally, and an unexpired copy is on file with the clerk and recorder when the lien is filed. | Mont. Code § 71-3-531 |
| Nebraska | No. The notice of right to assert a lien is expressly permissive. | Any time after entering the contract, at the claimant's option. | Contracting owner. | Nothing as to the existence of the lien. The section applies only where the contracting owner is a protected party, generally an individual who occupies or intends to occupy residential real estate of four or fewer units. Against that owner, a subcontractor's or supplier's lien is capped at what remains unpaid on the prime contract when the owner receives the notice, so the owner's good faith payments before then reduce it. | Neb. Rev. Stat. §§ 52-135, 52-136 |
| Nevada | Yes, from every lien claimant other than one performing only labor. Prime contractors and anyone contracting or selling directly to the owner are exempt. | No deadline. May be given at any time after first delivery of material or performance of work. | Owner, in person or by certified mail; a copy to the prime contractor for information only. | No lien may be perfected or enforced unless the notice has been given. The notice protects only the 31 days before it is given, plus everything after. | NRS § 108.245 |
| New Hampshire | Yes, for a person whose contract is with an agent, contractor, or subcontractor of the owner. The written notice is the condition of that person's lien on the property. | Before performing the labor or furnishing the material, for a full lien. Notice may also be given afterward, but the lien is then limited to the amount due or later due to the contractor. A claimant who gives notice must also give the owner a written account as often as once in 30 days. | Owner, or the person having charge of the property. On a construction mortgage, a separate notice also goes to the construction lender within 15 business days, though missing that one does not alone invalidate the lien. | No lien without the written notice. A notice given after the work limits the lien to the amount then due or later due to the contractor, agent, or subcontractor of the owner. | RSA §§ 447:5, 447:6, 447:8, 447:12-b |
| New Jersey | Commercial: no. The Notice of Unpaid Balance and Right to File Lien is optional and affects priority, not validity. Residential: yes. Filing and serving it, and serving a demand for arbitration, are conditions precedent to any lien under a residential construction contract. | Commercial: within 90 days after the last work, services, material, or equipment, and before the conveyance, lease, or mortgage it is meant to outrank is recorded. Residential: within 60 days after the last work, services, material, or equipment for which payment is claimed, with a demand for arbitration served within 10 days of filing unless the parties agreed in writing to another dispute resolution method. | County clerk. Commercial: no service required. Residential: also served on the owner and any contractor and subcontractor against whom the claim is asserted, in the manner a lien claim is served under § 2A:44A-7. | Commercial: loss of priority over a conveyance, lease, or mortgage recorded before the lien claim, not loss of the lien. Residential: no lien may be filed. | N.J.S.A. §§ 2A:44A-20, 2A:44A-21 |
| New Mexico | Conditional. Applies to claims over $5,000, and does not apply to residential property of four or fewer dwelling units, to original contractors, or to those contracting directly with the original contractor. | Not more than 60 days after initially furnishing work or materials. | Owner or reputed owner, or the original contractor if any, by certified mail with return receipt, facsimile with acknowledgement, or personal delivery. | A lien over $5,000 may not be enforced by action or otherwise without the notice. A late notice is allowed, but the lien then applies only to work performed or materials furnished on or after the date 30 days before the notice was given. | N.M. Stat. § 48-2-2.1 |
| New York | No preliminary notice. | Not applicable. | Not applicable. | Not applicable; the operative deadline is filing the notice of lien. | N.Y. Lien Law § 10 |
| North Carolina | Yes, on projects that require a lien agent. Delivered to the lien agent rather than to the owner. The owner must designate a lien agent where the costs of the undertaking are $40,000 or more, except for improvements to an existing single-family residence occupied by the owner or an accessory building to it. | No later than 15 days after the first furnishing of labor or materials by the potential lien claimant. A later notice still preserves the right to perfect if the lien agent receives it before a conveyance to a bona fide purchaser is recorded. | The designated lien agent. | Missing the 15-day window does not by itself defeat the lien. The claimant cannot perfect once a conveyance to a bona fide purchaser who is not an affiliate, relative, or insider of the owner is recorded before the lien agent receives the notice or the lien is perfected. An unperfected claim is also subordinate to a mortgage or deed of trust recorded before the notice is received, unless the lender is an affiliate, relative, or insider of the owner. None of this applies if the lien agent's contact information was neither posted nor provided on request. | N.C. Gen. Stat. §§ 44A-11.1, 44A-11.2 |
| North Dakota | No preliminary notice. Written notice that a lien will be claimed is required before recording. | At least 10 days before recording the construction lien, by certified mail. | Legal or equitable owner of the real estate. | The statute states no separate penalty. Under § 35-27-13, a lien is perfected by recording only by a claimant "having complied with the provisions of this chapter," which includes this notice. | N.D. Cent. Code § 35-27-02(4) |
| Ohio | Conditional. Subcontractors and material suppliers must serve it only if a notice of commencement was recorded (§ 1311.05(A), (H)). Original contractors and laborers are exempt. The section does not apply to a home construction contract as defined in § 1311.011 (§ 1311.05(E)). | Within 21 days after performing the first labor or work or furnishing the first materials. | The owner's, part owner's, or lessee's designee named in the notice of commencement, or the owner if no designee is named, and the original contractor, at the addresses in that notice. A party in direct contract with the original contractor need not serve the original contractor, and a supplier in direct contract with the owner need not serve the owner. | A late notice preserves rights only for the 21 days immediately preceding service and thereafter, and does not revive any prior lien rights. | Ohio Rev. Code § 1311.05 |
| Oklahoma | Yes, from any claimant other than an original contractor. Exempt: residential projects of four or fewer dwelling units, none occupied by an owner, and aggregate claims under $10,000. Neither exemption applies to a lien on property occupied as a dwelling by an owner (§ 142.6(B)(1), (B)(3)). | No later than 75 days after the last date of supply of material, services, labor, or equipment. | The original contractor and an owner of the property, at their last known addresses. | The portion of the lien claim for which no notice was sent is invalid and unenforceable (§ 142.6(D)). One compliant notice protects lien rights for all later supply on the project. | Okla. Stat. tit. 42, § 142.6 |
| Oregon | Yes, from anyone not furnishing at the owner's request (§ 87.021(1)). On a commercial improvement, a person who performs labor, provides labor and material, or rents equipment need not give it, but a supplier of materials only still must (§ 87.021(3)(b)). Commercial means any structure other than an owner-occupied residence of four or fewer units. | May be given at any time during the improvement, but protects only what was provided after a date eight days, excluding weekends and holidays, before delivery or mailing. | Owner of the site. | Everything furnished before the eight business day lookback is unprotected by that notice. | ORS § 87.021 |
| Pennsylvania | Subcontractors only, two separate notices. A Notice of Furnishing is required only on a searchable project, an improvement costing at least $1,500,000, and only if the owner filed and posted a Notice of Commencement (§ 1501.3(b)). A formal notice of intention is required before any subcontractor lien claim (§ 1501(b.1)). | Notice of Furnishing: within 45 days after first performing work or services or first providing materials at the job site. Formal notice of intention: at least 30 days before the claim is filed. | Notice of Furnishing: the State Construction Notices Directory. Formal notice: the owner. | A subcontractor that fails to substantially comply with the Notice of Furnishing rule forfeits the right to file a lien claim (§ 1501.3(c)). No claim by a subcontractor is valid without the formal notice of intention (§ 1501(b.1)). | 49 P.S. §§ 1501, 1501.3; § 1201(18) |
| Rhode Island | Yes, from any person claiming a mechanics lien (§ 34-28-4). A contractor dealing directly with the owner, other than a material supplier, must also give the owner a notice of possible mechanic's lien before starting work, in the written contract or by certified mail, or it cannot claim a lien (§ 34-28-4.1). | Mail before or within 200 days after doing the work or furnishing the materials, and file a copy in the land evidence records of the city or town within the same 200 days. | Owner of record of the land at the time of mailing, or the lessee or tenant where the lien is against that interest, by prepaid registered or certified mail with return receipt. | The lien is void and wholly lost. A timely notice covers only work or materials furnished in the 200 days before filing and after. If the mailed notice comes back undelivered, the lien is void unless the claimant files the notice with the returned envelope within 30 days after the return and no more than 200 days after mailing. | R.I. Gen. Laws §§ 34-28-4, 34-28-4.1 |
| South Carolina | Conditional. A notice of furnishing applies to sub-subcontractors and suppliers to subcontractors, and only where a notice of project commencement was filed. | No deadline is stated. Once the contractor receives the notice, its later payments to the subcontractor do not reduce what the claimant can recover. The notice must state the dates the first and last item was furnished or scheduled. | The contractor, by certified or registered mail. | The lien is capped at the amount the contractor owes the subcontractor rather than eliminated. Absent a notice of project commencement, the cap provision does not apply at all. | S.C. Code §§ 29-5-20(B), 29-5-23 |
| South Dakota | Conditional. Applies to sub-subcontractors and suppliers to subcontractors, and only where a notice of project commencement was filed. | Not later than 60 days after doing the last of the work or furnishing the last item. | The contractor identified in the notice of project commencement, by certified or registered mail, with a copy to the owner of record. | The claimant may not extend the lien by filing a lien statement under § 44-9-15, so the lien ceases 120 days after the last work. The post office receipt for mailing the notice must be attached to the lien and filed with the register of deeds. | SDCL § 44-9-53 |
| Tennessee | Yes, a notice of nonpayment, from every remote contractor whose account is unpaid, except on one, two, three, and four family residential units. | Within 90 days of the last day of each month within which work or labor was provided or materials furnished. | The owner and the prime contractor in contractual privity with the remote contractor. | A remote contractor who fails to comply has no right to claim a lien under the chapter, except as to retainage held to guarantee its performance. | Tenn. Code Ann. § 66-11-145 ‡ |
| Texas | Yes, from every claimant other than an original contractor. | Non-residential: not later than the 15th day of the third month after the month during which the labor or materials were provided. Residential: the 15th day of the second month. | The owner or reputed owner and the original contractor. | The lien is not valid. | Tex. Prop. Code § 53.056 |
| Utah | Yes, from any person who wants to claim a construction lien. Filed on a registry, not mailed. | No later than 20 days after the day the person commences providing construction work. | The State Construction Registry. | A person who never files may not claim a construction lien, § 38-1a-501(1)(e). A late notice may still be filed, but it protects nothing provided before the fifth day after filing, § 38-1a-501(1)(c). A notice filed more than 10 days after a notice of completion has no effect, § 38-1a-501(1)(d). | Utah Code § 38-1a-501 |
| Vermont | Yes, for anyone without a contract with the owner. A subcontractor or supplier has a lien by giving the owner written notice that it will claim one. | No fixed deadline. The notice must include the date payment is due, if known. | The owner, or the owner's agent having charge of the property. | The lien is given by the notice. It extends only to the portions of the contract price remaining unpaid when the notice is received, § 1921(b). | 9 V.S.A. §§ 1921(b), 1923 |
| Virginia | Only on one- or two-family homes whose building permit names a mechanics' lien agent. There, a lien claimant must notify the lien agent. Otherwise no preliminary notice is a condition of the lien. A separate optional notice under § 43-11 can make the owner or general contractor personally liable. | Lien agent notice: within 30 days after first performing labor or furnishing material, or within 30 days after the permit issues if work started before the permit, § 43-4.01(C). Optional § 43-11 notice: a first notice at any time, then a sworn account no later than 30 days after the building is completed or work on it otherwise ends. | The mechanics' lien agent named on the building permit, for the residential notice. For the optional § 43-11 notices, the owner or agent and the general contractor, or the general contractor alone. | On a covered home, a late lien agent notice limits the lien to labor and materials furnished on or after the day the notice is given. Skipping the optional § 43-11 notices forgoes personal liability of the owner or general contractor. | Va. Code §§ 43-4, 43-4.01, 43-11 |
| Washington | Yes, with exemptions for those contracting directly with the owner, laborers, and subcontractors contracting directly with the prime, subject to a narrow residential repair exception. | No fixed deadline. The notice protects what was supplied not more than 60 days before it is mailed or served, shortened to 10 days for a new single-family residence. | The owner or reputed owner. Also the prime contractor, if the prime has complied with RCW 19.27.095, 60.04.230, and 60.04.261, unless the claimant contracted directly with the prime. | Everything furnished before the 60 day lookback, or 10 day lookback on a new single-family residence, is unprotected. | RCW § 60.04.031 |
| West Virginia | No, as a precondition. A preliminary notice to the owner is permitted and changes a later account-filing obligation. | Before commencing work or furnishing materials. | Owner of the building or structure. | Nothing as to the lien. A claimant who gave the notice need not file its account and notice with the owner within 60 days after its last work, unless the owner demands it in writing within those 60 days. | W. Va. Code § 38-2-20 |
| Wisconsin | Only on wholly residential work that provides or adds 4 or fewer family living units, § 779.02(1)(c). On those jobs, yes from subcontractors and suppliers, and the prime contractor has a separate notice duty to the owner. No notice is required on partly or wholly nonresidential work. | Within 60 days after first performing, furnishing, or procuring labor, services, materials, plans, or specifications. | The owner or authorized agent, at the last known post office address, in two signed copies. The owner passes a copy to any construction lender within 10 days. | No lien on the land or improvement without the notice. A late but otherwise proper notice supports a lien only for work and materials furnished after the owner actually receives it, § 779.02(3). | Wis. Stat. § 779.02(1), (2), (3) |
| Wyoming | Yes, from contractors, subcontractors, and materialmen alike. | Contractor: before receiving any payment from the owner, including advances. Subcontractor or materialman: within 30 days after first providing services or materials. | The record owner or agent. Subcontractors and materialmen also copy the contractor they are working for. | Failure to send the notice within the time specified bars the right to assert a lien. | Wyo. Stat. §§ 29-2-112, 29-2-113 |
By state. One page each, with the same figures for a single state:
How to read the markers. Rows without a marker were verified against the state’s own official statute text on a government source for this update. Rows marked ‡ were verified against a published reproduction of the official code rather than the state’s own site, because the state publishes its code through a commercial provider. Treat every row, and especially a ‡ row, as a pointer to the law, not as a statement of it.
What does this page not cover, and when do you need a lawyer?
This page covers preliminary and pre-lien notice deadlines and recipients only. It does not cover mechanics lien filing deadlines, lien enforcement or foreclosure windows, payment bond claim notice, public project claim procedures, or the content requirements of the notice forms themselves beyond the recipients and delivery method.
Several other limits are worth stating plainly.
Statutes change, and lien law is amended more often than most people expect. Texas rewrote its derivative claimant notice effective January 1, 2022. Pennsylvania created the State Construction Notices Directory by a 2014 amendment, and the state announced it was operating in March 2017. Iowa moved to a registry model in 2012 and 2013. Ohio shortened the life of a recorded notice of commencement from six years to four, effective September 30, 2025.
Project type changes the answer inside a single state. Residential and commercial rules diverge in Montana, Oregon, Oklahoma, New Mexico, Indiana, Iowa, Tennessee, and Texas, among others. Public projects usually run on a different statutory scheme entirely, often a bond claim rather than a lien. The number of dwelling units, whether the owner occupies the property, and the dollar value of the project can each flip the requirement.
Where the notice of commencement controls, the statute is only half the answer. In Georgia, South Carolina, South Dakota, Ohio, Michigan, and Pennsylvania, the obligation and the recipient list depend on a document filed by someone else, which you have to find first.
Get a lawyer licensed in the relevant state when the amount at issue is material, when you have already missed a date and need to know what survives, when the ownership structure involves a ground lease, a receivership, or a tenant improvement, or when a court has construed a term in your state in a way the statute’s plain text does not reveal. Reading a statute correctly is not the same as knowing how that state’s courts have applied it.
How do construction teams keep preliminary notice deadlines from slipping?
The firms that do not miss these deadlines treat the notice as an output of onboarding a project, not as a task someone remembers. The trigger is the same everywhere: the moment a new job is set up and a first-furnishing date exists, the clock for that jurisdiction starts, and the notice either goes out on a schedule or it does not go out.
Three failure modes account for most of the misses. The first is a date that lives in one person’s head, usually the credit manager who knows which states are 20 days and which are 45. The second is a first-furnishing date that nobody recorded, so the clock cannot be calculated even by someone who knows the rule. The third is proof of service that was never filed with the notice, which turns a compliant notice into an unprovable one two years later when it matters.
Contracts Connected is built for that third problem in particular. Every document is tagged to the contract, the project, and the requirement it satisfies the moment it enters the system, so the notice and its return receipt or registry confirmation stay attached to the job rather than scattered across an inbox. Our co-founder ran a large federal general contracting firm for 15 years, about 100,000 documents a year.
- Preliminary notice template, 50-state pack→
- Payment bond requirements by state→
- Subcontractor compliance automation→
Frequently asked questions
What is a preliminary notice in construction?
A preliminary notice is a written notice a contractor, subcontractor, or supplier sends near the start of a construction project to tell the property owner and others that the sender is furnishing labor or materials and may claim a mechanics lien if it is not paid. It is not a lien and it is not a claim of nonpayment. In most states that require one, sending it on time is a precondition to having lien rights at all.
Which states require a preliminary notice to preserve lien rights?
Roughly half the states require some form of notice near the start of work, and the design varies enough that state-by-state checking is the only safe method. Arizona, California, Michigan, Ohio, Utah, and Montana are among the states with a true early-stage deadline running from first furnishing. Others, including Colorado and North Dakota, require notice only shortly before a lien is filed. A few, including New York and Delaware, require no preliminary notice at all.
Is the preliminary notice deadline measured from first furnishing or last furnishing?
Most states measure from first furnishing of labor or materials, which is why the notice is called preliminary. Several do not. Oklahoma measures 75 days from the last date of supply. Texas uses a monthly cadence tied to the month the labor or materials were provided. Illinois runs 90 days from completion of the claimant’s work. Reading the wrong end of the job into the statute is one of the most common ways firms lose the right.
Does a general contractor have to send a preliminary notice?
Usually not, because most statutes only require notice from claimants who have no direct contract with the owner. The owner already knows the general contractor is there. Arizona is the notable exception, requiring the notice from essentially every claimant. California requires a direct contractor to serve the construction lender, if there is one. Wyoming requires a contractor to send notice before receiving any payment, including advances. Missouri, Utah, and Rhode Island also put a notice duty on the contractor hired by the owner, Minnesota does when that contractor uses subcontractors or suppliers, and Arkansas does on residential work of four or fewer units.
What happens if you send a preliminary notice late?
It depends on the state, and the difference is large. In California, Arizona, Ohio, and New Mexico a late notice still works going forward but protects only the work performed in a short lookback window before service, so everything earlier is unsecured. Montana’s late notice reaches back 20 days, or 45 days on certain lender-funded work. In Utah a late notice protects only work provided from the fifth day after it is filed. In Florida, Maryland, and Wyoming, missing the deadline forfeits lien rights on that claim entirely. Send it late rather than not at all, but do not assume the lookback rule exists in your state.
Does sending a preliminary notice mean you are filing a lien?
No. A preliminary notice is informational and protective. Nevada’s statute says so directly in the required form text, telling the owner the notice is not a claim of nonpayment. Sending one on every job is normal commercial practice in states that require it, and treating it as an accusation is a misreading. The notice preserves an option. Whether the option is ever exercised is a separate decision made much later.