Change-order request template (sub to GC)

14-field sub-to-GC change-order request covering originating direction, cost breakdown, schedule impact, and reservation of rights.

ExcelWordPDF

The 14-field request a subcontractor sends a GC to turn extra work into an approved, payable change order. With nothing easy for the GC to reject and nothing easy to negotiate away.

Why subcontractors need a change-order request template

A superintendent points at a wall and says “we need that moved, start now, we’ll paper it later.” You move it. You burn two crews and a week of float. And four months later, when you bill for it, the GC’s PM looks at your invoice and says, “I don’t have a signed change order for that, so I can’t pay it.” Now you’re the one holding a five-figure hole, and the only thing you have to point to is a text message and your foreman’s memory of a conversation on a loud jobsite.

That is the change-order trap, and subs fall into it on almost every project. The work is real. The direction was real. But the request that should have converted that direction into a payable change order was either never written, written too late, or written so vaguely that the GC could pick it apart line by line. “Do the work, lose the money” is not a rare outcome. It is the default outcome when a sub treats the change-order request as paperwork to catch up on instead of the document that protects the claim.

Here is the part most subs miss. There is no standard, fill-in-the-blank form for this. AIA publishes for the executed change order, for a construction change directive, and for the architect’s proposal request. ConsensusDocs publishes its own 202 change order. But all of those are owner, architect, and contractor-tier instruments. None of them is a clean form a subcontractor uses to submit a priced change request up to the GC. So subs improvise. They write a quick email, attach a one-line quote with a lump-sum number and no backup, and hope the GC treats it as a formal request. It usually doesn’t. This template fills that gap. It is the structured request a subcontractor sends to a general contractor to document a change in scope, tie it back to the direction that caused it, break the cost down so the number is defensible, state the schedule impact, and preserve the right to claim cumulative delay and inefficiency later. It is built to do one job: turn extra work into an approved, payable change order, with enough detail that the GC has nothing easy to reject and nothing easy to negotiate away.

The cost of skipping it is not theoretical. A vague request gets sat on. A late request gets challenged as a waiver. An unpriced request gets “approved in concept” and then ground down at closeout when you have no bargaining position left. The fifteen minutes it takes to fill this out correctly the first time is the cheapest insurance a sub will ever buy against doing the work and eating the cost.

Who this template is for

  • Specialty subcontractors (electrical, mechanical, framing, drywall, concrete, glazing, finishes) submitting priced change requests up to the GC
  • Project managers and project engineers at subcontracting firms who own change-order origination and pricing
  • Mid-market general contractors who want their subs to submit changes in a consistent, reviewable format instead of one-line emails
  • Estimators building the labor, material, and equipment breakdown that supports the requested number
  • Office managers and contract administrators at sub firms who track which requests are out, approved, or stuck and need the paperwork to be clean

The 14-field change-order request template

The template carries 14 fields, the set a real change-order request needs to convert extra work into a payable change order. Each field exists to make the request harder for the GC to reject and easier for the GC to approve and pay.

  1. Project and contract identifiers. Capture the project name, the project address, the GC’s name, the owner’s name, and your subcontract number and date. These tie the request to the specific contract it modifies and to the specific schedule of values your billing runs against. A request that floats free of a contract number is the first thing a GC’s PM flags as incomplete, and it slows down everything downstream.
  2. COR number and date submitted. Assign your own sequential change-order-request number (for example, COR-007) and record the date you submit it. The number is how both sides track the request through review, and it is what you reference on the eventual pay application and subcontract change order. The submission date is just as important: it is the proof that you raised the change in real time, which matters if the GC later argues you sat on it or waived it.
  3. Originating direction reference. Name the document or event that caused the change and cite it precisely: the RFI number, the architect’s supplemental instruction (ASI), the proposal request, the owner directive, the field directive, or the differing-site-condition notice. If the direction was verbal, say so plainly and name who gave it, when, and where. This field is the spine of the request. A change order with no traceable origin is the easiest kind for a GC to reject, and a verbal direction you documented the same day is worth far more than one you reconstruct at closeout.
  4. Description of the changed scope. Describe in plain language what is being added, deleted, or modified, and how it differs from your original contracted scope. Be specific enough that someone who was not on the jobsite can understand exactly what work the number covers. Vague descriptions (“additional work per field conditions”) invite the GC to narrow what they think they approved, then dispute the rest when you bill it.
  5. Cause and origin classification. Classify why the change happened: design change, owner-directed addition, differing site condition, code or inspector requirement, errors or omissions in the documents, or coordination conflict with another trade. The classification matters because it points to who is responsible and which contract mechanism applies. A differing site condition and an owner-directed scope add follow different entitlement paths, and naming the cause up front frames the entitlement argument before the GC frames it against you.
  6. Detailed labor breakdown. List the labor by classification, showing estimated hours times the bare hourly rate, then the burden (taxes, insurance, fringe, and any prevailing-wage premium) applied on top. Do not bury labor in a single lump-sum line. The detailed build-up is what makes the number defensible when the GC’s PM or the owner’s reviewer pushes back, and it is the difference between a request that gets negotiated on its merits and one that gets dismissed as a guess.
  7. Materials and equipment breakdown. Itemize the added materials with quantities and unit prices, and list owned or rented equipment with rates and durations. Attach supplier quotes where you have them. A clean materials line with backing quotes is hard to argue with; a round-number “materials: $8,000” with nothing behind it is the first thing a reviewer crosses out, because it reads as padding even when it is honest.
  8. Lower-tier subcontractor costs. If the change pulls in your own subs or specialty vendors, capture their quoted amounts and attach their quotes. These costs flow through your request to the GC, so they need to be documented at the same standard you hold yourself to. Missing or undocumented lower-tier costs are a common reason a sub eats part of a change: the work got done, but the second-tier invoice never made it into the priced request.
  9. General conditions and indirect costs. Capture the project-level indirect costs the change drives: added supervision time, extended general conditions if the change stretches your duration, small tools, mobilization, or temporary facilities. These are real costs subs routinely forget to claim because they are not as visible as labor and material. If the change adds two weeks to your time on site, the supervision and general-conditions cost of those two weeks belongs in the request, not absorbed silently.
  10. Overhead and profit markup. State your overhead and profit percentage and apply it consistently with what your subcontract allows. Most subcontracts cap markup on changed work, often somewhere in the 10 to 15 percent range on self-performed work and a lower percentage on lower-tier costs, so cite the contract provision you are pricing against. Applying a markup the contract does not allow gets the whole request kicked back; applying the markup the contract does allow, and citing it, takes that argument off the table.
  11. Pricing method. State whether the request is a firm lump sum, time-and-materials with a not-to-exceed cap, or unit price against the contract’s unit-price schedule. The method sets the expectation for what backup you owe: T&M means daily tickets signed in the field, unit price means verified field measurements, lump sum means the build-up sheet stands on its own. Naming the method up front prevents the common fight where the GC expected a fixed number and you expected to bill actuals.
  12. Schedule impact and time extension request. State the calendar days the change adds, whether it affects the critical path, and whether you are requesting a formal time extension. If the change pushes a milestone or your substantial-completion date, say so here and request the extension in writing. Subs that price the cost but stay silent on schedule routinely absorb delay they could have claimed, and a change order that grants the money but not the time can leave you exposed to liquidated damages you did not cause.
  13. Supporting documentation list. List and attach everything that backs the request: supplier and lower-tier quotes, photographs of the condition, field directives, daily reports, timesheets, marked-up drawings, and any inspector or owner correspondence. The documentation is what carries the request when memories fade and the people who were on site move on. A request with a complete backup package gets approved; a request with a number and a promise to “send backup if needed” gets parked.
  14. Reservation of rights and signature block. Include a reservation-of-rights statement preserving your right to claim cumulative impact, delay, and inefficiency costs that are not yet quantifiable, plus a clear note that this request is not authorization to proceed until the GC signs and returns it. Add the signature and approval-routing block for both sides. The reservation of rights keeps you from waiving downstream impact claims by accepting a direct-cost number now, and the not-an-authorization note protects you from being told you proceeded at your own risk.

How to use the template

Fill the request out the same day the change is identified, not at the end of the month and not at closeout. Start with the originating-direction field: name the RFI, ASI, directive, or verbal instruction that caused the change, and if it was verbal, document who said what and when before the details fade. Then build the cost from the bottom up in the editable DOCX form, labor first, then materials, equipment, lower-tier costs, general conditions, and markup, so the number is a build-up the GC can follow line by line rather than a lump sum they have to take on faith.

The DOCX is an editable fillable form that mirrors the printable PDF, so your PM can complete it on screen and route it for signature. The XLSX uses a cost-breakdown layout, one row per cost line, with columns for description, quantity, unit, rate, and extended amount, plus the burden, markup, and total roll-up at the bottom. Work the cost in the spreadsheet, then carry the total and the supporting detail into the request form. Attach the documentation list as you go rather than promising to send it later, then route the completed request to the GC with your COR number on it and log the date you sent it. Do not let your crews keep working changed scope on a verbal direction once the request is out; the request is your record, but a signed return is your authorization to proceed and your guarantee of payment.

Stop chasing change-order approvals through someone’s inbox

The request is only half the battle. The other half is getting it in front of the right reviewer, getting a signature back before your crews keep working at risk, and not letting a five-figure change sit unanswered in a GC’s inbox for three weeks while your float disappears. That is a workflow problem, not a form problem. Contracts Connected’s approval workflows route every change-order request to the right approver automatically, track where it sits, send the reminders so it never goes quiet, and capture the signed return as a clean record tied to the contract, so the gap between “we agreed to it” and “it’s approved and payable” closes in days instead of months. The template makes the request defensible. The approval workflow makes sure it actually gets approved.

For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.

Frequently asked questions about the change-order request template

Is there a standard AIA or ConsensusDocs form for a subcontractor’s change-order request?

Not for the request itself. AIA G701 is the executed change order, G714 is the construction change directive, and G709 is the architect’s proposal request, and all of them operate at the owner, architect, and contractor tier. ConsensusDocs publishes its own 202 change order at that same tier. AIA does offer G701S, a contractor-to-subcontractor change order variation, but that is an executed change order, not a request a sub submits upward. There is no widely adopted standard form for the sub-to-GC change-order request, which is exactly why subs end up improvising with one-line emails. This template gives that step a consistent structure so the request is complete, priced, and traceable the first time.

What’s the difference between a change-order request, a change order, and a construction change directive?

A change-order request (often called a COR or a change-order proposal) is what the sub submits: a priced, documented proposal to perform changed work, which is not yet approved or binding. A construction change directive (CCD, AIA G714) is an authorization from the owner and architect to proceed with changed work before the price and time are finalized, used to keep the job moving while the number gets negotiated. A change order (AIA G701, or ConsensusDocs 202) is the fully executed instrument that amends the contract sum and time once everyone signs. The request is the front of that sequence. Get it right and the change order at the end is just paperwork; get it wrong and you may never reach a signed change order at all.

Should I keep working if I only have a verbal direction?

Proceeding on a verbal direction is how subs end up doing the work and losing the money. If the GC’s superintendent tells you to proceed, the safest move is to submit the request immediately and get a signature back before your crews touch the changed scope, because the signed return is your authorization and your guarantee of payment. When schedule pressure forces you to start before paperwork catches up, document the verbal direction in writing the same day, name who gave it, send that documentation to the GC’s PM, and ask for written confirmation or a construction change directive. A contemporaneous written record of a verbal direction is far stronger than a reconstruction made months later, but it is still second-best to a signature before the work begins.

How detailed does the cost breakdown need to be?

Detailed enough that a reviewer who was not on the jobsite can follow how you got to the number. That means labor broken out by classification with hours, bare rate, and burden shown separately; materials itemized with quantities and unit prices and supplier quotes attached; equipment with rates and durations; lower-tier costs with their own quotes; and overhead and profit applied at the percentage your subcontract allows. A lump-sum number with no build-up is the easiest kind for a GC to reject or grind down, because there is nothing to defend it. A line-by-line build-up shifts the conversation from “is this number real” to “is this line correct,” which is the conversation you want.

What is a reservation of rights and why does the template include one?

A reservation of rights is a statement that preserves your right to claim additional impact costs that you cannot quantify yet, even though you are submitting a number for the direct costs now. It matters because a single change rarely shows its full cost at the moment you price it. Cumulative changes erode productivity, stack delays, and create inefficiency that only becomes measurable later. Without a reservation of rights, accepting a direct-cost number now can be argued as a full and final settlement of that change, waiving the impact and delay costs you discover at closeout. The reservation keeps that door open so you are not signing away claims you have not yet been able to measure.

How does pricing method affect what backup I need to provide?

The pricing method sets the documentation standard the GC will hold you to. A firm lump sum needs a complete build-up sheet that stands on its own, because once it is approved, the number is fixed regardless of actual cost. Time-and-materials, usually capped with a not-to-exceed amount, needs daily T&M tickets signed by the GC’s field representative as the work happens, because you are billing actuals. Unit price needs verified field measurements tied to the contract’s unit-price schedule. Naming the method on the request tells both sides what to expect and prevents the common dispute where the GC believed it approved a fixed price and you believed you were billing actual cost.

Where this document lives in the system
Back-Office System · Contracts Connected
Product bridge

Contracts Connected fills out each change order on your own form, runs it through your approvals and gets it signed, so the contract total stays current. Construction change order management software.

More in Contract package

All Contract package templates