What is the Miller Act?
The Miller Act is the federal law that requires a contractor to furnish a performance bond and a payment bond before being awarded a contract for the construction, alteration, or repair of a federal public building or public work. It is codified at 40 U.S.C. §§ 3131 to 3134 and implemented at FAR Subpart 28.1. The performance bond protects the government. The payment bond protects the people who supply labor and material on the job.
That split is the whole design. The government gets one bond guaranteeing the work gets finished. Subcontractors and suppliers get a separate bond they can sue on when they do not get paid, because they cannot place a mechanics lien on federal property. The payment bond is the substitute for the lien right that does not exist on federal land.
The volume of work this covers is not small. Federal agencies obligated roughly $51.1 billion on contracts under construction industry NAICS codes in fiscal year 2025, spread across 53,168 contract awards, according to USAspending.gov, the federal government’s official spending database (retrieved October 1, 2026). About 58 percent of those awards have total obligations above the $150,000 bonding threshold, and they carry about 99 percent of the money.
What contract amount triggers Miller Act bond requirements?
Bonds are required on federal construction contracts exceeding $150,000, which is the figure in FAR 28.102-1(a) and the number a contracting officer will apply. The underlying statute states a lower figure. Here is the actual text of 40 U.S.C. § 3131(b):
Before any contract of more than $100,000 is awarded for the construction, alteration, or repair of any public building or public work of the Federal Government, a person must furnish to the Government the following bonds, which become binding when the contract is awarded.
So the statute says $100,000 and the regulation says $150,000. Both are current. FAR 28.102-1(a), current through FAC 2026-01 (effective March 13, 2026), states that 40 U.S.C. chapter 31, subchapter III “requires performance and payment bonds for any construction contract exceeding $150,000.” The $150,000 figure has been in the FAR since October 1, 2010. The Government Accountability Office used the same $150,000 figure in its review of surety bond waivers, GAO-17-683R.
Agencies buying under a Revolutionary FAR Overhaul (RFO) class deviation, including DoD, GSA, and VA, apply the same rules under the same section numbers. The RFO version of Part 28 keeps sections 28.102-1, 28.102-2, and 28.202 and clause 52.228-15. It also keeps the $150,000 and $35,000 thresholds, the rule that the contracting officer picks two or more payment protections, and the push toward a letter of credit. The FAR Council’s proposed rule of September 18, 2026 (91 FR 59534) would write that text into the FAR without substantive change. It also asks whether every Part 52 clause should move to a new number series, so check the clause number printed in your contract.
Why does the statute say $100,000 when the FAR says $150,000?
Because Congress froze a regulatory adjustment in place instead of raising the statutory number. Most dollar thresholds in federal acquisition law are recalculated for inflation every five years under 41 U.S.C. § 1908. The Miller Act is carved out of that process, but the carve-out came with a grandfather clause. Section 1908(b)(2)(D) excludes the thresholds in sections 3131 through 3134 of title 40 from adjustment, “except any modification of any such dollar threshold made by regulation in effect on the date of the enactment of this subparagraph shall remain in effect.”
The practical consequence is worth understanding, because it runs opposite to how contractors usually think about federal thresholds. The regulatory figure already in place, $150,000, was preserved and continues to govern. It is also now locked. Unlike the simplified acquisition threshold, which climbs every five years with the Consumer Price Index, the Miller Act bonding threshold does not drift. A contractor who learned this number years ago still has the right number today, and will still have it after the next inflation adjustment cycle.
The date-stamped position as of September 30, 2026: the operative threshold is more than $150,000, and it is not scheduled to move. The October 2025 inflation adjustment did not touch it, and the 2026 RFO proposed rule keeps it.
What payment protection applies to federal construction contracts below the bond threshold?
Contracts greater than $35,000 but not greater than $150,000 still carry payment protection, just not necessarily a bond. Under FAR 28.102-1(b)(1), which implements 40 U.S.C. § 3132, the contracting officer selects two or more of the following and the contractor supplies one of them: a payment bond, an irrevocable letter of credit, a tripartite escrow agreement, certificates of deposit, or a deposit of the securities listed at FAR 28.204-1 and 28.204-2. The regulation directs the contracting officer to give “particular consideration to inclusion of an irrevocable letter of credit” among the choices offered. Section 3132 itself still sets this range at more than $25,000 and not more than $100,000. FAR inflation adjustments raised those figures to $35,000 and $150,000 between 2006 and 2015, and the Section 1908(b)(2)(D) grandfather clause keeps both in force.
Whichever protection is selected must equal 100 percent of the original contract price under FAR 28.102-2(c), unless the contracting officer determines a lesser amount is adequate to protect the government. That is the same default percentage that applies above the threshold. Below $35,000, the FAR imposes no payment protection requirement of this kind. If you are a sub or supplier on a small federal job, this is the first thing to check, because the remedy you are looking for may be a letter of credit or an escrow account rather than a bond, and the claim process is completely different.
How large do the performance and payment bonds have to be?
Both bonds are set at 100 percent of the original contract price. FAR 28.102-2(b)(1) sets the penal amount of the performance bond at 100 percent of the original contract price unless the contracting officer determines a lesser amount is adequate to protect the government. FAR 28.102-2(b)(2) sets the payment bond at 100 percent as well, unless the contracting officer makes a written determination supported by specific findings that this amount is impractical, and in no case may the payment bond be less than the performance bond.
“Original contract price” is a defined term in FAR 28.102-2(a), and it excludes the price of options unless they are exercised at the time of award. If the contract price goes up, the government secures additional protection by directing the contractor to increase the penal sum of the existing bond, obtain an additional bond, or furnish additional alternative payment protection.
Timing matters as much as amount. Under FAR 28.102-1(c), the contractor must furnish all bonds or alternative payment protection, including any necessary reinsurance agreements, before receiving a notice to proceed with the work or being allowed to start work. On contracts above $150,000, the clause that carries this into the contract is FAR 52.228-15, which uses Standard Form 25 for the performance bond and Standard Form 25A for the payment bond. On contracts greater than $35,000 but not greater than $150,000, the clause is FAR 52.228-13, Alternative Payment Protections. For contracts performed in the United States or its outlying areas, corporate sureties must appear on the Treasury Department’s Circular 570 list of companies holding certificates of authority as acceptable sureties on federal bonds, per FAR 28.202(a)(1).
For small businesses that cannot get bonded on the open market, the Small Business Administration guarantees surety bonds through participating companies, and states that it will do so on federal contracts of up to $14 million, charging “a fee of 0.6% of the contract price” on performance and payment bond guarantees.
Who has standing to sue on a Miller Act payment bond?
Two groups, and only two. Anyone with a direct contract with the prime contractor may sue on the payment bond with no notice requirement at all. Anyone with a direct contract with a subcontractor of the prime, but no contract with the prime, may sue only if they first give the prime written notice within 90 days. Everyone below that has no claim on the bond, regardless of how much they are owed or how essential their work was.
This is the most misunderstood rule in federal construction payment, and it is misunderstood in a specific and expensive direction: parties assume that because they worked on the job and did not get paid, the bond is there for them. It frequently is not.
The tier limit is not a judicial invention. It was the stated design in 1935. The Supreme Court, in J.W. Bateson Co. v. United States ex rel. Board of Trustees, 434 U.S. 586 (1978), quoted the House and Senate committee reports on the original bill:
A sub-subcontractor may avail himself of the protection of the bond by giving written notice to the contractor, but that is as far as the bill goes. It is not felt that more remote relationships ought to come within the purview of the bond.
The Court’s holding in Bateson was direct. It concluded that “the word ‘subcontractor’ must be limited in meaning to one who contracts with a prime contractor.” In that case a sprinkler installer on a federal hospital addition failed to pay over amounts withheld from its employees’ wages for union funds, and the union and its funds sued on the bond. The installer had contracted with a subcontractor, not with the prime. The Court of Appeals had allowed recovery on the reasoning that the installer performed “an integral and significant part of” the prime’s contract. The Supreme Court reversed. Doing important work on the project does not create bond rights. Having the right contract does.
Why can a supplier to a supplier be outside the bond even though it looks like the second tier?
Because “subcontractor” in the Miller Act is a narrow, technical term that does not include ordinary materialmen, so a party can be one contract removed from the prime and still be too remote. This trips up companies that correctly count themselves as second tier and incorrectly conclude they are covered.
The controlling definition comes from Clifford F. MacEvoy Co. v. United States ex rel. Calvin Tomkins Co., 322 U.S. 102 (1944), where the Court held that in the building trades “a subcontractor is one who performs for and takes from the prime contractor a specific part of the labor or material requirements of the original contract, thus excluding ordinary laborers and materialmen.” The claimant in that case had sold materials to a materialman who in turn supplied the prime. The Court’s conclusion: “If Miller was not a subcontractor, Tomkins stands in too remote a relationship to secure the benefits of the bond.”
The practical test is therefore not “how many contracts am I away from the prime.” It is: did the party I contracted with take a defined portion of the prime’s scope and perform it? A drywall subcontractor that took a defined scope is a subcontractor, so its suppliers are covered. A supply house that merely sold materials to the prime is a materialman, so anyone selling to that supply house is not covered. Same apparent tier, opposite outcome. If your position depends on this distinction, it is worth a lawyer’s read before you rely on it.
What is the 90-day notice requirement and how must the notice be served?
A claimant with no direct contract with the prime must give the prime written notice within 90 days of the day it last performed labor or supplied material. That requirement comes from 40 U.S.C. § 3133(b)(2), and it applies only to second-tier claimants. If you contracted directly with the prime, no notice is required and you can skip this entirely.
Three things have to be right, and all three are strict:
Timing. The 90 days run from the claimant’s own last day of labor or material for the claim being made, not from the last invoice, not from the last payment application, and not from project completion.
Content. The notice “must state with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed.” A demand that names no amount, or names the wrong party, is exposed.
Service. The statute allows exactly two methods. Notice must be served “by any means that provides written, third-party verification of delivery to the contractor at any place the contractor maintains an office or conducts business or at the contractor’s residence,” or in any manner in which a United States marshal may serve a summons. Note what this excludes in practice: an email with no delivery verification, or ordinary first-class mail, does not satisfy the written third-party verification standard on its face. Use a method that generates an independent delivery record and keep that record with the claim file.
When does the one-year deadline to sue start, and where do you file?
The one-year clock starts on the day the claimant itself last performed labor or supplied material, and suit is filed in federal district court where the contract was to be performed, unless a valid subcontract clause names another federal district. The statute is unambiguous on the deadline:
An action brought under this subsection must be brought no later than one year after the day on which the last of the labor was performed or material was supplied by the person bringing the action.
Read that phrase carefully: by the person bringing the action. The clock is personal to the claimant. It is not tied to substantial completion, final acceptance, final payment, closeout, or the date the prime finished. An electrical sub that finished in March and a painter that finished in September on the same project have deadlines six months apart. Firms that track a single project-level date and apply it to every claim get this wrong.
There is also a floor as well as a ceiling. Under § 3133(b)(1), a claimant may bring suit once it “has not been paid in full within 90 days” after its last labor or material. So the window opens at 90 days and closes at one year, measured from the same date.
On venue, § 3133(b)(3) requires the action to be brought in the name of the United States for the use of the person bringing the action, and “in the United States District Court for any district in which the contract was to be performed and executed, regardless of the amount in controversy.” This is federal court, not state court, and there is no minimum amount in controversy, so a small claim is still filed in district court. The district named in the statute can still be moved to another federal district by contract. In In re Fireman’s Fund Insurance Cos., 588 F.2d 93 (5th Cir. 1979), the court held that the Miller Act venue provision “exists for the convenience of the parties” and “is subject to variation by their agreement.” It upheld moving a claim on a Navy hospital job in New Orleans to New Jersey under the subcontract’s venue clause. Read the disputes clause in your subcontract before you choose where to file.
Separately, § 3133(a) gives any unpaid supplier of labor or material the right to obtain a certified copy of the payment bond and the contract from the contracting agency by submitting an affidavit. Use it early. You cannot evaluate a claim against a bond you have never read.
What are the Miller Act requirements and deadlines at a glance?
The matrix below is the working reference. Every row cites its authority.
| Requirement | The rule | Authority | Deadline or trigger |
|---|---|---|---|
| Bond requirement, statutory text | Performance and payment bonds required before award | 40 U.S.C. § 3131(b) | Contracts of more than $100,000 |
| Bond requirement, operative figure | The threshold contracting officers apply | FAR 28.102-1(a), FAC 2026-01 | Construction contracts exceeding $150,000 |
| Threshold escalation | Miller Act thresholds are excluded from five-year CPI adjustment, with the existing regulatory figure grandfathered | 41 U.S.C. § 1908(b)(2)(D) | Threshold is fixed, not scheduled to rise |
| Below the threshold | Contracting officer selects two or more alternative payment protections, contractor supplies one | FAR 28.102-1(b); 40 U.S.C. § 3132 | Contracts greater than $35,000, not greater than $150,000 |
| Performance bond amount | 100 percent of the original contract price, unless the CO finds a lesser amount adequate | FAR 28.102-2(b)(1) | At contract award |
| Payment bond amount | 100 percent of the original contract price, and never less than the performance bond | FAR 28.102-2(b)(2); 40 U.S.C. § 3131(b)(2) | At contract award |
| When bonds are furnished | All bonds and reinsurance agreements delivered before work starts | FAR 28.102-1(c); FAR 52.228-15(c) | Before notice to proceed |
| Surety qualification | Corporate surety must be on the Treasury Circular 570 list | FAR 28.202(a)(1) | At bond issuance |
| Standing, first tier | Direct contract with the prime. May sue. No notice required | 40 U.S.C. § 3133(b)(1) | Unpaid 90 days after own last labor or material |
| Standing, second tier | Direct contract with a subcontractor of the prime. May sue only after 90-day notice | 40 U.S.C. § 3133(b)(2) | Notice within 90 days |
| Standing, third tier and below | No right of action on the payment bond | J.W. Bateson, 434 U.S. 586 (1978) | Never, regardless of amount owed |
| "Subcontractor" definition | One who performs for and takes from the prime a specific part of the labor or material requirements of the original contract. Excludes ordinary materialmen | MacEvoy, 322 U.S. 102 (1944) | Determines whether your supplier's supplier is covered |
| Notice content | Must state with substantial accuracy the amount claimed and the party supplied | 40 U.S.C. § 3133(b)(2) | With the 90-day notice |
| Notice service method | Any means providing written, third-party verification of delivery, or U.S. marshal service | 40 U.S.C. § 3133(b)(2) | With the 90-day notice |
| Earliest date suit may be filed | Claimant must be unpaid for 90 days | 40 U.S.C. § 3133(b)(1) | 90 days after own last labor or material |
| Deadline to file suit | One year, and the clock is personal to the claimant | 40 U.S.C. § 3133(b)(4) | One year after own last labor or material |
| Venue | Federal district court where the contract was to be performed and executed, no minimum amount in controversy. A subcontract forum selection clause can move the case to another federal district | 40 U.S.C. § 3133(b)(3); In re Fireman's Fund, 588 F.2d 93 (5th Cir. 1979) | At filing |
| Case caption | Brought in the name of the United States for the use of the claimant | 40 U.S.C. § 3133(b)(3) | At filing |
| Right to a copy of the bond | Agency must furnish a certified copy on affidavit of nonpayment | 40 U.S.C. § 3133(a) | Any time after nonpayment |
| Advance waiver of bond rights | Void unless in writing, signed, and executed after labor or material was furnished | 40 U.S.C. § 3133(c); FAR 52.228-15(e) | Waiver must post-date the work |
| Foreign country waiver | CO may waive bonds for work performed abroad if furnishing them is impracticable | 40 U.S.C. § 3131(d); FAR 28.102-1(a)(1) | At CO discretion |
| Other statutory waivers | Military cost-type contracts and certain vessel contracts may be waived by the named secretaries | 40 U.S.C. § 3134 | By secretarial waiver |
| Government liability for costs | The government is not liable for costs or expenses of a bond action | 40 U.S.C. § 3133(b)(5) | Always |
What does a Miller Act payment bond cover, and what does it not cover?
The payment bond covers persons who supplied labor and material in carrying out the work provided for in the contract, and who fall within the two protected tiers. Section 3131(b)(2) describes it as a bond “for the protection of all persons supplying labor and material in carrying out the work provided for in the contract for the use of each person.”
What it does not cover is the part people miss. It does not cover you if you are outside the protected tiers, which is the single largest category of failed claims. It does not substitute for a lien, because there is no mechanics lien against federal property, so if the bond does not reach you, there is generally no property-based backstop. It does not cover work outside the scope of the bonded prime contract. And it is not a performance remedy: the performance bond runs to the government, so a subcontractor cannot use it to force completion or recover delay damages from the surety in the way it might pursue the prime directly.
One further limit worth knowing: under § 3133(b)(5), “the Government is not liable for the payment of any costs or expenses of any civil action” on the bond. The claimant carries its own litigation costs.
Can a subcontractor waive its Miller Act rights in advance?
No. A waiver signed before the work is performed is void. Section 3133(c) states that a waiver of the right to bring a civil action on a payment bond is void unless it is in writing, signed by the person whose right is waived, and executed after that person has already furnished labor or material for use in the performance of the contract.
This matters at subcontract execution. Broad waiver-of-claims language sitting in a subcontract signed before mobilization does not extinguish a Miller Act right, because it fails the timing requirement on its face. FAR 52.228-15(e) carries the same rule into the contract clause itself. Waivers signed later, as part of a progress payment or final payment exchange, are a different matter and can be fully effective, which is why the sequencing of lien and bond waiver documents against payment applications deserves real attention rather than a rubber stamp.
Does the Miller Act apply to state, county, or city public projects?
No. The Miller Act applies only to contracts for the construction, alteration, or repair of a public building or public work of the Federal Government. State, county, municipal, and school district projects are governed by state “Little Miller Act” statutes, which set their own thresholds, notice deadlines, and limitations periods, and which differ substantially from the federal rules on this page.
The distinction is not academic, because most public construction is not federal. Census Bureau data put total public construction spending at a seasonally adjusted annual rate of $543.4 billion in July 2026, and the large majority of that is state and local rather than federal work. If your project is a state or local job, the deadlines on this page are the wrong deadlines. Start at payment bond requirements by state→, which covers state-level payment bond requirements jurisdiction by jurisdiction.
When does a Miller Act claimant need a construction attorney?
Sooner than most contractors think, because the deadlines here are unforgiving and there is no cure for missing one. This page is a reference, not legal advice, and there are four situations where reading a reference is not enough.
When your tier is arguable. If your right to recover turns on whether the party you contracted with was a true “subcontractor” or merely a materialman under MacEvoy, that is a legal question with money on it and a body of case law behind it. Do not self-diagnose.
When a deadline is close or may have passed. The one-year period is a condition on the right to sue. Unlike a missed invoice, it is not something you negotiate your way out of after the fact. If you are inside 90 days of a deadline, or unsure when your clock started because your last work was punch list or warranty work, get advice immediately rather than after you have reconstructed the dates.
When the notice was imperfect. Disputes over whether a notice was timely, sufficiently accurate as to amount, or properly served are common, and the answer is fact-specific.
When the bond may not exist. Bonds can be waived for foreign work under § 3131(d) and under the § 3134 secretarial waivers. Worth noting honestly: the GAO reported in GAO-17-683R that the Federal Procurement Data System “does not include information related to waivers to surety bond requirements,” so there is no central database that will tell you whether a given contract was bonded. You have to ask the agency, which is what the § 3133(a) certified copy right is for.
What this page also does not cover: the performance bond claim process from the government’s side, surety defenses and the equities between surety and prime, bid bonds under FAR 28.101, sureties other than corporate sureties, and the interaction between a Miller Act claim and a Contract Disputes Act claim against the government. Those are separate analyses.
How does Contracts Connected help contractors track bond obligations and claim deadlines?
Contracts Connected treats a bond the way it treats every other compliance document: as an obligation with a date attached, tied to the contract and the party it belongs to, rather than a PDF sitting in a folder. Bond documents are indexed to the project, the tier, and the requirement they satisfy the moment they enter the system, so the question “which of our federal jobs are bonded, by whom, and for how much” is a search rather than an afternoon.
The deadline problem is the one worth designing for. The clocks on this page run from a party-specific date that nobody circulates in a status report, and they run whether or not anyone is watching. Tracking bond and notice obligations against the subcontract they belong to means a date that started running in the field is visible in the office while there is still time to act on it. Our co-founder ran a large federal general contracting firm for 15 years, about 100,000 documents a year.
Related reading and free resources:
- Construction compliance software for federal GCs→
- Construction bond compliance tracking software→
- Miller Act bonding requirements checklist→
- Performance bond requirements checklist, federal→
- Payment bond requirements checklist→
Frequently asked questions
What contract amount triggers Miller Act bond requirements?
The statute at 40 U.S.C. 3131(b) sets the trigger at more than $100,000, but the figure contracting officers actually apply is the one in FAR 28.102-1(a), which requires performance and payment bonds for any construction contract exceeding $150,000. Work from the $150,000 figure and confirm it with the contracting officer. Below that, FAR 28.102-1(b) requires alternative payment protections on contracts greater than $35,000.
Who can sue on a Miller Act payment bond?
Two groups can sue. Anyone with a direct contract with the prime contractor can sue with no notice requirement. Anyone with a direct contract with a subcontractor, but no contract with the prime, can sue only after giving the prime written notice within 90 days. Parties further down than that have no rights against the bond at all, no matter how much they are owed.
Does a third-tier subcontractor or supplier have Miller Act rights?
No. Protection stops after the second tier. In J.W. Bateson Co. v. United States ex rel. Board of Trustees, 434 U.S. 586 (1978), the Supreme Court held that subcontractor in the Act means one who contracts with a prime contractor, so a party whose only contract is with a sub-subcontractor cannot recover. The committee reports said the same thing in 1935.
How must the 90-day Miller Act notice be served on the prime contractor?
Under 40 U.S.C. 3133(b)(2) the notice must be served either by any means that provides written, third-party verification of delivery to the prime at a place it maintains an office, conducts business, or resides, or in any manner a U.S. marshal may serve a summons. The notice must state with substantial accuracy the amount claimed and the party the labor or material went to.
When does the one-year Miller Act deadline to file suit start running?
It starts on the day the claimant itself last performed labor or supplied material, not on final completion, final payment, or closeout. Two parties on the same project can therefore have deadlines months apart. Punch list work, warranty work, and corrective work generally do not restart a clock that has already begun, which is where claimants most often lose the right to sue.
Can a subcontractor waive its right to sue on a Miller Act payment bond?
Only after the work is done. Under 40 U.S.C. 3133(c) a waiver is void unless it is in writing, signed by the person whose right is waived, and executed after that person has already furnished labor or material for the contract. An advance waiver buried in a subcontract signed before work started is unenforceable against the claimant.