Mechanics lien data

Mechanics Lien Statistics

NCS Credit's Lien Index, a 0 to 100 score of mechanics lien filing activity where 50 is neutral, was 47 in the third quarter of 2026, down from 56 a year earlier. NCS says the preliminary score will likely be revised upward. In a 2019 Levelset survey of 503 construction professionals, 58% said they have filed a mechanics lien.

This page lists sourced figures on lien filing activity, state lien deadlines and waiver rules, and the federal bond claim on public work. Each figure shows its publisher, year, sample and limit. Contracts Connected compiled and checked these figures. They are third-party figures, not Contracts Connected customer data.

Lien deadlines and waiver rules are set by state law and differ by state. The cards show Florida and Arizona as examples, and the Miller Act for federal jobs, where a payment bond claim replaces a lien.

Last reviewed: November 2026. 10 reviewed figures. 2 claim checks. Compilation licensed under CC BY 4.0.

Section A 5 figures

How many liens contractors file

Indexes and surveys from private companies, plus Census construction spending for scale. Treat first readings as preliminary.

47

NCS Credit Lien Index, third quarter 2026

NCS Credit, a credit and collection services firm, says its Lien Index was 47 in the third quarter of 2026, a 16% drop from 56 in the third quarter of 2025. The index is a 0 to 100 score of mechanic's lien filing activity where 50 is neutral, and NCS says the preliminary score will likely be revised upward.

The limit. This index comes from NCS Credit, a credit and collection services firm, and its formula is not published. The score is for the third quarter of 2026, and NCS says it will likely be revised upward.

Year
2026
Sample and method
Quarterly index of mechanic's lien activity across the U.S. construction industry; the formula and inputs are not published on the page
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "NCS Credit Lien Index, third quarter 2026," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#ncs-credit-2026-lien-index-third-quarter. Original source: NCS Credit, Lien Index Q3 2026 (blog post, published October 9, 2026), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
51 revised to 58

How NCS revised its first-print Lien Index scores

NCS Credit first reported its first-quarter 2026 Lien Index as 51 and later revised it to 58. It first reported the second quarter of 2026 as 48 and later revised it to 52.

The limit. These are NCS's own revision figures for two quarters. NCS revises first-print scores as recording offices clear backlogs.

Year
2026
Sample and method
Same index; revision history as stated by NCS in its own posts
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "How NCS revised its first-print Lien Index scores," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#ncs-credit-2026-lien-index-first-print-revisions. Original source: NCS Credit, Lien Index Q2 2026 (How to Read the Lien Index), published July 15, 2026, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
38 and 60 West and South lien index scores

NCS Credit Lien Index by region, third quarter 2026

NCS Credit's third-quarter 2026 regional Lien Index scores were South 60, West 38, Northeast 42 and Midwest 32. A score above 50 means lien filing activity is rising.

The limit. These are preliminary scores, and NCS expects them to be revised upward.

Year
2026
Sample and method
Regional cuts of the same quarterly index
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "NCS Credit Lien Index by region, third quarter 2026," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#ncs-credit-2026-lien-index-regions-third-quarter. Original source: NCS Credit, Lien Index Q3 2026 (blog post, published October 9, 2026), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
58%

Construction professionals who have filed a mechanics lien, Levelset 2019

In an August 2019 Levelset and QuickBooks Time survey of 503 construction professionals, 58% said they have filed a mechanics lien.

The limit. This is a 2019 survey of Levelset's own audience, not a random sample. The share who have ever filed a lien is not the share of unpaid invoices that end in a lien.

Year
2019
Sample and method
Survey of 503 construction professionals, conducted August 2019; respondents are Levelset's audience, not a random sample
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Construction professionals who have filed a mechanics lien, Levelset 2019," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#levelset-2019-filed-a-mechanics-lien. Original source: Levelset (a Procore company) with QuickBooks Time, Payment Issues, Problems, & Cash Stress Contractors & Subs Deal With (2019 National Construction Payments Report), published October 14, 2019, 2019. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
$2,186.1 billion

US construction spending, September 2026

The Census Bureau estimated construction spending at a seasonally adjusted annual rate of $2,186.1 billion in September 2026, 2.7% below September 2025 ($2,245.8 billion).

The limit. It is an estimate, and the Census Bureau revises it. It shows the size of the market, not lien activity.

Year
2026
Sample and method
Monthly Value of Construction Put in Place survey; seasonally adjusted annual rate; estimate with a margin of error
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "US construction spending, September 2026," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#census-2026-construction-spending-september. Original source: U.S. Census Bureau, Monthly Construction Spending, September 2026 (Release CB26-176, November 2, 2026), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section B 3 figures

What state law says about lien deadlines and waivers

Statute text from two states. Other states differ.

90 days

Florida deadline to record a claim of lien

In Florida, a claim of lien may be recorded no later than 90 days after the lienor finishes furnishing labor, services or materials. The recorded claim may stay valid for one year unless the owner acts to shorten that.

The limit. This is the 2025 edition of the statute, the latest with text online in November 2026. Florida amends this chapter from time to time.

Year
2025 statutes
Sample and method
State statute text, 2025 edition
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Florida deadline to record a claim of lien," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#florida-statutes-713-08-claim-of-lien-within-90-days. Original source: Florida Legislature, Florida Statutes 713.08 (2025), Claim of lien, 2025 statutes. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Unenforceable advance lien waivers in Florida

Florida rule on waiving lien rights in advance

Florida law says a right to claim a lien may not be waived in advance, and an advance waiver is unenforceable. A person also may not require a lienor to sign a waiver form that differs from the statutory forms.

The limit. Applies to Florida only. Other states vary.

Year
2025 statutes
Sample and method
State statute text, subsections (2) and (6)
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Florida rule on waiving lien rights in advance," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#florida-statutes-713-20-advance-waiver-unenforceable. Original source: Florida Legislature, Florida Statutes 713.20 (2025), Waiver of lien, 2025 statutes. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
120 days

Arizona deadline to record a lien

In Arizona, a lien must be recorded within 120 days after completion of the building or improvement, or within 60 days after a notice of completion is recorded.

The limit. This card covers the recording deadline only, not the deadline to enforce the lien.

Year
current statute text
Sample and method
State statute text
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Arizona deadline to record a lien," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#arizona-ars-33-993-record-lien-within-120-days. Original source: Arizona Legislature, A.R.S. 33-993, Duration of lien; time for recording, current statute text. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section C 2 figures

Federal public work: bond claims instead of liens

There is no lien on a federal building. The payment bond is the claim.

90 days to give notice; one year to sue

Miller Act deadlines to claim on a federal payment bond

On federal construction jobs covered by the Miller Act, a person with no direct contract with the prime contractor must give written notice within 90 days to claim on the payment bond, and must sue no later than one year after the last labor or material.

The limit. Applies to federal construction work, where there is no lien on the building; the bond is the claim.

Year
statute (current text)
Sample and method
Federal statute text
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Miller Act deadlines to claim on a federal payment bond," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#miller-act-40-usc-3133-notice-90-days-suit-one-year. Original source: Office of the Law Revision Counsel, via Cornell Legal Information Institute, 40 U.S.C. 3133 (Rights of persons furnishing labor or material), statute (current text). Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
$150,000

Federal payment bond line for construction contracts

Federal rules require a payment bond on any federal construction contract over $150,000. For contracts over $35,000 up to $150,000, the contracting officer picks at least two payment protections such as a bond, an irrevocable letter of credit or an escrow.

The limit. This line applies to federal contracts. State little Miller Acts set their own lines.

Year
statute (current text)
Sample and method
Federal regulation text
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Federal payment bond line for construction contracts," Contracts Connected Data, https://contractsconnected.com/data/mechanics-lien-statistics#far-28-102-1-payment-bond-150000. Original source: General Services Administration, Department of Defense and NASA (FAR), FAR 28.102-1 Bonds or other security, statute (current text). Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section D 2 checks

Claim checks: where widely repeated figures came from

These figures are repeated across the web. For each one, we traced where it came from and what it does and does not show. We do not cite any of them as a finding.

64% of lien claims paid within 3 months

Claim check: "64% of lien claims were paid within 3 months"

The claim as repeated. '64% of lien claims were paid within 3 months' and 'it worked 64% of the time'

Where it came from. Levelset blog post (September 6, 2012, updated November 4, 2019). The post says 'A few years ago, we conducted a survey that found...'. The source is Levelset's own undated survey, with no sample size, method or year on the page.

What it shows. That, per Levelset, a share of its audience that filed a lien got paid within three months.

What it does not show. It does not show a current rate, a national rate, or how many liens were filed or enforced.

Verdict. Levelset reported the figure from its own survey of its audience. The survey has no published sample size, method or year, so it cannot be checked.

Safe wording. "An undated Levelset survey reported that 64% of lien claims were paid within 3 months. Levelset does not publish the sample or method."

Do not cite this as a measured finding.

Year
2012
Sample and method
Levelset's own undated survey; no sample size, method or year on the page.
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
98% versus 95% Levelset 2019 lien threats

Claim check: Levelset 2019, contractors who "threaten to file" a lien, 98% versus 95%

The claim as repeated. Contractors who 'threaten to file' a lien

Where it came from. The same 2019 Levelset and QuickBooks Time page prints 98% in one place and 95% in another. Both come from one survey of 503 construction professionals, August 2019.

What it shows. That most surveyed contractors in Levelset's audience have used lien threats.

What it does not show. It does not say which figure is right, and the page's two numbers are for slightly different questions.

Verdict. The page gives two numbers for the same survey, and we cannot say which is right.

Safe wording. "Levelset's 2019 page reports 98% in one place and 95% in another for contractors who threaten to file a lien."

Do not cite this as a measured finding.

Year
2019
Sample and method
Survey of 503 construction professionals, August 2019.
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
Method

How we check figures

  1. Find the original publisher. We trace each figure to the organization that first published it, not to a page that repeats it.
  2. Fetch the page. We open the original page or file and read the figure there.
  3. Read the sample and method. We note who was counted, how, and when.
  4. State the limit. We write what the figure does not show, next to the figure.

Every figure on this page was re-read at its original source on 2026-11-03. The date of each check sits in the card's change log.

Questions

Frequently asked questions

What is the NCS Credit Lien Index?

It scores mechanics lien filing activity from 0 to 100, with 50 neutral. It was 47 in the third quarter of 2026, down from 56 a year earlier. NCS expects a later upward revision.

Why do Lien Index scores change after they are published?

NCS first reported its first-quarter 2026 score as 51 and later revised it to 58. Revisions come as recording offices clear backlogs, so a first reading is preliminary.

How many contractors have filed a mechanics lien?

In an August 2019 Levelset and QuickBooks Time survey of 503 construction professionals, 58% said they have filed one. The respondents are Levelset's audience, not a random sample.

What is the deadline to file a mechanics lien?

It depends on the state. Florida allows a claim of lien within 90 days after the lienor finishes furnishing. Arizona requires recording within 120 days after completion, or 60 days after a notice of completion.

Can a contractor waive lien rights in advance?

In Florida, a right to claim a lien may not be waived in advance, and an advance waiver is unenforceable. A person also may not require a waiver form that differs from the statutory forms.

What replaces a lien on federal construction jobs?

A Miller Act payment bond claim. A person with no direct contract with the prime contractor must give written notice within 90 days and sue within one year after the last labor or material.

Can I cite these figures?

Yes. You can quote, chart and republish them under CC BY 4.0 with credit to Contracts Connected. The numbers belong to the publishers, so cite the original source too. A link is welcome, never required.

Is this Contracts Connected customer data?

No. These are third-party figures that Contracts Connected compiled and checked against each original source. None of them is Contracts Connected customer data.

Cite our data

How to cite this page

You can quote, chart and republish any figure here. The Contracts Connected compilation (our wording, the notes and the layout) is licensed under Creative Commons Attribution 4.0 (CC BY 4.0). The numbers themselves belong to the organizations that published them, so cite the original source too.

Short credit. Source: Contracts Connected

Full credit. Contracts Connected, "Mechanics Lien Statistics," https://contractsconnected.com/data/mechanics-lien-statistics, reviewed November 2026, CC BY 4.0.

Linking. A link back is welcome and never required. If you link, any kind of link is fine, followed or not. Please use the name "Contracts Connected" or the page address as the link text.

Questions or corrections. support@contractsconnected.com. If a source changes a figure, we update it and record the change.

Downloads. CSV and JSON, with every figure and its change log.