Risk Transfer

Subcontractor insurance requirements by trade

Which coverages and endorsements to require from each trade on commercial and private work, why the exposure genuinely differs, and why a certificate on its own proves almost nothing.

On this page
  1. What insurance should a general contractor require from subcontractors?
  2. Which coverage types belong on a subcontract insurance requirement?
  3. Why do insurance requirements differ from one trade to another?
  4. What should you require from roofing and other hot work subcontractors?
  5. What should you require from electrical, mechanical, and plumbing subcontractors?
  6. What should you require from demolition, excavation, and earthwork subcontractors?
  7. What should you require from steel erection, rigging, and crane subcontractors?
  8. What should you require from environmental and abatement subcontractors?
  9. Which subcontractors carry professional liability exposure even when they are not the designer of record?
  10. What should you require from low-voltage and specialty systems subcontractors?
  11. Which endorsements decide whether the coverage actually responds?
  12. Why does a certificate of insurance prove almost nothing on its own?
  13. What limits should you require from each trade?
  14. Which coverages and endorsements should you require from each trade?
  15. What this page does not cover
  16. How does Contracts Connected help with subcontractor insurance compliance?
  17. Frequently asked questions
  18. Requirements are easy to write. Staying compliant is the hard part.

What insurance should a general contractor require from subcontractors?

Every subcontractor should carry commercial general liability, business auto liability, and workers compensation with employers liability. Trades with distinct exposures add coverage on top: umbrella or excess, professional liability for design work, pollution liability for environmental work, an installation floater for stored materials, and rigging coverage for lifted property. The limits are set by the prime contract, the owner, and your own risk tolerance, not by an industry number.

That last point is where most published requirement sets go wrong. A benchmark limit printed on a website is a guess about somebody else’s contract. Your real floor is whatever the prime contract flows down to you, and your real ceiling is whatever a given trade can actually buy without pricing itself off your bid list.

The reason any of this is a contract term rather than a formality is volume of loss. According to the Bureau of Labor Statistics Census of Fatal Occupational Injuries for 2024, released in February 2026, the construction industry recorded 1,034 fatal work injuries in a single year. Those losses land somewhere. Risk transfer is the mechanism that decides whether they land on the trade that caused them or on you.

Which coverage types belong on a subcontract insurance requirement?

Eight coverage types cover almost everything a general contractor needs to require in commercial construction. The first three are close to universal across every trade. The other five are triggered by what the trade actually does, not by its size or its contract value.

  • Commercial general liability. Third-party bodily injury and property damage arising out of the sub’s operations and, separately, out of its completed work. This is the policy every other requirement orbits.
  • Business auto liability. Owned, hired, and non-owned vehicles. Of the 1,034 construction fatalities the Bureau of Labor Statistics recorded in 2024, 244 were transportation incidents, second only to falls, slips, and trips at 389. A trade that “just drives to the site” is still a fleet exposure.
  • Workers compensation and employers liability. Workers compensation is state-mandated for private employers; the U.S. Department of Labor states plainly that individuals injured while employed by private companies should contact their state workers compensation board rather than a federal program. Employers liability is the second half of that policy and is the part that responds when an injured worker’s claim comes back at you through a suit rather than through the compensation system.
  • Umbrella or excess liability. Sits above the primary general liability, auto, and employers liability. This is usually where the real difference between two subcontractors hides, because two subs with identical primary limits can be very differently covered depending on whether the umbrella follows form and whether it sits over all three underlying policies or only the general liability.
  • Professional liability. Responds to a design or professional services error. Almost always written on a claims-made basis, which makes the retroactive date and the reporting period more important than the limit.
  • Contractors pollution liability. Responds to environmental loss the general liability form is written to exclude. Also typically claims-made.
  • Installation floater. Property coverage for materials and equipment in transit, in storage, and installed but not yet accepted. This is a property policy, not a liability policy, and general liability will not stand in for it.
  • Riggers liability. Covers damage to property in the sub’s care while it is being lifted or moved. Required because the general liability form excludes it by name.

Why do insurance requirements differ from one trade to another?

Because coverage responds to the mechanism of a loss, not to the name of the trade, and the mechanisms are genuinely different from one scope to the next. The federal fatality data makes that concrete rather than theoretical.

In 2024, according to the Bureau of Labor Statistics CFOI industry table, roofing contractors recorded 120 fatal work injuries and 96 of them were falls, slips, and trips. That is four out of five. Over the same year, site preparation contractors recorded 80 fatal injuries with only 10 falls, but 39 transportation incidents and 26 contact incidents, the category that captures being struck by or caught in equipment and collapsing material.

Same industry, same year, opposite failure modes. Roofing kills people by dropping them. Earthwork kills people by hitting them and burying them. A requirement set that hands both trades the same certificate template is not a requirement set, it is a form.

The property side splits the same way. A roofer’s defect shows up as water intrusion two winters after final payment, which is a completed operations claim. An excavator’s defect shows up as an undermined footing or a severed utility line during the work, which is an ongoing operations claim with an entirely different endorsement behind it.

What should you require from roofing and other hot work subcontractors?

The core three coverages, additional insured status on both ongoing and completed operations, and written confirmation that the general liability policy carries no hot work, torch, or kettle exclusion. Roofing is the trade where the certificate most often looks fine and the policy most often does not respond.

The fall exposure is the largest single line item in construction safety. Fall protection general requirements, 29 CFR 1926.501, was the most frequently cited standard by federal OSHA in fiscal year 2024, ahead of every other standard in general industry and construction combined. Pair that with 96 of 120 roofing contractor fatalities being falls and the underwriting logic is obvious.

The hot work exposure is different in kind. A torch-applied or kettle roof introduces an ignition source into a building that has other trades, stored materials, and often an occupied floor below. OSHA’s fire prevention standard for welding, cutting, and heating, 29 CFR 1926.352, requires that when normal precautions are not enough, additional personnel be assigned to guard against fire “for a sufficient period of time after completion of the work to ensure that no possibility of fire exists.” The reason that language exists is that the fire that burns the building down usually does not start while the torch is lit. It smolders, and it surfaces after the crew has gone home.

Exclusions for torch and hot work operations are common enough on roofing and specialty policies that the question belongs in your requirement set as a standing item. You cannot see an exclusion on a certificate. You have to read the policy’s forms and endorsements schedule.

What should you require from electrical, mechanical, and plumbing subcontractors?

The core three, completed operations additional insured status that outlasts the warranty period, and professional liability for any of them that designs a system rather than only installing one to someone else’s drawings. These trades are defined by latent loss, not by immediate loss.

The injury data reflects a different mix than roofing. In 2024 the Bureau of Labor Statistics recorded 59 fatal work injuries among electrical contractors and other wiring installation contractors, and 75 among plumbing, heating, and air-conditioning contractors, of which 22 were exposure to harmful substances or environments. Confined space, energized systems, and refrigerant and combustion gases are a different hazard profile than working on a roof edge, and they generate a different kind of claim.

The claim that actually costs a general contractor money in these trades is usually property, not injury, and it usually arrives late. A mechanical or plumbing failure surfaces as water damage months after substantial completion. An electrical fault surfaces as a fire or as equipment loss after the building is occupied. That is completed operations territory, which is exactly the coverage the ongoing operations additional insured endorsement stops providing the moment the work is finished.

For these trades, more than for any other, the completed operations endorsement is the one that matters and the one most often missing.

What should you require from demolition, excavation, and earthwork subcontractors?

The core three, confirmation that the general liability policy has not had explosion, collapse, and underground damage coverage stripped out, pollution liability on any site old enough to hold regulated material, and auto and equipment coverage that matches the fleet actually on site rather than the fleet on the application.

The exposure signature here is being struck and being buried. In 2024 site preparation contractors recorded 80 fatal work injuries, 39 of them transportation incidents and 26 of them contact incidents. Water and sewer line and related structures construction recorded 36 fatalities with 19 contact incidents, more than half. That ratio is the trench, and it is why the excavation standard is written the way it is.

OSHA’s protective systems rule, 29 CFR 1926.652(a)(1), requires that each employee in an excavation be protected from cave-ins by an adequate protective system, with only two exceptions: excavations made entirely in stable rock, and excavations less than five feet deep where a competent person’s examination shows no indication of a potential cave-in. A collapse claim is rarely a close question on liability. It is usually a question of whose policy pays and how far the tower goes.

Demolition adds a second exposure the general liability policy is not written for. OSHA’s asbestos standard for construction, 29 CFR 1926.1101, applies by its terms to demolition or salvage of structures where asbestos is present, along with removal, encapsulation, and cleanup work. If the building predates modern material bans, the scope is an environmental scope whether or not anybody labeled it one.

Coverage for explosion, collapse, and underground property damage, usually shortened to XCU, is the item most often quietly removed from policies written for these classes. Ask specifically whether those exclusions are attached. A certificate will never show you.

What should you require from steel erection, rigging, and crane subcontractors?

The core three, riggers liability or an equivalent extension covering the property being lifted, and documented crane operator certification. The general liability policy will not respond to damage to the thing the subcontractor is holding in the air, and that is not an oversight, it is the form working as designed.

The standard commercial general liability coverage form excludes property damage to “personal property in the care, custody or control of the insured.” The moment a rigger’s slings take the load, the load is in their care. That exclusion is precisely why riggers liability exists as a separate purchase, and why a general contractor who requires only general liability on a heavy pick has required the wrong thing.

The fatality pattern for these trades is spread across every mechanism at once. In 2024 the Bureau of Labor Statistics recorded 19 fatal work injuries among structural steel and precast concrete contractors, distributed roughly evenly across transportation incidents, falls, and contact incidents. Heavy and civil engineering construction as a whole recorded 158 fatalities that year, 41 of them contact incidents. Nothing about this scope has a single dominant failure mode, which is why the requirement set has to be broad rather than deep in one place.

On the crane itself, OSHA is explicit. Under 29 CFR 1926.1427(a), “the employer must ensure that each operator is trained, certified/licensed, and evaluated in accordance with this section before operating any equipment covered under subpart CC.” Certification is a document you should be collecting alongside the certificate of insurance, because an uncertified operator is both a citation and an argument the carrier may use later.

What should you require from environmental and abatement subcontractors?

Contractors pollution liability, as a standalone requirement, on top of the core three. The reason is not preference. It is that the standard general liability form excludes, by name, the exact work these trades are hired to perform.

The pollution exclusion in the widely used commercial general liability coverage form removes bodily injury and property damage arising out of the discharge of pollutants at any site where the insured or its subcontractors are performing operations, when the pollutants are brought to the site in connection with those operations, or when “the operations are to test for, monitor, clean up, remove, contain, treat, detoxify or neutralize, or in any way respond to, or assess the effects of pollutants.” Read that list again. It is a description of an abatement contract.

The scale of the underlying exposure is real. Specialty trade contractors recorded 106 fatal work injuries from exposure to harmful substances or environments in 2024, according to the Bureau of Labor Statistics industry table, out of 606 fatalities across the group.

Two structural details matter more than the limit on this coverage. Pollution policies are usually claims-made, so the retroactive date has to predate the work and the reporting period has to outlast your exposure. And the definition of a covered pollution condition varies widely between carriers, far more than general liability language does. This is the coverage most worth having your broker read word by word rather than checking off a certificate line.

Which subcontractors carry professional liability exposure even when they are not the designer of record?

Any trade performing delegated design, which in commercial construction is far more trades than most requirement sets account for. Fire protection subs calculating sprinkler layouts and hydraulics. Curtain wall and glazing subs engineering their own connections. Precast subs designing panel attachments. Mechanical subs producing coordination drawings that other trades build to. Every design-build and design-assist scope by definition.

The gap is written into the general liability policy. Its “insured contract” definition, which is what makes contractual indemnity coverable at all, specifically excludes a contract that indemnifies “an architect, engineer or surveyor for injury or damage arising out of: (a) Preparing, approving, or failing to prepare or approve, maps, shop drawings, opinions, reports, surveys, field orders, change orders or drawings and specifications; or (b) Giving directions or instructions, or failing to give them, if that is the primary cause of the injury or damage.”

In plain terms, the contractual liability coverage the general liability policy does provide runs out exactly where design begins. If your subcontract pushes design responsibility down to a trade and you only require general liability from that trade, you have transferred a risk to a policy that was drafted to decline it.

Because professional liability is claims-made and design errors surface late, require it to be maintained for a stated number of years after completion rather than only during the work. That is a subcontract drafting decision, not a certificate decision, and it is a good reason to have the requirement live in your subcontract template rather than in a checklist somebody fills out at onboarding. Our professional liability requirements by trade reference→ breaks the delegated-design trades out in a format you can attach to a subcontract.

What should you require from low-voltage and specialty systems subcontractors?

The core three, an installation floater or equivalent property coverage for equipment stored on site before it is installed, and professional liability where the sub is engineering the system rather than pulling cable to somebody else’s design. The physical injury exposure is lower here. The property and performance exposure is not.

Electrical contractors and other wiring installation contractors, the federal classification that also captures low-voltage wiring work, recorded 59 fatal work injuries in 2024 with 17 from falls, according to the Bureau of Labor Statistics. Lower than roofing by a wide margin, and not zero.

The loss that actually happens on these scopes is theft of or damage to uninstalled equipment. Head-end gear, switchgear, controls hardware, and access control components sit in a container or a locked room for weeks between delivery and installation, and during that window they are property, not liability. The general liability policy does not respond. The installation floater does, and only if it covers materials in storage off the final installed location, which not all of them do.

Fire alarm, access control, and building automation subs add a professional exposure on top, because a system that is designed wrong fails in a way that is a design error rather than an installation error. If the sub is producing the sequence of operations, they are designing.

Which endorsements decide whether the coverage actually responds?

Five. Additional insured for ongoing operations, additional insured for completed operations, primary and noncontributory, waiver of subrogation, and a per-project aggregate. A subcontractor can carry the exact limits your contract requires and still leave you with nothing, because limits describe how much money exists and endorsements describe whether any of it is yours.

Additional insured, ongoing operations (form CG 20 10). Adds you as an insured for liability caused in whole or in part by the sub’s acts or omissions in the performance of its ongoing operations for you. Then it stops. The endorsement’s own exclusion is the clearest statement of the problem in the whole field:

“This insurance does not apply to ‘bodily injury’ or ‘property damage’ occurring after: 1. All work, including materials, parts or equipment furnished in connection with such work, on the project (other than service, maintenance or repairs) to be performed by or on behalf of the additional insured(s) at the location of the covered operations has been completed; or 2. That portion of ‘your work’ out of which the injury or damage arises has been put to its intended use by any person or organization other than another contractor or subcontractor engaged in performing operations for a principal as a part of the same project.”

Standard additional insured ongoing operations endorsement, form CG 20 10 (2013 edition), as reproduced in the sample insurance requirements published by the Dormitory Authority of the State of New York.

Read literally, that endorsement stops covering you the moment the building gets used. Which is the moment most construction defect claims start.

Additional insured, completed operations (form CG 20 37). Covers you for bodily injury or property damage caused by the sub’s work at the designated location and included in the products-completed operations hazard. This is the one that survives closeout. On construction work you need both forms, not one, and requiring “additional insured status” without specifying both is how firms end up with half of it.

Primary and noncontributory (form CG 20 01). Without it, the sub’s carrier can argue your own policy shares the loss from the first dollar. The standard endorsement states that the insurance “is primary to and will not seek contribution from any other insurance available to an additional insured under your policy,” but conditions that on your having agreed in writing in a contract that it would be primary. The endorsement reads back to the subcontract, so the subcontract has to say it.

Waiver of subrogation (form CG 24 04). Stops the sub’s carrier from paying a claim and then coming after you to get it back. The standard form waives recovery against the scheduled person or organization for payments arising out of the named insured’s ongoing operations or completed work under a contract with that party, and it applies “only to the person or organization shown in the Schedule above.” A blanket waiver is a different form. Check which one is attached and check whose name is in the schedule.

Per-project aggregate (form CG 25 03). Gives your project its own general aggregate rather than sharing one annual pool with every other job the sub is running. The standard form provides that “a separate Designated Construction Project General Aggregate Limit applies to each designated construction project, and that limit is equal to the amount of the General Aggregate Limit shown in the Declarations.” One caveat worth knowing: that form applies to the general aggregate, not to the products-completed operations aggregate, so a per-project endorsement does not by itself protect your completed operations recovery.

One more thing changed in the 2013 editions of these forms that most requirement sets have not caught up to. The current additional insured forms limit coverage to what the contract requires and cap the payout at the lesser of the amount required by the contract or the policy limit. Coverage now reads back to your subcontract language. If your subcontract asks for less than you want, the endorsement gives less than you want, no matter what the policy limit says.

Our additional insured endorsement verification checklist→ walks the specific items to check on each endorsement page, and COI endorsement requirements by project type→ maps which of these five to require on which kind of job.

Why does a certificate of insurance prove almost nothing on its own?

Because the certificate itself says so, in its own text, on its own face. The standard certificate of liability insurance form, ACORD 25, states that it “is issued as a matter of information only and confers no rights upon the certificate holder” and that it “does not amend, extend or alter the coverage afforded by the policies below.” That language is quoted in a published opinion of the New York State Department of Financial Services Office of General Counsel addressing exactly what these certificates do and do not accomplish.

So the check mark in the additional insured column is a data entry made by a broker’s assistant on a form that disclaims itself. It is evidence that somebody believed coverage existed on the day the certificate printed. It is not the grant of coverage. The grant of coverage is the endorsement, and the endorsement is a separate document with a form number, an edition date, and a schedule that either has your legal entity name in it or does not.

What that means operationally is four checks per subcontractor, every time:

  1. Collect the actual endorsement pages, not the certificate alone.
  2. Read the schedule and confirm your correct legal entity is named. Many carriers will not accept “as required by written contract” as a schedule entry, and some owners specifically reject it.
  3. Check the form number and the edition date against what your subcontract requires, because the 2013 editions behave differently from the older ones.
  4. Confirm the completed operations form is separately attached. If you only see one additional insured endorsement on a construction job, you are probably missing the one that matters most.

Doing that by hand across a full subcontractor list is the part that breaks. If you are evaluating how to keep this current rather than accurate once at onboarding, our comparison of COI tracking software for general contractors→ covers the category honestly.

What limits should you require from each trade?

There is no honest universal answer, which is why this page publishes no numbers. Limits are set by four inputs, three of which you do not control, and any published benchmark is a guess about a contract the author has not read.

  • What the prime contract flows down. This is your floor and it is not negotiable. If the prime requires a limit and your subcontract requires less, you are personally funding the difference. This is the single most common gap and the easiest to check.
  • What the owner separately requires. Owners frequently impose requirements that do not appear in the prime’s insurance article, especially on institutional, healthcare, and public-adjacent private work. Read the owner’s insurance exhibit, not just the prime.
  • What the actual exposure of the scope is. A demolition scope on an occupied campus and a finish carpentry scope in a shell building are not the same risk at any contract value. Trade and setting drive this more than dollars do.
  • How much risk you are willing to hold. The residual after the first three. This is a real business decision about your own tower, your deductible position, and how much of a bad day you are prepared to absorb.

Both failure modes cost money. Requiring too little means sharing your own limits with somebody else’s loss. Requiring more than the trade can realistically buy means a shorter bid list, higher prices, and sometimes a certificate from a carrier you would not want to file a claim against, or a project-specific policy that quietly lapses the day after final payment.

Two structural notes that matter more than the primary number. First, the umbrella is usually where the meaningful difference lives, and whether it follows form and sits over auto and employers liability as well as general liability tells you more than its face limit does. Second, on claims-made coverages, professional and pollution, the retroactive date and the extended reporting period decide whether the policy responds at all. A large limit with a retroactive date after your work started is not coverage.

Which coverages and endorsements should you require from each trade?

The matrix below is the working reference. Coverages listed as core are commercial general liability, business auto, and workers compensation with employers liability, required of every trade; the column lists what goes on top of that base. Endorsement form numbers are the standard industry forms referenced by number, and you should confirm the edition attached to any given policy.

TradeCoverages to require beyond the core threeEndorsements that matter mostWhy the exposure is different
RoofingUmbrella or excess; confirm no hot work, torch, or kettle exclusionOngoing and completed operations additional insured; primary and noncontributory; waiver of subrogationFalls dominate everything else. 96 of 120 roofing contractor fatalities in 2024 were falls, slips, and trips. Water intrusion defects surface years after closeout, so completed operations is not optional
Welding, cutting, and other hot workUmbrella or excess; explicit confirmation of no hot work exclusionCompleted operations additional insured; primary and noncontributoryThe ignition source is introduced into a structure containing other trades' work. Fire often smolders and surfaces after the crew leaves, which is a completed operations loss, not an ongoing one
ElectricalUmbrella or excess; professional liability if the sub engineers any part of the systemCompleted operations additional insured; waiver of subrogation; per-project aggregateLatent failure. A fault surfaces as fire or equipment loss after occupancy. Energized work and arc exposure also drive a distinct employers liability profile
Mechanical, plumbing, and HVACUmbrella or excess; professional liability where the sub designs rather than installs to drawingsCompleted operations additional insured; primary and noncontributory; per-project aggregateWater. The characteristic claim is property damage months after substantial completion, well past the point where ongoing operations coverage has ended. 22 of 75 fatalities in this class in 2024 were exposure to harmful substances or environments
DemolitionContractors pollution liability; confirm explosion, collapse, and underground coverage is intactOngoing operations additional insured; primary and noncontributory; per-project aggregateStructural collapse and released contaminants in one scope. On older buildings the asbestos standard applies by its terms to demolition and salvage work whether or not the scope was labeled environmental
Excavation and earthworkContractors pollution liability on suspect sites; confirm explosion, collapse, and underground coverage is intact; equipment coverage matching the actual fleetOngoing operations additional insured; primary and noncontributory; waiver of subrogationStruck-by and cave-in, not falls. Site preparation contractors recorded 39 transportation and 26 contact fatalities against only 10 falls in 2024. Utility strikes create third-party losses far larger than the subcontract value
Steel erection and structural framingUmbrella or excess; riggers liability where the sub sets its own steelOngoing and completed operations additional insured; per-project aggregate; waiver of subrogationNo single dominant failure mode. Structural steel and precast fatalities in 2024 split roughly evenly across transportation, falls, and contact incidents, so the requirement set has to be broad rather than deep
Rigging and crane operationsRiggers liability; equipment and boom coverage; documented operator certificationOngoing operations additional insured; primary and noncontributory; waiver of subrogationGeneral liability excludes property damage to personal property in the insured's care, custody, or control. The load in the air is exactly that. Federal rules also require the employer to ensure each operator is trained, certified or licensed, and evaluated before operating
Environmental remediation and abatementContractors pollution liability, mandatory; professional liability where the sub writes the remediation planOngoing and completed operations additional insured; primary and noncontributoryThe general liability pollution exclusion names this work directly, removing operations to test for, monitor, clean up, remove, contain, treat, or neutralize pollutants. Claims-made structure means the retroactive date matters more than the limit
Design-build and delegated-design tradesProfessional liability, maintained for a stated period after completion; umbrella or excessCompleted operations additional insured; primary and noncontributoryThe general liability "insured contract" definition carves out indemnity for an architect, engineer, or surveyor's professional acts. Contractual risk transfer stops exactly where design begins
Fire protectionProfessional liability for hydraulic calculations and layout; umbrella or excessCompleted operations additional insured; per-project aggregate; waiver of subrogationDual exposure. A design error and an installation error produce the same flooded building but respond under two different policies, and the failure is usually discovered long after acceptance
Low-voltage, security, and building automationInstallation floater covering equipment in storage; professional liability where the sub designs the system or writes the sequence of operationsCompleted operations additional insured; waiver of subrogationThe dominant loss is theft or damage to high-value uninstalled equipment, which is a property loss general liability will not touch. A wrong sequence of operations is a design error, not an installation error

What this page does not cover

This page is a reference, not advice, and there are four things it deliberately will not do.

It publishes no dollar limits. Not ranges, not benchmarks, not examples. Every number you would want here is set by a contract this page has not read. A published limit would be more likely to mislead you than to help you, and requirement sets built off internet benchmarks are one of the more reliable ways to end up underinsured on a specific job.

It does not cover federal agency requirements. Insurance requirements on federal construction flow from the prime contract clauses and from agency-specific supplements, and they do not track commercial practice. Treat that as separate work.

It does not resolve state law. Several states restrict by statute how far indemnity and additional insured obligations can be pushed down the contracting chain, and some restrict waivers of subrogation on workers compensation policies. Those rules vary meaningfully and they can void a requirement you thought you had. Confirm with counsel licensed in the project’s state before relying on any of this.

It assumes a conventional insurance structure. If the project runs under a wrap-up, whether owner-controlled or contractor-controlled, most of the analysis above changes. What the wrap covers, what it does not, and what each trade still has to carry outside it are project-specific questions.

And the one that matters most: your broker and the contract control, in that order. Endorsement form language changes by edition, carriers use manuscript forms that depart from the standard ones, and the only reliable way to know whether a specific policy responds to a specific subcontract is to have someone qualified read both documents together. Nothing on this page is a substitute for that.

How does Contracts Connected help with subcontractor insurance compliance?

The hard part of this was never deciding what to require. It was keeping the requirement true across every subcontractor, on every project, for the whole life of the job and the completed operations tail behind it. A requirement set is a document. Compliance is a condition, and conditions decay.

Contracts Connected reads certificates and the endorsement pages behind them, checks coverage types, limits, effective dates, and endorsement forms against what the specific subcontract requires, and flags the gaps as deficiencies with the specific reason attached rather than as a red row on a spreadsheet. When a policy lapses or an endorsement is missing for the trade in question, that surfaces before somebody needs it, not during a claim. Our co-founder ran a large federal general contracting firm for 15 years, about 100,000 documents a year.

Frequently asked questions

What insurance should a general contractor require from subcontractors?

Every subcontractor should carry commercial general liability, business auto liability, and workers compensation with employers liability. Trades with distinct exposures add coverage on top of that base: umbrella or excess liability, professional liability for any design work, pollution liability for environmental work, an installation floater for stored materials, and rigging coverage for property being lifted. The limits come from the prime contract, the owner, and your own risk tolerance.

What is the difference between the CG 20 10 and CG 20 37 additional insured endorsements?

Form CG 20 10 adds you as an additional insured for the subcontractor’s ongoing operations, and its own text ends that coverage once all work on the project has been completed or put to its intended use. Form CG 20 37 adds you for completed operations, meaning claims that surface after the work is finished. On construction work you generally need both, because most construction defect claims arrive after substantial completion.

Does a certificate of insurance prove a subcontractor has additional insured coverage?

No. The standard certificate of liability insurance form, ACORD 25, states on its face that it is issued as a matter of information only, confers no rights upon the certificate holder, and does not amend, extend or alter the coverage afforded by the policies listed. A check mark in the additional insured box is a data entry made by a broker. The grant of coverage lives in the endorsement, so you have to read the endorsement.

Which construction trades need pollution liability insurance?

Any trade whose scope is to disturb, remove, or respond to a contaminant. That includes asbestos and lead abatement, mold and environmental remediation, tank removal, contaminated soil handling, and often demolition and excavation on older sites. The reason is structural: the pollution exclusion in the standard commercial general liability form specifically excludes operations to test for, monitor, clean up, remove, contain, treat, detoxify or neutralize pollutants.

Which subcontractors need professional liability insurance?

Any trade performing delegated design, not only the designer of record. Fire protection subs calculating sprinkler layouts, curtain wall and glazing subs engineering connections, precast subs designing panel attachments, and design-build or design-assist trades all carry professional exposure. The standard general liability form’s insured contract definition specifically carves out indemnity for an architect, engineer, or surveyor’s professional acts, so general liability does not fill this gap.

What insurance limits should a general contractor require from subcontractors?

There is no honest universal number, which is why this page publishes none. Limits are driven by what the prime contract flows down to you, what the owner separately requires, the actual exposure of the scope, and how much risk you are willing to hold yourself. Requiring less than the prime demands leaves you funding the gap. Requiring more than a trade can buy shrinks your bid list without adding real protection.

Requirements are easy to write. Staying compliant is the hard part.

Contracts Connected reads the endorsement pages behind every certificate, checks them against what the specific subcontract requires, and flags what is actually missing before somebody needs it. Our co-founder ran a large federal general contracting firm for 15 years, about 100,000 documents a year.

Book a demo

This page is provided for educational purposes only and does not constitute legal advice or insurance advice. Coverage depends on the actual policy forms, endorsements, and edition dates attached to a specific policy, and on the law of the project’s state. Confirm requirements with your broker and with qualified counsel before relying on them.