  "title": "Construction Closeout Statistics",
  "url": "https://contractsconnected.com/data/construction-closeout-statistics",
  "publisher": "Contracts Connected",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "license_name": "CC BY 4.0",
  "reviewed": "November 2026",
  "checked_on": "2026-11-03",
  "note": "Curated and source-checked compilation of published figures. Not Contracts Connected customer data.",
  "downloads": {
    "csv": "https://contractsconnected.com/data/construction-closeout-statistics.csv",
    "json": "https://contractsconnected.com/data/construction-closeout-statistics.json"
  },
  "figures": 15,
  "claim_checks": 2,
  "rows": [
    {
      "id": "california-legislature-1998-pcc-7107-retention-release-60-days",
      "title": "California public entity deadline to release retention",
      "section": "When public bodies must release retention and pay vendors",
      "kind": "figure",
      "statistic": "California: public entity must release retention within 60 days after completion; late charge is 2 percent per month",
      "wording": "California Public Contract Code 7107 says that within 60 days after the date of completion of the work of improvement, the public entity must release the retention. If it pays late, the charge is 2 percent per month on the amount improperly withheld, plus attorney fees.",
      "limit": "Public works contracts entered on or after Jan 1, 1993. In a dispute the entity may hold back up to 150 percent of the disputed amount. 'Completion' has four defined triggers (beneficial use with end of labor, acceptance, 100 days of cessation, or 30 days with a recorded notice). Section last amended 1998.",
      "source_publisher": "California Legislative Information (Public Contract Code)",
      "source_title": "Public Contract Code section 7107",
      "source_url": "https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=7107",
      "source_year": "1998",
      "sample_or_method": "Statute text",
      "geography": "California",
      "status": "Reviewed",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#california-legislature-1998-pcc-7107-retention-release-60-days",
      "cite_as": "Cite as: Contracts Connected, \"California public entity deadline to release retention,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#california-legislature-1998-pcc-7107-retention-release-60-days. Original source: California Legislative Information (Public Contract Code), Public Contract Code section 7107, 1998. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "california-legislature-1998-pcc-7107-retention-pay-within-7-days",
      "title": "California deadline for a contractor to pay vendors their retention share",
      "section": "When public bodies must release retention and pay vendors",
      "kind": "figure",
      "statistic": "California: original contractor must pay each vendor its share of retention within 7 days of receiving it",
      "wording": "Under California Public Contract Code 7107(d), within seven days of receiving retention, the original contractor must pay each vendor (the statute says subcontractors) from whom retention was withheld that vendor's share. A bona fide dispute lets it hold up to 150 percent of the disputed amount.",
      "limit": "Public works only. The statute's word is 'subcontractors.'",
      "source_publisher": "California Legislative Information (Public Contract Code)",
      "source_title": "Public Contract Code section 7107",
      "source_url": "https://leginfo.legislature.ca.gov/faces/codes_displaySection.xhtml?lawCode=PCC&sectionNum=7107",
      "source_year": "1998",
      "sample_or_method": "Statute text",
      "geography": "California",
      "status": "Reviewed",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#california-legislature-1998-pcc-7107-retention-pay-within-7-days",
      "cite_as": "Cite as: Contracts Connected, \"California deadline for a contractor to pay vendors their retention share,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#california-legislature-1998-pcc-7107-retention-pay-within-7-days. Original source: California Legislative Information (Public Contract Code), Public Contract Code section 7107, 1998. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "washington-legislature-2026-rcw-60-28-011-retainage-release",
      "title": "Washington public body deadline to release retained amounts",
      "section": "When public bodies must release retention and pay vendors",
      "kind": "figure",
      "statistic": "Washington: public body must pay retained amounts 60 days after the contractor requests release at completion; retainage capped at 5 percent",
      "wording": "Washington RCW 60.28.011 says that after all work other than landscaping is complete, the contractor may request release, and 'sixty days thereafter the public body must release and pay in full the amounts retained.' Retainage is capped at five percent of money earned, and lien notice must be given within 45 days of completion.",
      "limit": "Public works only. Retainage held for landscaping can continue after the rest is released.",
      "source_publisher": "Washington State Legislature (Revised Code of Washington)",
      "source_title": "RCW 60.28.011 Public improvements, retained percentage",
      "source_url": "https://app.leg.wa.gov/RCW/default.aspx?cite=60.28.011",
      "source_year": "2026",
      "sample_or_method": "Statute text",
      "geography": "Washington",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#washington-legislature-2026-rcw-60-28-011-retainage-release",
      "cite_as": "Cite as: Contracts Connected, \"Washington public body deadline to release retained amounts,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#washington-legislature-2026-rcw-60-28-011-retainage-release. Original source: Washington State Legislature (Revised Code of Washington), RCW 60.28.011 Public improvements, retained percentage, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "far-2026-contract-file-closeout-6-months",
      "title": "Federal time standards for closing contract files",
      "section": "Federal closeout and final payment rules",
      "kind": "figure",
      "statistic": "FAR 4.804-1: fixed-price contract files closed within 6 months; others 20 or 36 months",
      "wording": "FAR 4.804-1 says firm-fixed-price contract files (other than simplified acquisitions) should be closed within 6 months after the contracting officer receives evidence of physical completion. Files needing indirect cost rate settlement should close within 36 months, and all others within 20 months.",
      "limit": "The standards say 'should,' not 'must,' and apply to contract files, not to when a vendor gets paid. They start when the contracting officer receives evidence of physical completion. The FAR Overhaul's Part 4 deviation text keeps the same time standards in Table 4-2 (section 4.308-2).",
      "source_publisher": "Acquisition.gov (Federal Acquisition Regulation)",
      "source_title": "FAR 4.804-1 Closeout by the office administering the contract",
      "source_url": "https://www.acquisition.gov/far/4.804-1",
      "source_year": "2026",
      "sample_or_method": "Regulation text, FAC 2026-01 effective 03/13/2026",
      "geography": "US",
      "status": "Reviewed",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#far-2026-contract-file-closeout-6-months",
      "cite_as": "Cite as: Contracts Connected, \"Federal time standards for closing contract files,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-2026-contract-file-closeout-6-months. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 4.804-1 Closeout by the office administering the contract, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "far-2017-final-payment-52-232-27",
      "title": "Federal construction final payment timing",
      "section": "Federal closeout and final payment rules",
      "kind": "figure",
      "statistic": "FAR 52.232-27: final payment due on the 30th day after invoice or after Government acceptance, whichever is later",
      "wording": "Under FAR 52.232-27 (Jan 2017), a final payment on a federal construction contract is due on the later of the 30th day after a proper invoice or the 30th day after Government acceptance of the work. Retained amounts are due on the date the contract names, or 30 days after the contracting officer approves release if it names none.",
      "limit": "Federal construction contracts that include the clause.",
      "source_publisher": "Acquisition.gov (Federal Acquisition Regulation)",
      "source_title": "FAR 52.232-27 Prompt Payment for Construction Contracts (Jan 2017)",
      "source_url": "https://www.acquisition.gov/far/52.232-27",
      "source_year": "2017",
      "sample_or_method": "Regulation text",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#far-2017-final-payment-52-232-27",
      "cite_as": "Cite as: Contracts Connected, \"Federal construction final payment timing,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-2017-final-payment-52-232-27. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 52.232-27 Prompt Payment for Construction Contracts (Jan 2017), 2017. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "far-1994-construction-warranty-1-year",
      "title": "Federal construction warranty period",
      "section": "Federal closeout and final payment rules",
      "kind": "figure",
      "statistic": "FAR 52.246-21: construction warranty runs 1 year from final acceptance",
      "wording": "FAR 52.246-21 (Mar 1994) says the warranty of construction 'shall continue for a period of 1 year' from the date of final acceptance, or from the date the Government takes possession if that is earlier. The contractor fixes any defect at its own expense.",
      "limit": "Applies where the clause is in the contract, and contracts can set longer warranties. The year runs from acceptance or possession, not from the final payment.",
      "source_publisher": "Acquisition.gov (Federal Acquisition Regulation)",
      "source_title": "FAR 52.246-21 Warranty of Construction (Mar 1994)",
      "source_url": "https://www.acquisition.gov/far/52.246-21",
      "source_year": "1994",
      "sample_or_method": "Regulation text",
      "geography": "US",
      "status": "Reviewed",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#far-1994-construction-warranty-1-year",
      "cite_as": "Cite as: Contracts Connected, \"Federal construction warranty period,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-1994-construction-warranty-1-year. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 52.246-21 Warranty of Construction (Mar 1994), 1994. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "far-2026-closeout-checklist-15-items",
      "title": "Federal closeout checklist and the patent report period",
      "section": "Federal closeout and final payment rules",
      "kind": "figure",
      "statistic": "FAR 4.804-5: closeout checklist of 15 items; final patent reports cleared within 60 days",
      "wording": "FAR 4.804-5(a) lists 15 things to confirm before administrative closeout, including that the contractor's final invoice has been submitted, the contract audit is done, and excess funds are deobligated. It says final patent reports should be cleared within 60 days of receipt.",
      "limit": "A general procurement checklist, not construction specific. Only one time period appears (the 60 days for patent reports). The FAR Overhaul's Part 4 deviation text moves the closeout procedures to section 4.308-1.",
      "source_publisher": "Acquisition.gov (Federal Acquisition Regulation)",
      "source_title": "FAR 4.804-5 Procedures for closing out contract files",
      "source_url": "https://www.acquisition.gov/far/4.804-5",
      "source_year": "2026",
      "sample_or_method": "Regulation text, FAC 2026-01",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#far-2026-closeout-checklist-15-items",
      "cite_as": "Cite as: Contracts Connected, \"Federal closeout checklist and the patent report period,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#far-2026-closeout-checklist-15-items. Original source: Acquisition.gov (Federal Acquisition Regulation), FAR 4.804-5 Procedures for closing out contract files, 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "unlv-2018-las-vegas-high-rise-punch-list",
      "title": "Punch-list delay on one Las Vegas high-rise",
      "section": "Punch lists, O&M manuals and records",
      "kind": "figure",
      "statistic": "Las Vegas high-rise: punch-list period delayed about 6 months; multiple punch lists the top cause",
      "wording": "A University of Nevada, Las Vegas case study of one high-rise project in Southern Nevada found the punch-list period was delayed by about 6 months, with multiple punch lists as the greatest contributing factor and no official sign-off document as the most challenging issue.",
      "limit": "One project, interviews and a questionnaire of its participants. It shows causes on one job; it is not an industry average.",
      "source_publisher": "University of Nevada, Las Vegas (Shrestha, Rabasto, Shrestha), Construction Research Congress 2018 proceedings",
      "source_title": "Contributing Factors to the Punch-List Problem: A Case Study from a High-Rise Tower Project in Southern Nevada",
      "source_url": "https://oasis.library.unlv.edu/fac_articles/599",
      "source_year": "2018",
      "sample_or_method": "One project; telephone interviews and questionnaire (sample size not in the abstract)",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#unlv-2018-las-vegas-high-rise-punch-list",
      "cite_as": "Cite as: Contracts Connected, \"Punch-list delay on one Las Vegas high-rise,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#unlv-2018-las-vegas-high-rise-punch-list. Original source: University of Nevada, Las Vegas (Shrestha, Rabasto, Shrestha), Construction Research Congress 2018 proceedings, Contributing Factors to the Punch-List Problem: A Case Study from a High-Rise Tower Project in Southern Nevada, 2018. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "usace-navfac-afcec-2023-ufgs-01-78-23-om-manual-due-date",
      "title": "Federal guide specification deadline for the O&M manual",
      "section": "Punch lists, O&M manuals and records",
      "kind": "figure",
      "statistic": "UFGS 01 78 23: prefinal O&M manual due 90 or 60 calendar days before beneficial occupancy",
      "wording": "The federal Unified Facilities Guide Specification 01 78 23 (Operation and Maintenance Data) has the contractor submit the prefinal O&M manual a minimum of 90 or 60 calendar days before the Beneficial Occupancy Date, 90 for military construction and special projects and 60 for renovations or repairs.",
      "limit": "A guide specification the designer edits for each project (the days are bracketed options), used by Army, Navy and Air Force. The contract's own text controls.",
      "source_publisher": "USACE / NAVFAC / AFCEC (Unified Facilities Guide Specifications, via WBDG)",
      "source_title": "UFGS 01 78 23 Operation and Maintenance Data (May 2023, Change 4 - 08/26)",
      "source_url": "https://nibs-s3-wbdg3-production.s3.us-east-1.amazonaws.com/FFC/DOD/UFGS/UFGS%2001%2078%2023.pdf",
      "source_year": "2023",
      "sample_or_method": "Guide specification text",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#usace-navfac-afcec-2023-ufgs-01-78-23-om-manual-due-date",
      "cite_as": "Cite as: Contracts Connected, \"Federal guide specification deadline for the O&M manual,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#usace-navfac-afcec-2023-ufgs-01-78-23-om-manual-due-date. Original source: USACE / NAVFAC / AFCEC (Unified Facilities Guide Specifications, via WBDG), UFGS 01 78 23 Operation and Maintenance Data (May 2023, Change 4 - 08/26), 2023. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "fhwa-2012-federal-aid-project-records-3-years",
      "title": "Federal-aid project record retention",
      "section": "Punch lists, O&M manuals and records",
      "kind": "figure",
      "statistic": "FHWA: federal-aid project records kept at least 3 years after the last action on the project",
      "wording": "FHWA's closeout guide for local public agencies says federal regulation requires keeping all federal-aid project records for a minimum of three years after the last action on the project, usually when the agency accepts the final reimbursement payment.",
      "limit": "Federal-aid highway projects run by local agencies. The 2012 guide says to check state laws for longer periods.",
      "source_publisher": "U.S. Federal Highway Administration",
      "source_title": "Federal-aid Essentials for Local Public Agencies, Project Closeout (companion guide to video, August 2012)",
      "source_url": "https://www.fhwa.dot.gov/federal-aidessentials/companionresources/02projcloseout.pdf",
      "source_year": "2012",
      "sample_or_method": "FHWA guide text",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#fhwa-2012-federal-aid-project-records-3-years",
      "cite_as": "Cite as: Contracts Connected, \"Federal-aid project record retention,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#fhwa-2012-federal-aid-project-records-3-years. Original source: U.S. Federal Highway Administration, Federal-aid Essentials for Local Public Agencies, Project Closeout (companion guide to video, August 2012), 2012. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "gao-2017-army-over-age-contracts",
      "title": "Army over-age contracts due for closeout, fiscal 2017",
      "section": "Federal contract closeout backlogs",
      "kind": "figure",
      "statistic": "Army reported 231,627 over-age contracts, about 86 percent of those due for closeout (fiscal 2017)",
      "wording": "GAO reported that the Army had a total of 231,627 firm-fixed-price and flexibly-priced over-age contracts, about 86 percent of the total contracts due for closeout, based on its fiscal year 2017 third quarter review.",
      "limit": "All Army contract types, not construction only. A 2017 snapshot. GAO says the Army 'does not have the data broken out by contract-type.'",
      "source_publisher": "U.S. Government Accountability Office",
      "source_title": "Federal Contracting: Additional Management Attention and Action Needed to Close Contracts and Reduce Audit Backlog (GAO-17-738)",
      "source_url": "https://www.gao.gov/assets/gao-17-738.pdf",
      "source_year": "2017",
      "sample_or_method": "GAO review of five agencies (DOD, HHS, DHS, Justice, State), published September 2017",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#gao-2017-army-over-age-contracts",
      "cite_as": "Cite as: Contracts Connected, \"Army over-age contracts due for closeout, fiscal 2017,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2017-army-over-age-contracts. Original source: U.S. Government Accountability Office, Federal Contracting: Additional Management Attention and Action Needed to Close Contracts and Reduce Audit Backlog (GAO-17-738), 2017. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "gao-2017-dcaa-audit-days",
      "title": "Days for DCAA to finish an incurred cost audit, fiscal 2016",
      "section": "Federal contract closeout backlogs",
      "kind": "figure",
      "statistic": "DCAA took 885 days on average from adequate proposal to finished audit in fiscal 2016: 747 days waiting, 138 days of audit work",
      "wording": "GAO found that in fiscal 2016, the Defense Contract Audit Agency averaged 885 days from an adequate incurred cost proposal to a finished audit. Proposals waited an average of 747 days before audit work began, and the audit work took about 138 days.",
      "limit": "Applies to contracts that need an incurred cost audit before final indirect rates are set, mostly cost-type work, not fixed-price vendor jobs. Fiscal 2016 data. About 45 percent of proposals in fiscal 2014 to 2016 were inadequate.",
      "source_publisher": "U.S. Government Accountability Office",
      "source_title": "Federal Contracting: Additional Management Attention and Action Needed to Close Contracts and Reduce Audit Backlog (GAO-17-738)",
      "source_url": "https://www.gao.gov/assets/gao-17-738.pdf",
      "source_year": "2017",
      "sample_or_method": "GAO analysis of DCAA data",
      "geography": "US",
      "status": "Reviewed",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#gao-2017-dcaa-audit-days",
      "cite_as": "Cite as: Contracts Connected, \"Days for DCAA to finish an incurred cost audit, fiscal 2016,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2017-dcaa-audit-days. Original source: U.S. Government Accountability Office, Federal Contracting: Additional Management Attention and Action Needed to Close Contracts and Reduce Audit Backlog (GAO-17-738), 2017. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "gao-2012-dcma-contracts-awaiting-closeout",
      "title": "DCMA contracts awaiting closeout, July 2012",
      "section": "Federal contract closeout backlogs",
      "kind": "figure",
      "statistic": "DCMA had about 36,000 contracts awaiting closeout in July 2012, 28,000 of them awaiting final indirect cost rates",
      "wording": "GAO reported that as of July 2012 the Defense Contract Management Agency had approximately 36,000 contracts awaiting closeout, including 28,000 awaiting final indirect cost rates. The Army announced a goal of closing over 475,000 over-age contracts by September 2014.",
      "limit": "2012 data, all contract types, one agency plus an Army goal. The Army goal is a target, not an outcome.",
      "source_publisher": "U.S. Government Accountability Office",
      "source_title": "Defense Contracting: DOD Initiative to Address Audit Backlog Shows Promise, but Additional Management Attention Needed to Close Aging Contracts (GAO-13-131)",
      "source_url": "https://www.gao.gov/assets/gao-13-131.pdf",
      "source_year": "2012",
      "sample_or_method": "GAO analysis of DCMA data and interviews, December 2012",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#gao-2012-dcma-contracts-awaiting-closeout",
      "cite_as": "Cite as: Contracts Connected, \"DCMA contracts awaiting closeout, July 2012,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2012-dcma-contracts-awaiting-closeout. Original source: U.S. Government Accountability Office, Defense Contracting: DOD Initiative to Address Audit Backlog Shows Promise, but Additional Management Attention Needed to Close Aging Contracts (GAO-13-131), 2012. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "gao-2011-iraq-and-afghanistan-closeout-backlog",
      "title": "Iraq and Afghanistan contracts to review for closeout",
      "section": "Federal contract closeout backlogs",
      "kind": "figure",
      "statistic": "At least 58,000 Iraq contracts to review for closeout; about 90 percent of those with data already over age; 42,000 Afghanistan backlog",
      "wording": "GAO reported in 2011 that DOD had to review and possibly close at least 58,000 Iraq contracts from fiscal years 2003 to 2010, that about 90 percent of the limited contracts with closeout data were over age, and that the Afghanistan backlog of over 42,000 contracts suggested the causes were unresolved.",
      "limit": "Contingency contracts in Iraq and Afghanistan, not construction only, and the 90 percent covers only contracts where DOD could provide data. 2011 report.",
      "source_publisher": "U.S. Government Accountability Office",
      "source_title": "Contingency Contracting: Improved Planning and Management Oversight Needed to Address Challenges with Closing Contracts (GAO-11-891)",
      "source_url": "https://www.gao.gov/assets/gao-11-891.pdf",
      "source_year": "2011",
      "sample_or_method": "GAO audit of DOD closeout data, September 2011",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#gao-2011-iraq-and-afghanistan-closeout-backlog",
      "cite_as": "Cite as: Contracts Connected, \"Iraq and Afghanistan contracts to review for closeout,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#gao-2011-iraq-and-afghanistan-closeout-backlog. Original source: U.S. Government Accountability Office, Contingency Contracting: Improved Planning and Management Oversight Needed to Address Challenges with Closing Contracts (GAO-11-891), 2011. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "dod-ig-2024-afghanistan-contingency-contracts-closeout",
      "title": "Afghanistan contingency contracts not closed out as required",
      "section": "Federal contract closeout backlogs",
      "kind": "figure",
      "statistic": "DoD IG: 15 of 20 closed Afghanistan contingency contracts (75 percent) were not closed out as required",
      "wording": "A February 2024 DoD Inspector General audit of 30 Afghanistan contingency contracts found officials did not close out 15 (75 percent) of the 20 closed contracts and would not close at least 4 (40 percent) of the 10 open contracts as required. Half of the 20 closed contracts (10) lacked all closeout steps or the closeout statement. DoD missed a chance to reprogram at least $3.7 million in canceled funds.",
      "limit": "Thirty contingency contracts, not construction. The agency lists audit delays, staff turnover, tracking failures and competing priorities as causes. Not a rate for DoD as a whole.",
      "source_publisher": "U.S. Department of Defense Office of Inspector General",
      "source_title": "Audit of DoD Afghanistan Contingency Contracts Closeout (DODIG-2024-059)",
      "source_url": "https://media.defense.gov/2024/Feb/26/2003399973/-1/-1/1/DODIG-2024-059%20SECURE.PDF",
      "source_year": "2024",
      "sample_or_method": "30 contracts reviewed (20 closed, 10 open)",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#dod-ig-2024-afghanistan-contingency-contracts-closeout",
      "cite_as": "Cite as: Contracts Connected, \"Afghanistan contingency contracts not closed out as required,\" Contracts Connected Data, https://contractsconnected.com/data/construction-closeout-statistics#dod-ig-2024-afghanistan-contingency-contracts-closeout. Original source: U.S. Department of Defense Office of Inspector General, Audit of DoD Afghanistan Contingency Contracts Closeout (DODIG-2024-059), 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "far-2026-6-month-closeout-claim-check",
      "title": "Claim check: \"Federal contracts must be closed out within 6 months\"",
      "section": "Claim checks: two closeout claims stated as one number",
      "kind": "claim_check",
      "statistic": "6 months",
      "wording": "Federal contracts must be closed out within 6 months",
      "limit": "The 6 months does not apply to every contract file, and the rule says 'should,' not 'must.'",
      "source_publisher": "Acquisition.gov (Federal Acquisition Regulation)",
      "source_title": "FAR 4.804-1 Closeout by the office administering the contract",
      "source_url": "https://www.acquisition.gov/far/4.804-1",
      "source_year": "2026",
      "sample_or_method": "",
      "geography": "",
      "status": "Claim check: not cited as a finding",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#far-2026-6-month-closeout-claim-check",
      "cite_as": "",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "far-2017-retainage-at-closeout-30-days-claim-check",
      "title": "Claim check: \"A contractor must be paid retainage 'at closeout' within 30 days\"",
      "section": "Claim checks: two closeout claims stated as one number",
      "kind": "claim_check",
      "statistic": "30 days",
      "wording": "A contractor must be paid retainage 'at closeout' within 30 days",
      "limit": "No single number applies across the country.",
      "source_publisher": "Acquisition.gov (Federal Acquisition Regulation)",
      "source_title": "FAR 52.232-27 Prompt Payment for Construction Contracts (Jan 2017)",
      "source_url": "https://www.acquisition.gov/far/52.232-27",
      "source_year": "2017",
      "sample_or_method": "",
      "geography": "",
      "status": "Claim check: not cited as a finding",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/construction-closeout-statistics#far-2017-retainage-at-closeout-30-days-claim-check",
      "cite_as": "",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    }
  ]
}