Subcontract package checklist (federal)

11 required documents for every federal subcontract. SF-1413, Miller Act bonds, SAM.gov, FAR flow-downs.

ExcelWordPDF

The 11 documents every federal prime must collect and verify before a subcontractor mobilizes. CC Federal Subcontract Package Checklist

Why federal primes need a complete subcontract package on day one

You execute the subcontract. You send the package to your new sub. Clean cover letter, PDF attached, DocuSign link. Then you wait. What comes back over the next two weeks is not a clean package. It is a scanned W-9 from 2019 with a different legal name than SAM.gov. A COI that lists your project address wrong. An SF-1413 that someone signed but nobody dated. And a certified payroll setup email that asks, “What’s a WH-347?” Federal subcontracting is not harder than commercial work because the forms are longer. It is harder because the consequences of a missing checkbox arrive six months after award, during an agency audit, when you have no standing and no good options.

We built this checklist because the team that ran operations on a federal GC processed hundreds of subcontract packages a year. The pattern was always the same: primes who collected a complete package at execution had clean audits. Primes who chased docs piecemeal had last-minute fire drills before every contracting-officer review. The difference between those two outcomes is almost entirely what you require on day one.

Federal subcontracts carry requirements that commercial packages don’t touch. The Miller Act means your sub needs bonds on anything over $150,000 or you are exposed. The Davis-Bacon requirement means a certified payroll cadence has to be agreed to at the start, not discovered at the first payroll period. FAR 52.222-6 flow-downs are not optional reading for federal primes: the contract requires them, the agency will ask about them, and your sub cannot claim ignorance if you flowed them down in writing at execution.

This checklist covers the full federal subcontract package. Not just the documents everyone remembers, but the ones that kill audits when they are missing: SF-1413, SAM.gov verification against the exclusion list, small-business classification on record, EEO certification, Buy American acknowledgment. Eleven items. None of them complicated. All of them required.

Send the package clean. Collect documents before the sub mobilizes. File everything by subcontract. When the contracting officer asks for the package 18 months from now, you open a folder and hand it over. That is what this checklist makes possible.

Who this checklist is for

  • Federal general contractors managing prime contracts with subcontracting requirements
  • Prime contractors on Davis-Bacon projects required to verify sub compliance at the package stage
  • 8(a) prime contractors subcontracting scope to other small businesses
  • Contracts administrators who collect, review, and file subcontract packages across multiple federal projects
  • Project managers responsible for sub onboarding before mobilization on federal work

If you are looking for the commercial version without the federal-specific requirements, see the Subcontract package checklist (commercial).

The 11-point federal subcontract package

The checklist covers 11 items every federal prime must collect and verify before a sub mobilizes.

  1. Executed subcontract with FAR clause flow-downs attached. The signed subcontract is the foundation of the package, but on a federal job it is not complete without the required FAR clause exhibits. Mandatory flow-downs include 52.222-26 (Equal Opportunity), 52.222-6 (Davis-Bacon), and any contract-specific clauses the prime is required to pass through. File the exhibit separately from the body of the agreement so amendments to either document don’t create cross-reference confusion.
  2. SF-1413 Statement and Acknowledgment signed and dated. On covered Davis-Bacon construction work, the SF-1413 is required from every first-tier subcontractor before work begins. The form documents the sub’s acknowledgment of Davis-Bacon obligations and certifies their payroll practices. Unsigned or undated forms don’t satisfy the requirement. Collect before execution, not at the first payroll review.
  3. W-9 with TIN matching SAM.gov registration. A W-9 with a tax identification number that does not match the sub’s SAM.gov registration is a problem you will catch in the first pay cycle, not at the right time. Pull the sub’s SAM.gov entity record and verify the legal name, TIN, and CAGE code match the W-9 exactly. Mismatches create 1099 compliance issues and can trigger payment holds.
  4. Certificate of insurance meeting federal project limits. COI requirements on federal projects often exceed commercial minimums. Verify that the coverage types, limits, endorsements, and additional insured language match what the prime contract requires, not just what the sub’s standard certificate shows. The COI must name the correct project and list the United States as an additional insured where required. Expired certificates at audit are among the most common findings.
  5. Miller Act payment and performance bonds for subcontracts over $150,000. The Miller Act requires payment and performance bonds on federal construction subcontracts where the subcontract value exceeds $150,000. Unlike commercial bonding, the federal threshold is fixed by statute, not by contract. Collect the bond originals from the sub’s surety before mobilization. Verify the bonding company is listed on the Treasury Department’s approved surety list (Circular 570).
  6. Davis-Bacon prevailing wage acknowledgment. Beyond the SF-1413, a separate acknowledgment that the sub understands the specific wage decision applicable to this contract is good practice and often required. The acknowledgment should reference the wage decision number and version, confirm the sub’s obligation to pay no less than the listed rates, and confirm that the sub will submit WH-347 forms on the weekly schedule agreed to at execution.
  7. Certified payroll submission cadence agreed and documented. WH-347 submissions are due weekly, within seven days of the regular payroll period. Before the sub mobilizes, confirm in writing: the day of the week payroll closes, the day WH-347 forms are due to the prime, and the method of submission. A sub who doesn’t know this cadence when they start will be behind on the first Friday. Getting it in writing at package execution creates an enforceable standard and protects the prime if the sub falls behind.
  8. Small business and DBE classification documented. Federal primes with subcontracting plans are required to track and report small business, 8(a), HUBZone, WOSB, VOSB, and DBE participation. Before the sub begins work, verify their current size and socioeconomic classification in SAM.gov, confirm it matches the representation on the subcontract, and record it in the project file. Classifications can change at annual recertification, so note the date of verification.
  9. EEO and Affirmative Action compliance certification. FAR 52.222-26 flows down to subcontractors. Collect the sub’s signed EEO certification before execution, and confirm that any sub with 50 or more employees and a contract of $50,000 or more has a current Affirmative Action Plan on file. Documenting collection at package execution removes any ambiguity about when the obligation was communicated and accepted.
  10. Buy American Act compliance acknowledgment. On federal contracts with Buy American requirements, the prime’s flow-down obligation includes getting a written acknowledgment from the sub that materials supplied will comply. This is not a clause most subs have memorized. A specific, signed acknowledgment referencing the project and the relevant FAR clause creates a record that the prime discharged the flow-down requirement, which matters when the contracting officer reviews your subcontracting file.
  11. SAM.gov registration active, exclusions checked, NAICS code matching scope. Pull the sub’s SAM.gov entity record on the day of subcontract execution, not on the day of award. Registrations expire. The exclusion list catches suspended and debarred firms. The NAICS code on the record should match the scope of work the sub is performing under this contract. Print or screenshot the SAM.gov result and file it with the package, dated, so there is a clear record that the prime verified compliance before award.

How to run the checklist at execution

Start the package at the point of subcontract negotiation, not after execution. Send the sub a requirements letter that lists every document on this checklist and specifies deadlines before mobilization. When documents arrive, work down the list in order: verify each item against the applicable standard, mark it complete or flag it for correction, and file it in the project’s subcontract folder indexed by sub name. Do not allow a sub to mobilize until every item is collected and verified. A signed subcontract with an incomplete package is a problem you will fix under pressure later. Fix it before the sub starts.

Stop chasing documents after the sub mobilizes

A complete federal subcontract package collected at execution takes two hours. The same package collected piecemeal over three months of follow-up emails takes forty. Contracts Connected reads incoming subcontract documents, flags missing items against your package requirements, and tells you what is still needed before you approve the sub to start. Same checklist, automated from the moment a document hits your inbox.

For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.

Frequently asked questions about the subcontract package checklist

What is the difference between a federal and a commercial subcontract package?

A commercial subcontract package typically covers the executed agreement, W-9, COI, scope exhibit, and lien waiver template. A federal package adds four major layers: SF-1413 acknowledgment, Miller Act bonding requirements tied to a statutory dollar threshold, Davis-Bacon and certified payroll obligations with specific submission cadences, and FAR clause flow-downs that the prime is contractually required to pass to every covered subcontractor. SAM.gov verification, EEO certification, and Buy American acknowledgment are also standard federal requirements that rarely appear in commercial packages.

When is the Miller Act bond required on a subcontract?

The Miller Act requires payment and performance bonds on federal construction subcontracts where the subcontract value exceeds $150,000. This threshold is set by statute and applies regardless of what the prime contract or the prime’s bonding arrangement says. The bond must be issued by a surety on the Treasury Department’s approved list (Circular 570). Primes who waive or fail to collect the bond above the threshold expose themselves to direct liability to lower-tier suppliers and laborers.

Do all FAR clauses flow down to subcontractors?

No. Only mandatory flow-down clauses and contract-specific clauses designated by the contracting officer for flow-down are required to pass through to subcontractors. Mandatory flow-downs include clauses like 52.222-6 (Davis-Bacon), 52.222-26 (Equal Opportunity), and 52.222-40 (Notification of Employee Rights). Other clauses may be required by the specific contract. Primes should review their prime contract and include a flow-down exhibit listing each applicable clause so there is no ambiguity about what the sub has accepted.

Is SF-1413 required for every federal subcontractor?

SF-1413 is required for every first-tier subcontractor performing work on a covered Davis-Bacon construction contract. It must be collected before work begins, not after. The form documents the sub’s acknowledgment of prevailing wage obligations and certifies that their employees will be paid no less than the Davis-Bacon rates applicable to the contract. Second-tier and lower-tier subs are generally not required to submit SF-1413 directly to the prime, but the first-tier sub is responsible for collecting similar acknowledgments from their own subs.

How do I verify a subcontractor’s SAM.gov registration before award?

Go to sam.gov, search the sub’s legal name or Unique Entity Identifier (UEI), and confirm that the record shows active registration, no active exclusions, and an unexpired registration date. Check that the entity’s legal name and TIN match the W-9 the sub provided. Verify that the NAICS code on the record includes or is compatible with the scope of work. Print or screenshot the search result with the date visible and file it with the subcontract package. Repeat this check if the subcontract is not executed within 90 days of the original verification.

What happens if a sub’s certified payroll is late or missing?

The prime is responsible for collecting and reviewing WH-347 forms from every active subcontractor, weekly. If a sub fails to submit on time, the contracting officer can withhold payment from the prime until the sub comes into compliance. The prime can pass that withholding to the sub per contract terms, but the prime-agency relationship is the one that takes the hit. Documenting the agreed submission cadence at package execution gives the prime an enforceable standard and a clear record that the obligation was communicated before work began.

Where this document lives in the system
Back-Office System · Contracts Connected