Construction closeout data

Construction Closeout Statistics

California Public Contract Code 7107 says a public entity must release retention within 60 days after completion of the work, and a late payment carries a charge of 2 percent per month. Washington RCW 60.28.011 sets 60 days after the contractor requests release at completion, with retainage capped at 5 percent. On federal work, FAR 4.804-1 says firm-fixed-price contract files should be closed within 6 months after the contracting officer receives evidence of physical completion.

This page lists sourced figures on state retention release rules, federal closeout and final payment rules, punch lists, records and federal closeout backlogs. Each figure shows its publisher, year, sample and limit. Contracts Connected compiled and checked these figures. They are third-party figures, not Contracts Connected customer data.

The state rules cover public works, and the federal rules cover federal contracts. The claim checks cover the claim that federal contracts must close within 6 months and the claim that retainage is due 30 days after closeout.

Last reviewed: November 2026. 15 reviewed figures. 2 claim checks. Compilation licensed under CC BY 4.0.

Section A 3 figures

When public bodies must release retention and pay vendors

Statute text for California and Washington public works. It covers when the public body releases retention and, in California, when the contractor passes it on.

60 days

California public entity deadline to release retention

California Public Contract Code 7107 says that within 60 days after the date of completion of the work of improvement, the public entity must release the retention. If it pays late, the charge is 2 percent per month on the amount improperly withheld, plus attorney fees.

The limit. Public works contracts entered on or after Jan 1, 1993. In a dispute the entity may hold back up to 150 percent of the disputed amount. 'Completion' has four defined triggers (beneficial use with end of labor, acceptance, 100 days of cessation, or 30 days with a recorded notice). Section last amended 1998.

Year
1998
Sample and method
Statute text
US or not
California
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "California public entity deadline to release retention," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#california-legislature-1998-pcc-7107-retention-release-60-days. Original source: California Legislative Information (Public Contract Code), Public Contract Code section 7107, 1998. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
7 days

California deadline for a contractor to pay vendors their retention share

Under California Public Contract Code 7107(d), within seven days of receiving retention, the original contractor must pay each vendor (the statute says subcontractors) from whom retention was withheld that vendor's share. A bona fide dispute lets it hold up to 150 percent of the disputed amount.

The limit. Public works only. The statute's word is 'subcontractors.'

Year
1998
Sample and method
Statute text
US or not
California
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "California deadline for a contractor to pay vendors their retention share," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#california-legislature-1998-pcc-7107-retention-pay-within-7-days. Original source: California Legislative Information (Public Contract Code), Public Contract Code section 7107, 1998. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
60 days; retainage capped at 5 percent

Washington public body deadline to release retained amounts

Washington RCW 60.28.011 says that after all work other than landscaping is complete, the contractor may request release, and 'sixty days thereafter the public body must release and pay in full the amounts retained.' Retainage is capped at five percent of money earned, and lien notice must be given within 45 days of completion.

The limit. Public works only. Retainage held for landscaping can continue after the rest is released.

Year
2026
Sample and method
Statute text
US or not
Washington
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Washington public body deadline to release retained amounts," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#washington-legislature-2026-rcw-60-28-011-retainage-release. Original source: Washington State Legislature (Revised Code of Washington), RCW 60.28.011 Public improvements, retained percentage, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section B 4 figures

Federal closeout and final payment rules

FAR text for closing contract files, final payment, the construction warranty and the closeout checklist.

6 months

Federal time standards for closing contract files

FAR 4.804-1 says firm-fixed-price contract files (other than simplified acquisitions) should be closed within 6 months after the contracting officer receives evidence of physical completion. Files needing indirect cost rate settlement should close within 36 months, and all others within 20 months.

The limit. The standards say 'should,' not 'must,' and apply to contract files, not to when a vendor gets paid. They start when the contracting officer receives evidence of physical completion. The FAR Overhaul's Part 4 deviation text keeps the same time standards in Table 4-2 (section 4.308-2).

Year
2026
Sample and method
Regulation text, FAC 2026-01 effective 03/13/2026
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Federal time standards for closing contract files," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-2026-contract-file-closeout-6-months. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 4.804-1 Closeout by the office administering the contract, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
30th day after invoice or acceptance

Federal construction final payment timing

Under FAR 52.232-27 (Jan 2017), a final payment on a federal construction contract is due on the later of the 30th day after a proper invoice or the 30th day after Government acceptance of the work. Retained amounts are due on the date the contract names, or 30 days after the contracting officer approves release if it names none.

The limit. Federal construction contracts that include the clause.

Year
2017
Sample and method
Regulation text
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Federal construction final payment timing," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-2017-final-payment-52-232-27. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 52.232-27 Prompt Payment for Construction Contracts (Jan 2017), 2017. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
1 year

Federal construction warranty period

FAR 52.246-21 (Mar 1994) says the warranty of construction 'shall continue for a period of 1 year' from the date of final acceptance, or from the date the Government takes possession if that is earlier. The contractor fixes any defect at its own expense.

The limit. Applies where the clause is in the contract, and contracts can set longer warranties. The year runs from acceptance or possession, not from the final payment.

Year
1994
Sample and method
Regulation text
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Federal construction warranty period," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-1994-construction-warranty-1-year. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 52.246-21 Warranty of Construction (Mar 1994), 1994. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
15 items

Federal closeout checklist and the patent report period

FAR 4.804-5(a) lists 15 things to confirm before administrative closeout, including that the contractor's final invoice has been submitted, the contract audit is done, and excess funds are deobligated. It says final patent reports should be cleared within 60 days of receipt.

The limit. A general procurement checklist, not construction specific. Only one time period appears (the 60 days for patent reports). The FAR Overhaul's Part 4 deviation text moves the closeout procedures to section 4.308-1.

Year
2026
Sample and method
Regulation text, FAC 2026-01
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Federal closeout checklist and the patent report period," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-2026-closeout-checklist-15-items. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 4.804-5 Procedures for closing out contract files, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section C 3 figures

Punch lists, O&M manuals and records

A case study of one high-rise project, a federal guide specification and a Federal Highway Administration guide for local agencies.

About 6 months

Punch-list delay on one Las Vegas high-rise

A University of Nevada, Las Vegas case study of one high-rise project in Southern Nevada found the punch-list period was delayed by about 6 months, with multiple punch lists as the greatest contributing factor and no official sign-off document as the most challenging issue.

The limit. One project, interviews and a questionnaire of its participants. It shows causes on one job; it is not an industry average.

Year
2018
Sample and method
One project; telephone interviews and questionnaire (sample size not in the abstract)
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Punch-list delay on one Las Vegas high-rise," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#unlv-2018-las-vegas-high-rise-punch-list. Original source: University of Nevada, Las Vegas (Shrestha, Rabasto, Shrestha), Construction Research Congress 2018 proceedings, Contributing Factors to the Punch-List Problem: A Case Study from a High-Rise Tower Project in Southern Nevada, 2018. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
90 or 60 days

Federal guide specification deadline for the O&M manual

The federal Unified Facilities Guide Specification 01 78 23 (Operation and Maintenance Data) has the contractor submit the prefinal O&M manual a minimum of 90 or 60 calendar days before the Beneficial Occupancy Date, 90 for military construction and special projects and 60 for renovations or repairs.

The limit. A guide specification the designer edits for each project (the days are bracketed options), used by Army, Navy and Air Force. The contract's own text controls.

Year
2023
Sample and method
Guide specification text
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Federal guide specification deadline for the O&M manual," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#usace-navfac-afcec-2023-ufgs-01-78-23-om-manual-due-date. Original source: USACE / NAVFAC / AFCEC (Unified Facilities Guide Specifications, via WBDG), UFGS 01 78 23 Operation and Maintenance Data (May 2023, Change 4 - 08/26), 2023. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
3 years

Federal-aid project record retention

FHWA's closeout guide for local public agencies says federal regulation requires keeping all federal-aid project records for a minimum of three years after the last action on the project, usually when the agency accepts the final reimbursement payment.

The limit. Federal-aid highway projects run by local agencies. The 2012 guide says to check state laws for longer periods.

Year
2012
Sample and method
FHWA guide text
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Federal-aid project record retention," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#fhwa-2012-federal-aid-project-records-3-years. Original source: U.S. Federal Highway Administration, Federal-aid Essentials for Local Public Agencies, Project Closeout (companion guide to video, August 2012), 2012. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section D 5 figures

Federal contract closeout backlogs

GAO and DoD Inspector General reports on contracts waiting to be closed. None is a construction-only count.

231,627 contracts

Army over-age contracts due for closeout, fiscal 2017

GAO reported that the Army had a total of 231,627 firm-fixed-price and flexibly-priced over-age contracts, about 86 percent of the total contracts due for closeout, based on its fiscal year 2017 third quarter review.

The limit. All Army contract types, not construction only. A 2017 snapshot. GAO says the Army 'does not have the data broken out by contract-type.'

Year
2017
Sample and method
GAO review of five agencies (DOD, HHS, DHS, Justice, State), published September 2017
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Army over-age contracts due for closeout, fiscal 2017," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2017-army-over-age-contracts. Original source: U.S. Government Accountability Office, Federal Contracting: Additional Management Attention and Action Needed to Close Contracts and Reduce Audit Backlog (GAO-17-738), 2017. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
885 days

Days for DCAA to finish an incurred cost audit, fiscal 2016

GAO found that in fiscal 2016, the Defense Contract Audit Agency averaged 885 days from an adequate incurred cost proposal to a finished audit. Proposals waited an average of 747 days before audit work began, and the audit work took about 138 days.

The limit. Applies to contracts that need an incurred cost audit before final indirect rates are set, mostly cost-type work, not fixed-price vendor jobs. Fiscal 2016 data. About 45 percent of proposals in fiscal 2014 to 2016 were inadequate.

Year
2017
Sample and method
GAO analysis of DCAA data
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Days for DCAA to finish an incurred cost audit, fiscal 2016," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2017-dcaa-audit-days. Original source: U.S. Government Accountability Office, Federal Contracting: Additional Management Attention and Action Needed to Close Contracts and Reduce Audit Backlog (GAO-17-738), 2017. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
36,000 contracts

DCMA contracts awaiting closeout, July 2012

GAO reported that as of July 2012 the Defense Contract Management Agency had approximately 36,000 contracts awaiting closeout, including 28,000 awaiting final indirect cost rates. The Army announced a goal of closing over 475,000 over-age contracts by September 2014.

The limit. 2012 data, all contract types, one agency plus an Army goal. The Army goal is a target, not an outcome.

Year
2012
Sample and method
GAO analysis of DCMA data and interviews, December 2012
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "DCMA contracts awaiting closeout, July 2012," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2012-dcma-contracts-awaiting-closeout. Original source: U.S. Government Accountability Office, Defense Contracting: DOD Initiative to Address Audit Backlog Shows Promise, but Additional Management Attention Needed to Close Aging Contracts (GAO-13-131), 2012. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
58,000 contracts

Iraq and Afghanistan contracts to review for closeout

GAO reported in 2011 that DOD had to review and possibly close at least 58,000 Iraq contracts from fiscal years 2003 to 2010, that about 90 percent of the limited contracts with closeout data were over age, and that the Afghanistan backlog of over 42,000 contracts suggested the causes were unresolved.

The limit. Contingency contracts in Iraq and Afghanistan, not construction only, and the 90 percent covers only contracts where DOD could provide data. 2011 report.

Year
2011
Sample and method
GAO audit of DOD closeout data, September 2011
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Iraq and Afghanistan contracts to review for closeout," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2011-iraq-and-afghanistan-closeout-backlog. Original source: U.S. Government Accountability Office, Contingency Contracting: Improved Planning and Management Oversight Needed to Address Challenges with Closing Contracts (GAO-11-891), 2011. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
15 of 20

Afghanistan contingency contracts not closed out as required

A February 2024 DoD Inspector General audit of 30 Afghanistan contingency contracts found officials did not close out 15 (75 percent) of the 20 closed contracts and would not close at least 4 (40 percent) of the 10 open contracts as required. Half of the 20 closed contracts (10) lacked all closeout steps or the closeout statement. DoD missed a chance to reprogram at least $3.7 million in canceled funds.

The limit. Thirty contingency contracts, not construction. The agency lists audit delays, staff turnover, tracking failures and competing priorities as causes. Not a rate for DoD as a whole.

Year
2024
Sample and method
30 contracts reviewed (20 closed, 10 open)
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Afghanistan contingency contracts not closed out as required," Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#dod-ig-2024-afghanistan-contingency-contracts-closeout. Original source: U.S. Department of Defense Office of Inspector General, Audit of DoD Afghanistan Contingency Contracts Closeout (DODIG-2024-059), 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section E 2 checks

Claim checks: two closeout claims stated as one number

Guides repeat these two claims as a single number. For each one, we show what the original source says.

6 months

Claim check: "Federal contracts must be closed out within 6 months"

The claim as repeated. Federal contracts must be closed out within 6 months

Where it came from. A common shorthand for FAR 4.804-1.

What it shows. FAR 4.804-1 says 'should,' not 'must.' The 6 months is only for firm-fixed-price files (other than simplified acquisitions) and counts from when the contracting officer receives evidence of physical completion. Cost-type files get 20 or 36 months.

What it does not show. The 6 months does not apply to every contract file, and the rule says 'should,' not 'must.'

Verdict. The 6 months is real but narrower than the claim.

Safe wording. "FAR 4.804-1 says firm-fixed-price contract files should be closed within 6 months after the contracting officer receives evidence of physical completion."

Do not cite this as a measured finding.

Year
2026
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
30 days

Claim check: "A contractor must be paid retainage 'at closeout' within 30 days"

The claim as repeated. A contractor must be paid retainage 'at closeout' within 30 days

Where it came from. A general reading of federal prompt payment rules.

What it shows. FAR 52.232-27 sets the retainage release date by contract, or 30 days after the contracting officer approves release. State rules differ, for example 60 days in California and Washington public works.

What it does not show. No single number applies across the country.

Verdict. The release date depends on the contract clause or the state statute.

Safe wording. "FAR 52.232-27 sets the retainage release date by contract, or 30 days after the contracting officer approves release. State rules differ, for example 60 days in California and Washington public works."

Do not cite this as a measured finding.

Year
2017
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
Method

How we check figures

  1. Find the original publisher. We trace each figure to the organization that first published it, not to a page that repeats it.
  2. Fetch the page. We open the original page or file and read the figure there.
  3. Read the sample and method. We note who was counted, how, and when.
  4. State the limit. We write what the figure does not show, next to the figure.

Every figure on this page was re-read at its original source on 2026-11-03. The date of each check sits in the card's change log.

Questions

Frequently asked questions

How long does a public entity have to release retention in California?

Within 60 days after the date of completion of the work, under Public Contract Code 7107. Late payment carries a charge of 2 percent per month on the amount improperly withheld, plus attorney fees.

How soon must a contractor pay vendors their share of retention in California?

Within seven days of receiving retention, the original contractor must pay each vendor its share. A bona fide dispute lets it hold up to 150 percent of the disputed amount.

When must Washington public bodies release retainage?

Under RCW 60.28.011, 60 days after the contractor requests release at completion, the public body must release and pay in full what it retained. Retainage is capped at five percent of money earned.

Must federal contracts be closed out within 6 months?

No. FAR 4.804-1 says firm-fixed-price contract files should be closed within 6 months after the contracting officer receives evidence of physical completion. Files needing indirect cost rate settlement get 36 months.

How long is the federal construction warranty?

FAR 52.246-21 says the warranty of construction continues for 1 year from final acceptance, or from the date the Government takes possession if that is earlier. Contracts can set longer warranties.

When is final payment due on a federal construction contract?

Under FAR 52.232-27, final payment is due on the later of the 30th day after a proper invoice or the 30th day after Government acceptance of the work.

Can I cite these figures?

Yes. You can quote, chart and republish them under CC BY 4.0 with credit to Contracts Connected. The numbers belong to the publishers, so cite the original source too. A link is welcome, never required.

Is this Contracts Connected customer data?

No. These are third-party figures that Contracts Connected compiled and checked against each original source. None of them is Contracts Connected customer data.

Cite our data

How to cite this page

You can quote, chart and republish any figure here. The Contracts Connected compilation (our wording, the notes and the layout) is licensed under Creative Commons Attribution 4.0 (CC BY 4.0). The numbers themselves belong to the organizations that published them, so cite the original source too.

Short credit. Source: Contracts Connected

Full credit. Contracts Connected, "Construction Closeout Statistics," https://contractsconnected.com/data/construction-closeout-statistics, reviewed November 2026, CC BY 4.0.

Linking. A link back is welcome and never required. If you link, any kind of link is fine, followed or not. Please use the name "Contracts Connected" or the page address as the link text.

Questions or corrections. support@contractsconnected.com. If a source changes a figure, we update it and record the change.

Downloads. CSV and JSON, with every figure and its change log.