Every performance bond, payment bond, and surety vetting step a federal prime must clear before a shovel goes in the ground. CC Miller Act Bonding Requirements Checklist

Why federal primes need a Miller Act bonding checklist

If you’re a prime on a federal construction contract, the bonding conversation usually goes one of two ways. Either you’ve done it a dozen times and you’re just going through the motions, or you’re six weeks from award and your surety is asking for documents you haven’t pulled together yet. Either way, the Miller Act doesn’t care. The bond has to be in place before you touch a shovel.

The Miller Act requires a performance bond and a payment bond on every federal construction contract exceeding $150,000. That’s the rule in FAR 28.102-1. The reality is a lot messier. You’re coordinating with a surety whose underwriting limitation you may be bumping against, a contracting officer who won’t issue a notice to proceed until your executed bonds are in, and subs and suppliers who can ask you for a copy of your payment bond at any time. Miss any of those pieces and you’re not in compliance, even if you have bonds in hand.

The bond problems that cost primes money are paperwork misses: a price increase that never got its added coverage, or a bond dated before the contract, which the SF 25 forbids. Both are easy to catch if someone is looking.

This checklist walks you through 14 steps: the threshold test, both required bonds, surety vetting, bond delivery after award, added coverage on price increases, the payment bond copies subs and suppliers can ask for, and whether a federal agency or a state or local owner awarded the contract. It starts before you bid and runs through the project lifecycle as contract value changes. For the claim side, notice deadlines and who can sue, see our Miller Act bond requirements and claims guide.

This checklist can flag the gaps and keep you organized across 40 subs, but it can’t chase the bond paperwork down the chain on your behalf. Contracts Connected collects each sub’s bonds through the vendor portal with the rest of the compliance package, files them, and shows which subs are still missing one. That’s the part of this job nobody wants to own manually.

Who this checklist is for

  • Federal general contractors managing contracts above the $150,000 Miller Act threshold
  • Prime contractors responsible for bonding compliance from bid through closeout
  • 8(a) federal subs acting as primes on set-aside contracts requiring performance and payment bonds
  • Compliance officers preparing bid guarantees and bond packages for contracting officer review
  • Project administrators tracking added bond coverage and surety consents through contract modifications

The 14-step Miller Act bonding checklist

The checklist covers 14 steps every prime must complete from bid through project close.

  1. Confirm the contract’s anticipated value, with options, exceeds $150,000. Miller Act performance and payment bonds apply to federal construction contracts expected to exceed $150,000 (FAR 28.102-1). Under FAR 1.108(c), that test uses the final anticipated value, including all options and any ceiling or maximum, not the base year alone. A $120,000 base year with three $40,000 option years counts as $240,000 for this test. Over $35,000 and up to $150,000, FAR 28.102-1(b) still requires you to furnish one of the payment protections the contracting officer selects, such as a payment bond or an irrevocable letter of credit. The solicitation tells you which rule applies: FAR 52.228-15 means Miller Act bonds, and FAR 52.228-13 means alternative payment protection.
  2. Obtain a performance bond at 100% of the original contract price. The performance bond (SF 25) guarantees your completion obligations to the government. Its penal sum must equal 100% of the original contract price unless the contracting officer decides a lower amount is adequate (FAR 28.102-2). The original contract price is the award price without unexercised options, or the minimum-quantity price on an indefinite-quantity contract. On an IDIQ, that minimum is only the starting point, so read the solicitation’s bond clause for how each task order gets bonded. A bond in the wrong penal sum can be declined without advance notice (31 CFR 223.17(b)(6)), so match it to the award.
  3. Obtain a payment bond at 100% of the original contract price. The payment bond (SF 25-A) protects anyone who contracts with you, or with one of your subcontractors, to furnish labor or material for the job (40 U.S.C. 3133(b)). It stops there: a vendor to one of your suppliers, and anyone below your subs’ own subs and suppliers, has no claim on it. It must equal 100% of the original contract price unless the contracting officer finds that amount impractical in writing, and it can never be less than the performance bond (FAR 28.102-2). The two bonds are separate instruments, from the same surety or from different ones.
  4. Verify the surety is listed on Treasury Circular 570. Treasury Circular 570 lists the companies certified to write federal bonds. Treasury republishes it every August 1 and posts changes, such as new certifications and terminations, as they occur. A surety company must appear as a certified insurer, not only as a reinsurer, for the contracting officer to accept its bond (FAR 28.202; Circular 570). Individual sureties that pledge Treasury-eligible assets, and deposits such as an irrevocable letter of credit, are the other options (FAR 28.203, 28.204). Recheck the listing during the job: if Treasury removes your surety, the contracting officer can require a new bond.
  5. Check the penal sum against the surety’s underwriting limitation. Circular 570 shows each company’s underwriting limitation: the most it may carry alone on a single bond, 10% of its capital and surplus as Treasury figures it. It does not cap the bond. A larger bond is acceptable if other listed companies coinsure the excess, each within its own limit, or if the excess is reinsured on SF 273 and SF 274 (FAR 28.202(a)(2)). Treasury’s rule also lists SF 275 for Miller Act bonds (31 CFR 223.11(b)(1)(ii)). The contracting office generally wants the signed reinsurance agreements with the bonds. If the solicitation allows later filing, they are due within the time it sets, no more than 45 days after the bond is executed.
  6. Deliver bonds to the contracting officer after award and before work starts. The bonds must be dated the same day as the contract or later (SF 25), and they go to the contracting officer within the period the solicitation sets after award. Under the standard FAR 52.228-1 provision that period is 10 days after you receive the bond forms. No notice to proceed issues and no work starts until they are in (FAR 28.102-1(c)). Late bonds can get the contract terminated for default, and you pay any extra cost of buying the work elsewhere (FAR 52.228-1). Confirm receipt in writing.
  7. Capture bond number, issue date, and surety contact. Record the bond number, execution date, surety name, and the surety’s designated contact for claims and bond matters. This information goes in your project compliance binder and should be accessible to your project team without hunting through email chains.
  8. Track the added bond coverage on every modification that raises the price. When a modification raises the contract price, including each option the government exercises after award, the government can require added bond coverage, generally 100% of the increase (FAR 28.102-2, 52.228-15(b)(3)). The contracting officer directs it, either through the original surety on SF 1415 (Consent of Surety and Increase of Penalty) or through an additional bond. The FAR sets no fixed dollar or percentage trigger for this. If the additional bond comes from a different surety, the contracting officer also needs the original surety’s consent on SF 1414. When no added bond is required, that consent is still needed for out-of-scope work or a price change, up or down, of more than 25% or $50,000 (FAR 28.106-5). Time extensions alone need no surety paperwork. File the executed form with each modification.
  9. Keep a complete copy of the bond package the contracting officer accepted. The executed bonds go to the contracting officer and stay in the government’s contract file. Keep a full copy in your project file: the SF 25 and SF 25-A, the surety’s power of attorney, any SF 273, SF 274 or SF 275 reinsurance agreements, every SF 1414 or SF 1415, and the contracting officer’s acceptance or notice to proceed. Keep each project’s package separate, so anyone can pull it without asking where things are. Before sending electronically signed bonds, ask the contracting officer whether the agency accepts them. Some agencies accept them under FAR class deviations. GSA’s regulation still calls for manual signatures and a corporate seal, and GSA rescinded its own e-signature deviation for bonds in July 2026.
  10. Track the events that change bond coverage, not an expiration date. The SF 25 performance bond has no expiration date. It covers the original contract term, any time extensions the government grants, authorized modifications, and the life of any guaranty, such as the one-year warranty after final acceptance, with or without notice to the surety. A schedule slip does not need a surety extension endorsement. Two things do need action: a price increase where the contracting officer requires more coverage (item 8), and a surety that becomes unacceptable, for example after Treasury removes it from Circular 570, which obliges you to furnish added security (FAR 52.228-2). If an irrevocable letter of credit stands in for a surety, track its expiry too: the contracting officer can draw on it if no replacement arrives at least 30 days before it expires (FAR 52.228-2).
  11. Give a copy of the payment bond to any sub or supplier who asks. FAR 52.228-12 requires you to promptly give a copy of your Miller Act payment bond to any prospective subcontractor or supplier who asks for one. The contracting officer must also give the surety’s name and address, the penal amount, or a copy when a sub or supplier asks (FAR 28.106-6). No FAR rule makes you send a copy with each subcontract, but it is a good habit. It does not change the claim deadlines: the 90-day notice and one-year suit periods run from the claimant’s last day of labor or material.
  12. Confirm who awarded the contract: a federal agency, or a state, local, tribal or private owner. The Miller Act applies when a federal agency awards the contract for a federal public building or public work (40 U.S.C. 3131(b)). A state’s share of the cost does not add a state bond to it. When a state, city, county, tribe, nonprofit or private owner awards the contract, the Miller Act does not apply, even if federal grants or loans pay for the work (GE Supply v. USF&G, 6th Cir. 1993). The owner’s contract sets the bond terms. State and local owners follow the state’s Little Miller Act. Local governments and nonprofits spending federal grants must also meet 2 CFR 200.326: a 5% bid guarantee and 100% performance and payment bonds above the simplified acquisition threshold, unless the federal agency or pass-through entity accepts their own bonding policy. Federal-aid highways follow the state DOT’s FHWA-approved rules (23 CFR 635.110).
  13. Confirm bid bond was procured for the solicitation phase. The Miller Act does not require bid bonds, but FAR 28.101-1 requires a bid guarantee whenever the contract requires a performance bond, sealed bid or negotiated, unless the chief of the contracting office waives it. The solicitation sets the amount, at least 20% of the bid price and no more than $3 million, and construction needs a separate bid guarantee for each solicitation, not an annual bid bond. In sealed bidding, a missing or deficient bid guarantee gets the bid rejected unless a FAR 28.101-4(c) exception applies. Include the surety’s signed and dated power of attorney with the bid bond, because a missing one at bid opening is a responsiveness defect (FAR 28.101-3(d)).
  14. Keep bond records for 3 years after final payment, longer if a claim is open. If your contract includes FAR 52.215-2 or 52.214-26, FAR 4.703 requires you to keep contract records available for 3 years after final payment, longer for a terminated portion or while a claim, appeal or lawsuit is open. FAR does not list bonds by name, and the executed originals sit with the contracting officer, so keeping your bond copies, consents of surety and surety letters on the same clock is good practice. Start the clock at final payment, not closeout. Mark the date in your file, and think twice before shredding: the government can bring a Contract Disputes Act claim up to 6 years after it accrues (41 U.S.C. 7103(a)(4)(A)).

How to run the checklist

Run items 1, 4, 5, 12 and 13 before you bid, and line up items 2 and 3 with your surety. Deliver item 6 within the solicitation’s post-award window, and complete items 7 and 9 the day the contracting officer accepts the bonds. Return to items 8 and 10 every time a modification changes the price, handle item 11 whenever a sub or supplier asks, and recheck item 4 each August 1 and whenever Treasury posts a change. Item 14 is a calendar entry. Mark it and move on.

The Excel version includes a compliance percentage formula (=COUNTIF(D2:D15,TRUE)/14) so you can see how many of the 14 steps are done on each project.

Stop tracking Miller Act bonds manually

Fourteen steps on your own bonds, then the same paperwork again from every bonded sub. Contracts Connected collects each sub’s bonds through the vendor portal along with their COIs, W-9s and licenses, files them where you can find them, and shows which subs are still missing one. It reminds vendors Monday and Wednesday mornings until everything is in, so you stop chasing bonds by email.

For educational purposes. These templates, checklists, and trackers are practical starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.

Frequently asked questions about the miller Act bonding requirements checklist

What is the Miller Act?

The Miller Act is a federal statute (40 U.S.C. 3131-3134) that requires a performance bond and a payment bond on federal construction contracts. The statute’s text says $100,000, and FAR 28.102-1 sets the operative figure: contracts over $150,000. You deliver the bonds after award, within the window the solicitation sets, and before work starts. The performance bond protects the government’s interest in project completion. The payment bond protects subcontractors and suppliers who cannot file a mechanics lien on federal property because the government holds sovereign immunity against such claims.

Who is protected by a Miller Act payment bond?

The bond covers two tiers and no more. Tier one is anyone who contracted directly with the prime to furnish labor or material, including subcontractors, suppliers and laborers. Tier two is anyone who contracted directly with one of the prime’s subcontractors, and they must give the prime written notice within 90 days of their last labor or material (40 U.S.C. 3133(b)(2)). Anyone further down has no claim on the bond: not the subs or suppliers of a sub-subcontractor (J.W. Bateson Co. v. United States, 1978), and not a vendor that sold to a firm that only supplied material to the prime (Clifford F. MacEvoy Co. v. United States, 1944). Whether a firm that contracted with the prime counts as a subcontractor or a supplier depends on how substantial its share of the work is (F.D. Rich Co. v. United States, 1974).

How long do subcontractors have to file a Miller Act claim?

Only claimants who contracted with a subcontractor, and not with the prime, must give the prime written notice within 90 days of the last day they furnished labor or material (40 U.S.C. 3133(b)(2)), by a method that gives written third-party verification of delivery, or by service the way a U.S. marshal serves a summons. Subs and suppliers who contracted directly with the prime give no notice, but may not sue until 90 days after their last labor or material. Every claimant must sue within one year of the last day they furnished labor or material. Missing either deadline bars the claim. Some courts have interpreted these periods strictly, so do not assume informal notice or payment dispute correspondence substitutes for formal written notice.

What is Treasury Circular 570 and why does it matter?

Treasury Circular 570 is the U.S. Department of the Treasury’s list of companies approved to write surety bonds on federal contracts, republished every August 1 with changes posted as they occur. Each listed company has an underwriting limitation, the most it may carry on a single bond without coinsurance or reinsurance. It does not cap the bond amount: a company can write a larger bond if other certified companies coinsure or reinsure the excess. For a contract performed in the United States, a surety company that is not on Circular 570 is not acceptable, and the contracting officer will not accept its bond. Check the live listing at fiscal.treasury.gov, including interim changes, before you submit bonds.

What is a Little Miller Act?

A Little Miller Act is a state-level statute that mirrors the federal Miller Act and requires bonds on public works that the state or its local governments award. Every state has some version, though Vermont’s covers only its transportation projects, and thresholds, bond amounts and claim procedures vary widely. Several states require a bond on every covered contract, and where a statute names a dollar trigger it runs from $5,000 or less on some road and local contracts to over $500,000 for Virginia non-transportation work. A state Little Miller Act applies when the state or one of its local governments awards the contract, including projects paid with federal grants. A contract a federal agency awards follows only the federal Miller Act, even when a state shares the cost.

Are bid bonds required under the Miller Act?

No. The Miller Act covers performance and payment bonds only, and you deliver those after award, within the window the solicitation sets and before work starts. A bid guarantee, usually a bid bond, backs your promise to sign the contract and furnish the bonds if you win. FAR 28.101-1 requires one whenever the contract requires a performance bond, sealed bid or negotiated, unless the chief of the contracting office waives it. The amount is at least 20% of the bid price, capped at $3 million, and the requirement appears in the solicitation through FAR 52.228-1. What differs by method is the penalty for a defective one: rejection in sealed bidding, subject to the FAR 28.101-4(c) exceptions, and in negotiation, rejection when the award is made on initial proposals without discussions.

Where this document lives in the system
Back-Office System · Contracts Connected