Mechanics Liens

Arizona Lien Law: Deadlines, Notices, Waivers and Bonds

The Arizona deadline to record a mechanics lien and the completion trigger that starts it, the suit deadline, the 20-day preliminary notice, lien waiver forms and the public works payment bond rule, with the statute for each.

On this page
  1. Arizona lien law at a glance
  2. Deadline to record an Arizona lien
  3. Deadline to sue to enforce an Arizona lien
  4. Arizona preliminary notice
  5. Arizona lien waivers
  6. Arizona public-work payment bonds
  7. Paperwork that goes with it
  8. See every state
  9. Frequently asked questions

In Arizona you record a lien within 120 days after completion of the improvement, or within 60 days after the owner records a notice of completion. You then have 6 months from recording the lien to file suit to enforce it.

Arizona lien law at a glance

Topic The rule in Arizona Statute
Record the lien 120 days after completion of the improvement; 60 days after the owner records a notice of completion A.R.S. §§ 33-993(A), 33-998(A)
Enforce it (suit) 6 months from recording the lien A.R.S. §§ 33-993(A), 33-998(A)
Preliminary notice Yes, and from essentially every claimant, including one contracting directly with the owner. Wage laborers exempt. Deadline: 20 days after first furnishing labor, professional services, materials, machinery, fixtures, or tools to the jobsite. Late notice preserves a lien only for what was furnished in the 20 days before service and thereafter. A.R.S. § 33-992.01
Lien waivers Statutory form: yes, four forms. Advance waiver by contract: void, Ariz. Rev. Stat. § 33-1008(A). Unconditional forms must print the warning in type at least as large as any other on the form. Ariz. Rev. Stat. § 33-1008
Public-work payment bonds Required on every contract for counties, cities, towns and districts unless a statute exempts it; over $100,000 for state agencies under the procurement code Ariz. Rev. Stat. §§ 34-222(A), 41-2574(A), 41-2535

Deadline to record an Arizona lien

In Arizona the deadline to record the lien is 120 days after completion of the improvement, or 60 days after the owner records a notice of completion. The statutes are A.R.S. §§ 33-993(A) and 33-998(A).

The trigger is completion of the improvement itself, not the day the crew demobilized. A credit manager who counts 90 days forward from demobilization is correct in Florida, Michigan and Washington, and wrong in Arizona and Tennessee, where the same 90 or 120 day period runs from completion of the improvement itself.

Arizona cuts its 120 day period to 60 days when the owner records a notice of completion under A.R.S. § 33-993(A).

Deadline to sue to enforce an Arizona lien

Recording the lien only preserves the claim. In Arizona the deadline to file suit is 6 months from recording the lien.

Arizona preliminary notice

Arizona calls it a preliminary notice. It requires the 20 day notice from essentially every claimant furnishing labor, professional services, materials, machinery, fixtures, or tools, including the party with a direct contract with the owner. Arizona is the notable exception to the usual rule that only claimants without a direct contract with the owner must send one. Wage laborers are exempt. The statute is A.R.S. § 33-992.01.

The deadline is 20 days after first furnishing. Arizona is one of the states with a true early-stage deadline running from first furnishing.

Arizona has the longest list of recipients: the owner or reputed owner, the original contractor or reputed contractor, the construction lender or reputed construction lender if any, and the person with whom the claimant contracted.

Arizona uses a 20-day lookback: send the notice late and you keep lien rights for work furnished in the 20 days before service and everything after, and you lose everything earlier.

Arizona lien waivers

Arizona is one of eleven states that prescribe a lien waiver form in their statutes, and one of five that prescribe all four forms, conditional and unconditional across progress and final payment (Ariz. Rev. Stat. § 33-1008). In most of the form states, a waiver that does not substantially follow the printed form is unenforceable.

Arizona requires the unconditional form to carry a warning, in type at least as large as the largest type on the document, reading that “This document is enforceable against you if you sign it, even if you have not been paid.”

Arizona is among the twenty-nine states where a statute voids or bars an advance waiver. The Arizona row reads: void, Ariz. Rev. Stat. § 33-1008(A). Arizona does not require notarization.

Arizona public-work payment bonds

On public work the bond replaces the lien. In Arizona a bond is required on every contract for counties, cities, towns and districts unless a statute exempts it. For state agencies it is over $100,000 under the procurement code. The statutes are Ariz. Rev. Stat. §§ 34-222(A), 41-2574(A) and 41-2535.

Several states require a bond on covered contracts of any size unless a waiver or exception applies, and Arizona does the same for local governments.

Paperwork that goes with it

Templates for the documents behind a Arizona claim:

See every state

The same four topics for all 50 states:

Frequently asked questions

How long do I have to record a mechanics lien in Arizona?

120 days after completion of the improvement, or 60 days after the owner records a notice of completion (A.R.S. § 33-993(A)).

Does Arizona require a preliminary notice?

Yes, within 20 days after first furnishing, from essentially every claimant, including one contracting directly with the owner. Wage laborers are exempt. A late notice preserves a lien only for what was furnished in the 20 days before service and thereafter (A.R.S. § 33-992.01).

Does Arizona have statutory lien waiver forms?

Yes, four forms, at Ariz. Rev. Stat. § 33-1008. The unconditional forms must print a warning in type at least as large as any other on the form. A contract term that waives lien rights in advance is void (§ 33-1008(A)).

When does a public project in Arizona need a payment bond?

A bond is required on every contract for counties, cities, towns and districts unless a statute exempts it. For state agencies it is over $100,000 under the procurement code.

Related: lien waiver software

This page is a summary of what four 50-state references say about Arizona, not legal advice. Check the statute, and a construction attorney licensed in Arizona, before relying on it for a specific job.

Contracts Connected is the Back-Office System (BOS) for construction.

See what it would take off your plate.

SOC 2 Type II · U.S. hosted · AI optional
Book a demo