Excavation / trenching competent-person checklist

15-point daily inspection before trench entry. Soil class, protective systems, atmospheric testing, egress.

ExcelWordPDF

The 15-point daily inspection OSHA 1926 Subpart P requires before workers enter any trench. Soil classification, protective system verification, atmospheric testing, egress, water controls, and every trigger that stops work until conditions are corrected.

Why every site with an active trench needs a documented competent-person inspection

Trenching is one of OSHA’s Focus Four fatal hazard categories, right alongside falls, struck-by, and electrocution, and it earns that designation because trench collapses kill fast, without warning, and with almost no margin for error once the soil moves. A cubic yard of dirt weighs roughly 3,000 pounds. A standard 4-foot-wide, 5-foot-deep trench can collapse and bury a worker in under a second. The worker doesn’t have time to move. The rescuer who jumps in to help often becomes the second fatality. OSHA 29 CFR 1926.651(k) makes the rule clear: a competent person must inspect every trench and excavation before workers enter each shift, after every rainstorm or other weather event that could affect conditions, when soil conditions visibly change, and after every unplanned occurrence that could increase hazard. That’s not a checklist item you delegate to the junior PE on the job. OSHA defines a competent person for excavation work as someone who can identify existing and predictable hazards, is authorized to take immediate corrective action, understands soil classification under Appendix A and B of Subpart P, and can evaluate the adequacy of protective systems. On most jobs that person is the site superintendent, the safety officer, or a designated competent-person appointee who’s taken the formal training. The designation has to be on paper; the inspection has to be documented; the corrective action has to be logged before workers go down.

The problem we see on active federal and commercial sites: the competent person exists on the org chart, the training certificate is somewhere in the job file, and the inspection “happens” in the sense that someone walked the trench before the crew started work. But the documentation is a blank sign-in sheet or a three-word entry in a paper log that nobody can find three weeks later when the contracting officer, the inspector, or the plaintiff’s attorney asks what was checked on the morning a worker was injured. No soil classification recorded. No protective system type documented. No atmospheric test results. No notation of who was the competent person on duty that day, what they found, and what corrective action they took or deferred.

We built this checklist after years of watching project teams treat the competent-person inspection as a ritual rather than a record. The 15 points on this list are the things OSHA actually cites primes and subs for when a trench incident triggers an investigation: failure to document soil classification before excavation, failure to verify the protective system matched the soil class and trench geometry, failure to record atmospheric testing results before entry, failure to confirm egress access within 25 lateral feet of every worker, failure to document water-accumulation controls before entry, and failure to record the re-inspection trigger events (rain, vibration, visible soil movement) that required a fresh assessment. Each of those is a citable violation under Subpart P. Each of them is also, more importantly, a failure point that kills workers.

Use this daily. Fill it out before entry on every shift. Keep the completed forms in the project’s safety file for the duration of the project plus three years. If a trench fails inspection, stop work, note the deficiency, document the corrective action required, and don’t clear entry until conditions are corrected and re-inspected. That’s the job.

Who this checklist is for

  • Mid-market general contractors managing excavation subcontractors on commercial and civil projects where OSHA 1926 Subpart P applies
  • Prime contractors on federal and federally-assisted construction where EM 385-1-1 excavation requirements layer on top of OSHA Subpart P
  • Specialty subcontractors, utility, civil, pipeline, and site-work subs, who perform excavation work and need documented competent-person compliance
  • Site Safety and Health Officers (SSHOs) on federal jobs required to maintain daily inspection records as part of the Accident Prevention Plan
  • Project superintendents who are designated as the competent person for excavation work and need a defensible daily inspection record
  • Safety directors maintaining standardized inspection documentation across multiple active projects

If you’re on a federal project, this inspection record sits inside the broader Site Safety and Health Plan required by EM 385-1-1. Start with the Federal site safety plan (EM 385-1-1) template and reference this checklist as the trenching daily inspection artifact. For the per-activity breakdown, the Activity hazard analysis (AHA) template carries excavation-specific steps, hazards, and controls down to the crew level.

The 15-point daily competent-person inspection

The checklist covers 15 daily competent-person verifications before any worker enters a trench or excavation under OSHA 1926 Subpart P.

  1. Competent person identity and designation documented. Record the full name of the designated competent person performing this inspection and their qualification basis (formal competent-person training course, documented experience, or both). OSHA 1926.651(k)(1) requires the inspection to be performed by a competent person, not just any supervisor present on site. If the designated competent person is unavailable, work in the excavation stops until a qualified replacement is documented. A blank “inspector name” field is itself a citable deficiency.
  2. Soil classification determined and recorded per Appendix A and B. Classify the soil as Type A, Type B, or Type C using the visual and manual tests defined in Appendix A and B to Subpart P: thumb penetration test, dry strength test, plasticity test, fissure check, and observation of layering, moisture seepage, and vibration sources. Record the classification and the tests performed, not just the conclusion. OSHA citation language typically reads “employer failed to document the basis for soil classification”. The classification alone without the supporting test observations doesn’t satisfy the standard.
  3. Protective system type verified against soil class and trench geometry. Confirm the protective system in place (sloping, benching, shoring, or shielding) matches the classified soil type and the actual trench dimensions. Sloping angles are dictated by soil class: Type A maximum 3/4:1 (53°), Type B 1:1 (45°), Type C 1½:1 (34°). Tabulated shoring and shielding data must be on site, and the actual trench depth and width must fall within the manufacturer’s or engineer’s specifications. A shield approved for Type B soil in an 8-foot trench is not automatically compliant in a 12-foot trench or after soil classification downgrades to Type C from rain.
  4. Atmospheric testing completed before entry and results recorded. Test the atmosphere in the trench for oxygen content (acceptable range 19.5%–23.5%), lower explosive limit (must be below 10% of LEL before entry), and toxic gases (particularly CO, H₂S, and any project-specific contaminants from nearby utilities, industrial history, or chemical storage). Document meter type, calibration date, readings at top, middle, and bottom of trench, and tester’s name. Atmospheric testing is required before entry regardless of trench depth when there’s any reason to suspect atmospheric hazard, and utilities work, old fill, and proximity to fuel storage are all “any reason to suspect.”
  5. Water accumulation controls verified before entry. Inspect for and document any evidence of water in the trench bottom or walls: standing water, seepage, saturated soil, or discoloration indicating subsurface flow. If water is present, document the control method in use, pumping with sloped trench bottom, controlled drainage, or dewatering wells, and confirm the method is actively working before clearing entry. OSHA 1926.651(h) prohibits entry into any trench with accumulated water unless adequate precautions are taken. “We’ll pump it as we go” is not adequate documentation.
  6. Surcharge load setback distances verified. Walk the perimeter and document the location and type of all surcharge loads: excavated spoil, construction materials, equipment, and vehicles. Excavated spoil must be kept at least 2 feet from the edge of the excavation per 1926.651(j)(2). Heavy equipment and material stockpiles beyond the 2-foot minimum must still be evaluated for the additional load they impose on trench walls. A loaded concrete truck 10 feet from a Type B trench changes the soil dynamics. Record the setback distance measured for spoil piles and the location of any equipment operating near the trench edge.
  7. Mobile equipment and traffic setback controls confirmed. Document the location of all mobile equipment operating near the trench (excavators, loaders, delivery vehicles, forklifts) and the barriers or stop-logs in place to prevent inadvertent encroachment. Where traffic is present, including internal site traffic, confirm barricading is adequate to prevent vehicles from approaching the trench edge without the operator’s awareness. Document whether flaggers are posted for any traffic-control scenario. Equipment vibration is one of the most common reclassification triggers for soil type during a shift. Record any equipment activity near the trench that could affect wall stability.
  8. Pedestrian and public protection barriers in place. Verify that barricades, fencing, or covers are in place on all sides of the excavation that are accessible to workers not involved in the excavation activity, public pedestrian traffic, or any other non-authorized persons. Per 1926.651(i), walkways and bridges provided over excavations must have standard guardrails. Document barrier type, coverage, and any gaps. An open, unmarked trench that a delivery driver walks into is a citation with no defense.
  9. Ingress and egress within 25 lateral feet of every worker. Confirm that a ladder, ramp, or stairway is accessible to every worker in the trench within 25 lateral feet of travel, per 1926.651(c)(2). Count and document the number of egress points, their type (ladder, ramp, or steps), their condition (secure at top, extending 3 feet above grade for ladders), and the measured lateral distance to the farthest worker position. In a long utility trench where crew spreads out, the 25-foot rule requires multiple egress points. A single ladder at one end of a 60-foot trench is non-compliant.
  10. Fall protection at walkways, bridges, and excavation crossings. Inspect any pedestrian or worker crossing points over the excavation and confirm standard guardrail systems are in place (top rail at 42 inches ±3 inches, mid-rail, toe board). Document the number of crossing points, their location, and guardrail condition. This applies to temporary plywood crossings, pipe or steel bridging, and any other improvised crossing structure. The guardrail requirement doesn’t relax because the crossing is temporary.
  11. Daily inspection cadence and trigger-event re-inspection documented. Record the time of this inspection and confirm when the previous inspection was performed (date, time, competent person). If any trigger events occurred since the last inspection, rain, adjacent blasting or pile driving, unexpected water infiltration, utility strike, visible soil cracking or slumping, document the event and the re-inspection it triggered. OSHA 1926.651(k)(2) requires inspections “as needed throughout the shift” when conditions change. One morning inspection with no notation of afternoon trigger events is incomplete documentation on a day with a 2:00 p.m. thunderstorm.
  12. Weather and vibration trigger assessment. Document current weather conditions and any weather events since the last inspection that could affect soil stability: rainfall (note duration and intensity), temperature-driven freeze/thaw cycles, high-wind events affecting shoring. Document any active vibration sources on or adjacent to the site: pile driving, demolition, heavy compaction, nearby roadway traffic on soft soil. Vibration from any source can degrade soil classification from one type to another without visible surface change. The competent person must assess and re-classify if vibration has been significant.
  13. Training and competent-person sign-off captured. Obtain the competent person’s signature certifying the inspection was performed, the findings are accurate, and any noted deficiencies have been corrected or work has been suspended pending correction. Also confirm that all workers entering the trench have received site-specific excavation hazard awareness orientation (required under the Accident Prevention Plan on federal work; best practice on commercial work). The signature is the legally operative record. An unsigned inspection form is an unsigned document.
  14. Emergency response equipment present and accessible. Verify that rescue equipment appropriate for the depth and conditions is accessible at the trench: ladders, rope, retrieval line (for trench rescue), first aid kit, emergency contact numbers posted at the site entrance, and, if the trench depth or soil conditions create entrapment risk, a non-entry rescue system (rope and harness rated for rescue load). Document what’s present and its condition. Non-permit excavations still require emergency-preparedness documentation under a responsible safety plan.
  15. Suspension trigger and correction log. If any inspection item above is marked as deficient, document the specific deficiency, the corrective action required, the estimated time to correction, and whether work is suspended or continuing in unaffected portions of the trench while the deficiency is addressed. No worker may re-enter a deficient area until the competent person re-inspects and clears entry in writing. This field is the record that shows OSHA and any reviewer that deficiencies were identified, acted on, and cleared, not just noted and forgotten.

How to run the daily competent-person inspection

Run this checklist before the first worker enters the trench each shift. Assign one competent person per active trench per shift, not per project if multiple trenches are open. Work down the 15 items in order; don’t skip atmospheric testing because the trench looks clean or surcharge-load setbacks because the crew knows to stay back. Each item gets a mark: Pass, Fail, or N/A with a note.

  • Open the printed PDF version or the working Excel version with built-in checkboxes.
  • Work down the 15 items in order for the trench before any worker enters.
  • Mark each item: Pass, Fail, or
  • N/A. Any item marked
  • Fail stops work in the affected area immediately. Document the deficiency, the corrective action, and the estimated resolution time.
  • When a deficiency is corrected, re-inspect the specific failed item and clear entry in writing.
  • File the completed form in the project’s safety documentation binder. Keep every completed form for the life of the project plus three years.

For federal projects with EM 385-1-1 requirements, this form should be referenced in the Site Safety and Health Plan’s Trenching and Excavation Plan section as the daily inspection artifact.

Stop routing competent-person inspection forms through email

Each completed inspection form takes 10 minutes to fill out, photograph, email to the safety director, and file somewhere everyone can find it when OSHA shows up. Across five active trenches on two federal projects over a 90-day dig phase, that’s a lot of email threads with attachments named “trench-inspection-tue.jpg” and a project manager who can’t find last Tuesday’s form without calling three people. Contracts Connected’s Approval Workflows route completed inspection forms through the competent person, the SSHO, and the project manager automatically, version every submission, and keep the audit-trail file ready for the contracting officer or OSHA compliance officer the moment they ask, not after a 20-minute search through a shared drive.

For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.

Trenching has direct life-safety consequences. This checklist is a structural starting point, not a substitute for a site-specific competent person evaluation. Review the document with your safety officer or qualified safety professional before deploying on any live project.

Frequently asked questions about the excavation / trenching competent-person checklist

Who qualifies as a competent person for OSHA excavation work?

Under OSHA 29 CFR 1926 Subpart P, a competent person for excavation is someone who can identify existing and predictable hazards in the surrounding area, or working conditions that are unsanitary, hazardous, or dangerous to workers, and who has the authority to take prompt corrective measures to eliminate those hazards. For excavation specifically, that means understanding soil classification per Appendix A and B, knowing how to evaluate protective system adequacy, and being authorized to stop work. A competent person is designated by the employer, not self-designated by the worker. The designation and the training basis should be in writing in the project file before excavation starts.

Does every excavation require a competent-person inspection, even shallow ones?

Yes. OSHA 1926.651(k) applies to all excavations, not just trenches deeper than 5 feet (the depth at which protective systems become mandatory). A 3-foot excavation still requires a competent-person inspection before entry. The protective system requirements may differ by depth, but the inspection, soil classification, and atmospheric testing requirements apply regardless. The common field shortcut of treating any dig under 5 feet as inspection-exempt is incorrect and citable.

How often does the competent person need to inspect during a shift?

At minimum before workers enter each shift, but the standard requires inspection “as needed throughout the shift” whenever conditions change. Trigger events that require a re-inspection mid-shift include: any rainfall or storm event, any water accumulation or increased seepage, any evidence of soil movement (cracking, slumping, bulging), any nearby vibration activity (blasting, pile driving, heavy compaction), any equipment or vehicle inadvertently approaching the trench edge, and any utility strike or unexpected subsurface condition. “Before-shift only” is defensible in stable conditions on a calm day. On any day with rain, heavy equipment operating nearby, or visible soil changes, the competent person needs to be in the trench area and documenting throughout.

What’s the difference between sloping, shoring, and shielding as protective systems?

Sloping removes material to create a stable inclined slope on trench walls, eliminating the vertical cut. Shoring uses timber, hydraulic, or pneumatic systems to hold the trench walls in place, allowing a vertical or near-vertical cut. Shielding uses a trench box or other structure that protects workers from wall collapse by containing the collapse zone. It doesn’t prevent collapse, it protects the worker inside the box from being buried. The appropriate system depends on soil classification, trench depth and width, adjacent loads, and whether continuous dewatering is needed. On federal work, the engineer of record or a qualified person must approve the protective system selection before it’s used.

Are trench boxes always acceptable as the protective system?

A trench box (shield) is an OSHA-approved protective system when used within the manufacturer’s tabulated data for that specific shield. Meaning the trench depth, soil type, and surcharge loads are within the shield’s rated specifications. A shield rated for 12-foot depth in Type B soil does not become compliant by pulling it up 2 feet in a 14-foot trench. The shield must also be installed before workers enter, not lowered in after the crew is already at the bottom. The competent person must verify the shield’s make, model, rated capacity, and actual installation depth against the manufacturer’s specifications at each inspection. On federal projects, USACE requires documented evidence that the shield system was selected and installed per engineering specifications.

What should be done if soil classification changes during excavation?

Stop work in the affected area immediately, re-classify the soil using the Appendix A and B tests for the current conditions, and determine whether the existing protective system is adequate for the new classification. If it is not, for example, a Type B trench box rating is no longer sufficient after classification downgrades to Type C, workers must exit the trench, the protective system must be upgraded to match the new classification, and the competent person must inspect and clear re-entry before work resumes. Document the original classification, the trigger for re-classification, the new classification basis, the system change made, and the re-entry clearance in the inspection log. This is one of the most common causes of serious injury in trench work: soil that starts the day as Type B and becomes Type C after a morning rainstorm, with no re-inspection and no system upgrade.

Where this document lives in the system