Change order data

Change Order Statistics for Construction

No source we reviewed gives one national share of contract value for change orders. In state audits the share runs from 1.96% on one West Virginia contract to 51.95% on another. In 1994, GAO found that 43% of 437 completed federal building contracts had cost growth of 10 percent or more.

This page lists sourced figures on how much change orders add to cost, how many agencies issue, what causes them, how long they take to finalize and what they do to labor productivity. Each figure shows its publisher, year, sample and limit. Contracts Connected compiled and checked these figures. They are third-party figures, not Contracts Connected customer data.

Most state figures are old audits of one agency. The claim checks show where a widely repeated productivity figure came from and why no national number is cited here.

Last reviewed: November 2026. 14 reviewed figures. 3 claim checks. Compilation licensed under CC BY 4.0.

Section A 4 figures

How much change orders add to cost

Audits of single agencies and projects. The share depends on the owner, the project and the year, so read each figure with its limit.

43%

Federal building contracts with cost growth of 10 percent or more, 1994

In a 1994 review of 437 completed federal building contracts, the Government Accountability Office (then the General Accounting Office) found that 43% had cost growth of 10 percent or more, and over 50% of the new construction and repair contracts had cost growth above the 5 percent and 7 percent GSA budgets for changes.

The limit. This is a 1994 review of federal buildings only. It measures all cost growth on the contract, not only owner-requested changes.

Year
1994
Sample and method
GSA data on 100 new construction and 337 repair and alteration contracts substantially completed fiscal year 1988 through the first half of fiscal year 1993
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Federal building contracts with cost growth of 10 percent or more, 1994," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#gao-1994-gsa-contracts-cost-growth-10-percent. Original source: U.S. General Accounting Office (now GAO), GGD-94-145, General Services Administration: Better Data and Oversight Needed to Improve Construction Management (June 1994), 1994. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
$12 million on $118.4 million

What 100 reviewed change orders added to eight Missouri highway projects

Missouri's State Auditor reviewed 100 change orders on 8 Department of Transportation projects, issued over 18 months in 2000 and 2001. The projects were expected to cost $118.4 million and the 100 change orders increased costs by $12 million.

The limit. Eight projects in one state in 2000 to 2001. The auditors' sample is not the state average.

Year
2002
Sample and method
Auditors' review of 100 change orders on 8 construction projects, 2000 to 2001; not a random sample of all projects
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "What 100 reviewed change orders added to eight Missouri highway projects," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-100-change-orders-12-million. Original source: Missouri Office of State Auditor (Claire McCaskill), Missouri Department of Transportation Contract Change Orders (performance audit, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
51.95%

How much change orders raised one West Virginia jail contract

A West Virginia legislative audit found change orders of $3,399,309 were added to the $6,543,000 Eastern Regional Jail construction contract, a total increase of 51.95%. Later jail contracts stayed under a 5% increase.

The limit. One project, 1997 to 1999, in a memo from a state audit office. It does not show what is typical.

Year
2002
Sample and method
Review of one agency's construction contracts; the 51.95% is one facility for the period July 1, 1997 to December 31, 1999
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "How much change orders raised one West Virginia jail contract," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#west-virginia-legislature-2002-jail-change-orders-51-95-percent. Original source: West Virginia Legislature, Legislative Post Audit Division, Follow-up Review of the Change Orders Issued for Regional Jail Construction Contracts (memo dated July 11, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
4.14%, 1.96%, 2.74%

How much change orders raised three later West Virginia contracts

In the 2002 follow-up, West Virginia auditors found change orders raised the North Central Regional Jail contract by 4.14%, the Lakin Correctional Center contract by 1.96% and the Western Regional Jail contract by 2.74%.

The limit. Two of the three contracts were unfinished, so the final shares may be higher.

Year
2002
Sample and method
Three general construction contracts; Lakin was 95% complete and Western about 50% complete when reviewed
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "How much change orders raised three later West Virginia contracts," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#west-virginia-legislature-2002-three-contracts-change-orders. Original source: West Virginia Legislature, Legislative Post Audit Division, Follow-up Review of the Change Orders Issued for Regional Jail Construction Contracts (memo dated July 11, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section B 4 figures

How many change orders agencies issue

Counts and dollars from agency reports and audits. None of them is a national rate.

3 percent

Missouri DOT's own change order rate, and three neighboring states

Missouri Department of Transportation officials told auditors their 3 percent change order rate was comparable or better than neighboring states: Kansas 2 to 5 percent, Iowa 5.4 percent and Illinois 4 to 7 percent.

The limit. This is the department's own claim about itself and three other states, from 2002. It is not an audit finding.

Year
2002
Sample and method
Department officials' statement quoted in the audit summary; not an audit finding
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Missouri DOT's own change order rate, and three neighboring states," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-modot-3-percent-change-order-rate. Original source: Missouri Office of State Auditor (Claire McCaskill), Missouri Department of Transportation Contract Change Orders (performance audit, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
$224,093,394

Change orders on the Southwest light rail civil construction contract

Minnesota's Legislative Auditor found that from March 2019 to October 2022, 550 of 658 civil construction change orders on the Southwest light rail project increased cost, by a total of $224,093,394. 44 decreased cost and 64 had no cost effect, for a net total impact of $219,452,031.

The limit. One very large transit project. It shows the dollars and counts, not a share of contract value.

Year
2023
Sample and method
Auditor's analysis of Metropolitan Council data for one civil construction contract, March 2019 to October 2022 (Exhibit 2.1)
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Change orders on the Southwest light rail civil construction contract," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#minnesota-auditor-2023-southwest-light-rail-change-orders. Original source: Minnesota Office of the Legislative Auditor, Program Evaluation Division, Southwest Light Rail Transit Construction: Metropolitan Council Oversight of Contractors (June 2023), 2023. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
1,253 change orders, $346.9 million

Caltrans change orders in one quarter, October to December 2023

Caltrans says its 12 districts issued 1,253 change orders worth $346.9 million, including supplemental change orders, from October to December 2023. For July to September 2023 it reported 1,187 change orders worth $285.1 million.

The limit. Counts and dollars for single quarters, not a percent of contract value, so it cannot be turned into a share.

Year
2024
Sample and method
Agency's quarterly count of change orders across its districts
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Caltrans change orders in one quarter, October to December 2023," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#caltrans-2024-change-orders-in-one-quarter. Original source: California Department of Transportation, Change (order) is a fact of life in Construction, Mile Marker 2024 Issue 1, 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
9 change orders of $500,000 or more

WSDOT change orders of $500,000 or more, fourth quarter 2024

The Washington State Department of Transportation says it tracked nine change orders of $500,000 or more in the fourth quarter of 2024, and it posts all such change orders each month.

The limit. Counts only large change orders, not all of them, and no contract value share is given.

Year
2024
Sample and method
Agency's count of large change orders ($500,000 or more) by quarter, 2020 Q1 through 2024 Q4
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "WSDOT change orders of $500,000 or more, fourth quarter 2024," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#wsdot-2024-large-change-orders-fourth-quarter. Original source: Washington State Department of Transportation, Gray Notebook, Change orders, 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section C 3 figures

Why change orders happen and whether they can be avoided

What research and auditors say drives changes, and how often changes lead to disputes.

Scope modification most common source of change

The most common source of change and the highest-impact cause of overruns, 1991

A 1991 Construction Industry Institute report says scope modification is the most common source of change, and that poor scope definition is the highest-impact cause of projects running over budget.

The limit. Qualitative findings from the report's abstract page only, published in 1991. The abstract page gives no sample size or percentages.

Year
1991
Sample and method
Research report; the page gives no sample size or percentages (those are in Chapter 5 and Appendix B, not shown)
US or not
Not stated
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "The most common source of change and the highest-impact cause of overruns, 1991," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#cii-1991-scope-modification-most-common-source-of-change. Original source: Construction Industry Institute (CII), Construction Changes and Change Orders: Their Magnitude and Impact (Publication SD-66, April 1, 1991, 125 pages), 1991. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
330 of 796 line items

Missouri change order line items the auditors called avoidable

Missouri auditors counted 796 line items in the 100 change orders they reviewed, called 59% of the line items necessary and unforeseen before the contract was awarded, and found the department could have avoided 330 of them, totaling $5.8 million.

The limit. Auditor's opinion on a small sample. 'Avoidable' means officials could have handled the project properly before it went to bid.

Year
2002
Sample and method
Same 100 change orders on 8 projects; auditors' judgment of necessity
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Missouri change order line items the auditors called avoidable," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-avoidable-change-order-line-items. Original source: Missouri Office of State Auditor (Claire McCaskill), Missouri Department of Transportation Contract Change Orders (performance audit, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
4th most common dispute cause: owner-directed changes

Where owner-directed changes rank among causes of construction disputes

Arcadis's 2024 North America disputes report, using 2023 survey results, ranks owner-directed changes as the fourth most common cause of construction disputes (fifth in 2022). The average dispute value was $43 million and the average length was 14.4 months.

The limit. It ranks causes of disputes, not how often change orders happen. Covers North America, not the U.S. alone.

Year
2024
Sample and method
Survey by the Arcadis North America Contract Solutions team; only North American input; sample size not stated in the sections read
US or not
US and Canada
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Where owner-directed changes rank among causes of construction disputes," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#arcadis-2024-owner-directed-changes-rank-among-dispute-causes. Original source: Arcadis, 14th Annual Construction Disputes Report, North America 2024: Managing Construction Disputes in the Digital Age, 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section D 3 figures

How long changes take and what they do to productivity

Time to finalize a change, and labor efficiency on changed work.

About 45%

Army Corps contract changes that took more than 60 days to finalize

GAO reported that about 45% of completed construction contract changes at the Army Corps of Engineers from 2013 through 2018 took more than 60 days to finalize, and a little more than 3% took more than one year.

The limit. This is time to process a change, not cost or how often changes happen. One agency's data, compiled ad hoc by USACE officials.

Year
2019
Sample and method
USACE data on contract changes finalized January 2013 to August 2018, measured from the contractor's proposal to the finalized change; excludes terminations, claims, options and administrative modifications
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Army Corps contract changes that took more than 60 days to finalize," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#gao-2019-army-corps-changes-over-60-days. Original source: U.S. Government Accountability Office, GAO-19-500, Federal Construction: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes (July 2019), 2019. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
GSA could not provide data

GSA could not provide data on how long its contract changes take

GAO found that the Army Corps reviews change data only on an ad hoc basis, and that the General Services Administration was unable to provide similar data on how long its construction contract changes take.

The limit. Describes the data gap in 2019; agencies may have changed since.

Year
2019
Sample and method
GAO review of Army Corps and GSA change processes and data
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "GSA could not provide data on how long its contract changes take," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#gao-2019-gsa-could-not-provide-change-timing-data. Original source: U.S. Government Accountability Office, GAO-19-500, Federal Construction: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes (July 2019), 2019. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
70% of normal

Labor efficiency on changed work, four sites over 151 weeks

A 1994 Construction Industry Institute study of productivity data from four construction sites over 151 weeks found labor efficiency on changed work averaged about 70 percent of normal, and about a third of the days with changed work showed no loss.

The limit. Small sample (four sites) and more than 30 years old; the page does not say the sites were in the U.S. It measures labor productivity on changed work, not project cost growth.

Year
1994
Sample and method
Productivity data from four active construction sites, 151 weeks
US or not
Not stated
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Labor efficiency on changed work, four sites over 151 weeks," Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#cii-1994-efficiency-on-changed-work. Original source: Construction Industry Institute (CII), The Effects of Change on Labor Productivity: Why and How Much (Publication SD-99, August 1, 1994), 1994. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section E 3 checks

Claim checks: where widely repeated figures came from

These figures are repeated across the web. For each one, we traced where it came from and what it does and does not show. We do not cite any of them as a finding.

30 percent claimed productivity loss

Claim check: "Change orders cause a 30 percent productivity loss"

The claim as repeated. Change orders cut labor productivity by about 30 percent

Where it came from. This is commonly summarized from CII research. We did not trace who repeats it. It comes from Construction Industry Institute SD-99 (1994): four sites, 151 weeks, with efficiency on changed work about 70 percent of normal.

What it shows. A loss of about 30 percent on days with changed work at those four sites, with about a third of such days showing no loss.

What it does not show. It does not show a 30 percent loss across whole projects or on all change orders, and it is a small sample.

Verdict. The study is real, and the 30 percent comes from it. It supports a narrow sentence about days with changed work at four sites. It does not support a claim about all change orders.

Safe wording. "A 1994 Construction Industry Institute study of four sites found labor efficiency on changed work averaged about 70 percent of normal."

Do not cite this as a measured finding.

Year
1994
Sample and method
Four construction sites, 151 weeks.
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
No national average change order share of contract value

Claim check: a single national "average change order share"

The claim as repeated. A single industry-wide figure for change orders as a share of contract value

Where it came from. We did not find this claim in our review. State audits range widely: 3 percent (Missouri officials, 2002), nearly 9 percent (Nevada, reported 2002, see the Nevada claim check below), 4.14 percent and 51.95 percent on single West Virginia jails.

What it shows. That the share depends on owner, project type and year.

What it does not show. No source in our review supports one national number.

Verdict. No source we reviewed gives one national share of contract value. The state audits we found differ widely, so the share depends on owner, project type and year.

Safe wording. "State figures we found range from 1.96 percent on one West Virginia jail contract to 51.95 percent on another."

Do not cite this as a measured finding.

Year
2002
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
731 change orders on 98 Nevada projects, $447 million to $487 million, 2002

Claim check: Nevada road projects, 2002, 731 change orders

The claim as repeated. Change orders added $40 million to Nevada Department of Transportation road projects over 30 months, a rate of nearly 9 percent

Where it came from. Northern Nevada Business Weekly, March 14, 2002, reporting an Executive Branch Audit Committee hearing. The audit by the governor's Internal Audit Division (98 state road projects, January 1, 1999 to June 30, 2001) was read only through the news report. We did not find the audit itself.

What it shows. As reported: original contract total of $447 million rose to $487 million through 731 change orders; the transportation director called a rate of nearly 9 percent too high.

What it does not show. The figures are second-hand and 24 years old. We did not find the audit, so they are unverified.

Verdict. The figures come from a news report of a hearing. We have not seen the audit, so they are unverified.

Safe wording. "A March 2002 news report said Nevada road projects rose from an original $447 million to $487 million through 731 change orders, and the transportation director called a rate of nearly 9 percent too high."

Do not cite this as a measured finding.

Year
2002
Sample and method
Second-hand news report of a state audit of 98 road projects, January 1, 1999 to June 30, 2001.
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
Method

How we check figures

  1. Find the original publisher. We trace each figure to the organization that first published it, not to a page that repeats it.
  2. Fetch the page. We open the original page or file and read the figure there.
  3. Read the sample and method. We note who was counted, how, and when.
  4. State the limit. We write what the figure does not show, next to the figure.

Every figure on this page was re-read at its original source on 2026-11-03. The date of each check sits in the card's change log.

Questions

Frequently asked questions

How much do change orders add to a construction contract?

No source we reviewed gives one national share. State audits range from 1.96% on one West Virginia contract to 51.95% on another, and the share depends on owner, project type and year.

How common is cost growth on construction contracts?

In a 1994 GAO review of 437 completed federal building contracts, 43% had cost growth of 10 percent or more. That counts all cost growth on the contract, not only owner-requested changes.

Do change orders really cut productivity by 30 percent?

The figure traces to a 1994 Construction Industry Institute study of four sites over 151 weeks. Efficiency on changed work averaged about 70 percent of normal. It does not show a loss across whole projects.

How long do change orders take to finalize?

GAO reported that about 45% of completed Army Corps of Engineers contract changes from 2013 through 2018 took more than 60 days to finalize, and a little more than 3% took more than one year.

What causes change orders?

A 1991 Construction Industry Institute report says scope modification is the most common source of change, and poor scope definition is the highest-impact cause of projects running over budget.

How many change orders do state agencies issue?

Caltrans reported 1,253 change orders worth $346.9 million from October to December 2023. The Washington State Department of Transportation tracked nine change orders of $500,000 or more in the fourth quarter of 2024.

Can I cite these figures?

Yes. You can quote, chart and republish them under CC BY 4.0 with credit to Contracts Connected. The numbers belong to the publishers, so cite the original source too. A link is welcome, never required.

Is this Contracts Connected customer data?

No. These are third-party figures that Contracts Connected compiled and checked against each original source. None of them is Contracts Connected customer data.

Cite our data

How to cite this page

You can quote, chart and republish any figure here. The Contracts Connected compilation (our wording, the notes and the layout) is licensed under Creative Commons Attribution 4.0 (CC BY 4.0). The numbers themselves belong to the organizations that published them, so cite the original source too.

Short credit. Source: Contracts Connected

Full credit. Contracts Connected, "Change Order Statistics for Construction," https://contractsconnected.com/data/change-order-statistics, reviewed November 2026, CC BY 4.0.

Linking. A link back is welcome and never required. If you link, any kind of link is fine, followed or not. Please use the name "Contracts Connected" or the page address as the link text.

Questions or corrections. support@contractsconnected.com. If a source changes a figure, we update it and record the change.

Downloads. CSV and JSON, with every figure and its change log.