In Nevada you record a lien within 90 days after the latest of completion of the work of improvement, your last delivery of material or equipment, or your last work. If a notice of completion is recorded and served, the deadline is 40 days after it. You then have 6 months from recording the notice of lien to file suit to enforce it.
Nevada lien law at a glance
| Topic | The rule in Nevada | Statute |
|---|---|---|
| Record the lien | 90 days after the latest of completion of the work of improvement, the claimant’s last delivery of material or equipment, or the claimant’s last work; or 40 days after a recorded and served notice of completion | NRS §§ 108.226(1), 108.233(1) |
| Enforce it (suit) | 6 months from recording the notice of lien | NRS §§ 108.226(1), 108.233(1) |
| Preliminary notice | Yes, from every lien claimant other than one performing only labor. Prime contractors and anyone contracting or selling directly to the owner are exempt. No deadline: it may be given at any time after first delivery of material or performance of work. No lien may be perfected or enforced unless the notice has been given. It protects only the 31 days before it is given, plus everything after. | NRS § 108.245 |
| Lien waivers | Statutory form: yes, four forms. Advance waiver by contract: void, NRS 108.2457(1). Any contract term impairing lien rights is void. | Nev. Rev. Stat. § 108.2457 |
| Public-work payment bonds | Over $100,000; payment bond of at least 50% of the contract amount; NDOT highway contracts fall under a separate statute that requires a bond on every contract but not necessarily a payment bond | Nev. Rev. Stat. §§ 339.025, 408.357 |
Deadline to record a Nevada lien
In Nevada the deadline to record the lien is 90 days after the latest of completion of the work of improvement, the claimant’s last delivery of material or equipment, or the claimant’s last work. If a notice of completion is recorded and served, the deadline is 40 days after it. The governing statutes are NRS §§ 108.226(1) and 108.233(1).
Nevada cuts 90 days to 40 under NRS § 108.226(1) when a notice of completion is recorded and served.
Deadline to sue to enforce a Nevada lien
Recording the lien only preserves the claim. In Nevada the deadline to file suit to enforce it is 6 months from recording the notice of lien. The statutes are NRS §§ 108.226(1) and 108.233(1).
Nevada preliminary notice
Nevada is one of the states that call it a notice of right to claim a lien or a notice of right to lien. It is required from every lien claimant other than one performing only labor. Prime contractors and anyone contracting or selling directly to the owner are exempt. The statute is NRS § 108.245.
Nevada sets no deadline. The notice may be given at any time after first delivery or performance, and it simply protects the 31 days before it was given plus everything after. Nevada’s 31-day lookback works this way by design rather than as a penalty. No lien may be perfected or enforced unless the notice has been given.
Send it to the owner in person or by certified mail, with a copy to the prime contractor for information only. Nevada’s statute says the notice “does not constitute a lien.” The form language it mandates tells the owner that the notice “is not a notice that the undersigned has not been or does not expect to be paid, but a notice required by law.”
Nevada lien waivers
Nevada is one of eleven states that prescribe a lien waiver form in their statutes. It is one of five (with Arizona, California, Michigan and Texas) that prescribe all four forms, conditional and unconditional across progress and final payment. The statute is Nev. Rev. Stat. § 108.2457. In most of the form states, a waiver that does not substantially follow the printed form is unenforceable, which means the release fails and the lien rights survive.
Nevada is among the twenty-nine states where a statute voids or bars a contract clause that waives lien rights before labor or materials are furnished or before payment is received. The Nevada row reads: void, NRS 108.2457(1). Any contract term impairing lien rights is void.
Nevada does not require notarization. Its waiver forms print no notary requirement. Many owners and lenders demand it anyway as a matter of contract, which is a business requirement rather than a statutory one.
Nevada public-work payment bonds
On public work the bond replaces the lien. In Nevada the threshold is over $100,000, with a payment bond of at least 50% of the contract amount. NDOT highway contracts fall under a separate statute that requires a bond on every contract but not necessarily a payment bond. The statutes are Nev. Rev. Stat. §§ 339.025 and 408.357.
Paperwork that goes with it
Templates for the documents behind a Nevada claim:
- Lien waiver, conditional progress (50-state pack)
- Lien waiver, unconditional progress (50-state pack)
- Lien waiver, conditional final (50-state pack)
- Lien waiver, unconditional final (50-state pack)
- Preliminary notice template (50-state)
- Notice of intent to lien template
- Statutory deadline tracker for lien claims
- Mechanics lien filing checklist, state by state
See every state
The same four topics for all 50 states:
- Mechanics lien deadlines by state
- Lien waiver requirements by state
- Payment bond requirements by state
- Preliminary notice deadlines by state
Frequently asked questions
How long do I have to record a mechanics lien in Nevada?
90 days after the latest of completion of the work of improvement, your last delivery of material or equipment, or your last work. If a notice of completion is recorded and served, it is 40 days after that notice. The statutes are NRS §§ 108.226(1) and 108.233(1).
Does Nevada require a preliminary notice?
Yes, from every lien claimant other than one performing only labor. Prime contractors and anyone contracting or selling directly to the owner are exempt. There is no deadline, but it protects only the 31 days before it is given, plus everything after (NRS § 108.245).
Does Nevada have a statutory lien waiver form?
Yes. Nevada prescribes four forms, conditional and unconditional across progress and final payment, at Nev. Rev. Stat. § 108.2457. A contract term that waives lien rights in advance is void.
When does a public project in Nevada need a payment bond?
Over $100,000, with a payment bond of at least 50% of the contract amount (Nev. Rev. Stat. §§ 339.025, 408.357). NDOT highway contracts fall under a separate statute.