Why builder’s risk verification matters
A water main lets go on the third floor of a half-built mid-rise at 2 a.m. By the time anyone gets there, water has run down four floors, soaked the framing, shorted out the freshly installed gear, and warped material that was staged for next week. The damage runs into seven figures. The general contractor is not panicked, because the project carries builder’s risk insurance and the certificate has been in the project file since the foundation was poured.
Then the adjuster starts asking questions. Was the off-site material that got ruined in temporary storage actually covered, or only material already installed on site? Water damage is covered, but was this the kind of water event the policy includes, or the kind it excludes? The damaged electrical gear had just finished a commissioning run. Does the policy cover loss during testing, or does it carve that out? And the deductible is not the routine number on a general liability policy. It is large, and the subcontract never said who eats it. The GC assumed the policy worked one way. It works another way, and the gap is now their problem.
That is the trap. Builder’s risk, also called course-of-construction insurance, is not liability insurance. It is first-party property insurance on the structure being built, the materials going into it, and the equipment on site during construction. It pays for direct physical damage to the work itself. Commercial general liability pays third parties when the insured is legally liable for bodily injury or property damage. They are different policies, doing different jobs, and a clean CGL certificate tells you nothing about whether the building under construction is protected against fire, wind, water, or theft.
Here is the part that catches even experienced reviewers. Builder’s risk does not show up on an ACORD 25. The ACORD 25 is the Certificate of Liability Insurance. Builder’s risk is property coverage, and property insurance is evidenced on a different form, the ACORD 28, Evidence of Commercial Property Insurance. If someone hands you an ACORD 25 to “prove builder’s risk,” the form itself is the wrong instrument. It cannot carry that proof.
And even the right form is a summary. Whether off-site storage is covered, what the wind and flood deductibles are, which defects clause applies, and when the coverage actually ends are all questions the certificate cannot fully answer. The only reliable answer lives in the policy and its endorsements. This checklist runs that verification the way the gap actually surfaces, which is the morning after a loss, when the assumptions get tested.
Who this checklist is for
- Mid-market general contractors who carry or require builder’s risk on active projects and need to confirm the structure, the materials, and the staged equipment are all actually covered before a loss tests it
- Prime contractors who write the property-insurance requirement into the prime contract and the subcontracts and need to confirm the policy that was bought matches the policy that was specified
- Owners and developers who often procure the builder’s risk policy themselves and want to verify the named insureds, the loss payee, and the limit basis before they sign off
- Risk managers and compliance officers auditing a course-of-construction program for covered-property scope, sublimits, deductibles, and the defects clause, not just the existence of a policy
- Project administrators verifying at project start, at each renewal, and at substantial completion that coverage is in force, correctly scoped, and has not lapsed before the job is actually done
The 15-point builder’s risk verification
The checklist covers 15 verification points every GC, prime, or owner should confirm before treating a builder’s risk policy as adequate protection for the project:
- You are reviewing actual property-insurance evidence, not an ACORD 25. Builder’s risk is first-party property coverage, and it is evidenced on the ACORD 28, Evidence of Commercial Property Insurance, not the ACORD 25 Certificate of Liability Insurance. If you were handed an ACORD 25 as proof of builder’s risk, the form is the wrong instrument and proves nothing about property coverage. Confirm you are holding property evidence, and better still, get the policy declarations and endorsements behind it.
- The named insureds match who actually has an interest in the work. On a course-of-construction policy the named insureds typically include the owner, the general contractor, and the subcontractors and sub-subcontractors. Industry guidance favors showing the subs as actual named or additional insureds rather than relying on loose “as their interests may appear” wording, which can narrow what a sub recovers. Confirm every party with a stake in the physical work is on the policy in a way that gives them standing to collect.
- The lender or other loss payee is correctly named. A construction lender almost always requires loss-payee or mortgagee status so loss proceeds flow to rebuilding rather than disappearing. Confirm the loss payee is named exactly as the loan documents require, with the correct legal entity and address. A missing or misspelled loss payee can stall a claim payment at the worst possible time.
- The covered-property scope is read in full, not assumed. Builder’s risk should cover the permanent work and the structure, but the categories that get missed are materials and supplies stored on site, materials in transit, and materials in temporary or off-site storage. These last categories are frequently sublimited or have to be specifically scheduled. Confirm the scope language and the sublimits actually cover where your material sits and how it moves, not just what is already installed.
- The policy is written on a special-form (all-risk) basis, or you know exactly which perils are named. Builder’s risk is usually written on an all-risk or special-form basis, meaning it covers direct physical loss from any cause except those specifically excluded. A named-peril policy only covers the causes it lists, which is far narrower. Confirm which basis applies, because on a named-peril form a loss from an unlisted cause is simply not covered.
- The limit basis is correct: completed value versus reporting form. A completed-value policy sets the limit at the full projected completed value of the project at inception, with no periodic reporting required. A reporting form requires the insured to report in-place values periodically as construction progresses, and underreporting can trigger a penalty at claim time. Confirm which basis the policy uses and that the limit reflects the true completed value, because an underinsured project shares the shortfall in any large loss.
- The completed-value limit is actually adequate for this project. Read the limit against the real total cost of the work, including hard costs and any materials the policy is meant to protect. A limit set against a stale budget or an early estimate leaves the project underinsured as scope and cost grow. Confirm the limit was set against current numbers and that change-order growth has not pushed the project value above the policy limit.
- Materials in transit and off-site storage are specifically confirmed, with their sublimits. This is the single most common builder’s risk gap. Coverage for material in transit and material sitting in a yard or fabrication shop off site is often capped well below the main limit, and sometimes requires the location to be scheduled. Confirm the transit and off-site sublimits are large enough for your largest single shipment and your largest staged quantity, and that any required scheduling has been done.
- Soft costs and delay coverage are addressed if the schedule has exposure. Builder’s risk can be extended to cover soft costs and delay in completion, also called delay in start-up, which pays additional expenses and lost income when a covered physical loss pushes the completion date. This is an extension, not automatic base coverage. On a project where a delay carries real financial exposure, confirm whether soft-costs and delay coverage was actually purchased and what it includes.
- The defects clause is identified, because LEG 1, 2, and 3 cover very different amounts. Builder’s risk policies handle defective design, workmanship, and materials through a defects exclusion, and the London Engineering Group wordings are the common framework. LEG 1 is the most restrictive and excludes essentially all loss tied to a defect. LEG 2 excludes the cost of fixing the defective part itself but covers resulting damage. LEG 3 is the broadest and covers resulting damage while excluding only the cost to improve the original work. Confirm which clause applies, because the difference between LEG 1 and LEG 3 can be an entire claim.
- Flood, earthquake, and windstorm sublimits and deductibles are read, and you know who bears them. Catastrophe perils are frequently sublimited and carry their own deductibles, often a percentage of the values at risk rather than a flat dollar amount, which on a large project can be a very large number. Confirm whether flood, earth movement, and named-storm coverage is included, at what sublimit, and on what deductible, and confirm the subcontract or prime contract says who is responsible for that deductible.
- Testing and commissioning coverage is confirmed for any project with installed systems. Testing and commissioning of mechanical, electrical, and other systems is a high-risk window, and some policies restrict or exclude loss during this phase. If the project involves systems that will be energized and tested before handover, confirm the policy covers loss during testing and commissioning rather than carving it out right when the risk peaks.
- A waiver of subrogation among the project parties is in place. A waiver of subrogation prevents the insurer, after paying a loss, from turning around and suing another party on the project to recover. On a course-of-construction policy the owner, contractor, and subcontractors should mutually waive subrogation so a covered loss does not turn into litigation between the parties who were all supposed to be protected. Confirm the waiver language is present and covers the parties your contract requires.
- Coverage runs through the right end point, and occupancy will not void it. Builder’s risk typically ends at a defined trigger, often the earliest of substantial completion, owner occupancy or beneficial occupancy, acceptance, or policy expiration, but the exact trigger is form-specific and some forms run differently. The real trap is occupancy: moving in or putting the building to use can suspend or void coverage unless a permission-to-occupy endorsement is added. Confirm when coverage ends, that it survives to actual completion of your scope, and that any early occupancy is covered by endorsement.
- The deductible responsibility is fixed in the subcontract, and the policy and endorsements are retained in the file. Builder’s risk deductibles are larger than routine liability deductibles, and standard construction contracts such as AIA A201 and ConsensusDocs address property insurance and deductible allocation, so the contract should say who pays. Confirm the subcontract assigns the deductible clearly, and keep the full policy, declarations, and endorsements in the project file alongside this completed checklist, because the certificate alone will not answer the questions an adjuster asks after a loss.
How to run the verification
Run this checklist at project start, before any material is staged or installed, and again at every policy renewal and at substantial completion. Start by confirming you are holding actual property evidence, the ACORD 28, and then get the policy declarations and endorsements behind it, because the form is a summary and the answers you need live in the policy. Work the 15 points in order. Mark each item OK, Flag, or Reject. A Flag goes back to the broker or the party that procured the policy for correction. A Reject stops reliance on the coverage until the deficiency is fixed and documented in writing. The Excel version of this checklist gives you a per-item status column with OK, Flag, and Reject, a notes field for the actual sublimit, deductible, and defects clause you saw, and a =COUNTIF(D2:D16,TRUE)/15 compliance percentage that rolls up across the project so you can see at a glance whether the course-of-construction program is fully verified or still carrying an open gap.
Stop assuming the ACORD covers the building itself
A certificate of liability insurance proves a sub carries liability coverage. It says nothing about whether the structure under construction is protected against fire, wind, water, or theft, because that is a different policy on a different form. Confirming builder’s risk by hand means getting the right evidence, then reading the policy for covered-property scope, sublimits, deductibles, the defects clause, and the date coverage actually ends, on every project and at every renewal. Contracts Connected’s COI Analyzer reads the documents the moment they arrive, flags where the certificate you were handed does not prove the coverage you need, and tracks what is actually verified against what the contract required. The checklist tells you what to look for. CC does the looking.
For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.
Frequently asked questions about the builder's risk insurance verification checklist
What is the difference between builder’s risk and commercial general liability?
They are two different policies doing two different jobs. Builder’s risk is first-party property insurance that pays for direct physical damage to the structure being built, the materials going into it, and equipment on site during construction. Commercial general liability is third-party insurance that pays when the insured is legally liable for bodily injury or property damage to someone else. A fire that destroys the half-built structure is a builder’s risk claim. A passerby injured by a falling tool is a CGL claim. A clean CGL certificate says nothing about whether the building itself is protected.
Why doesn’t an ACORD 25 prove builder’s risk coverage?
Because the ACORD 25 is the Certificate of Liability Insurance, and builder’s risk is property insurance, not liability. The two live on different forms. Property coverage is evidenced on the ACORD 28, Evidence of Commercial Property Insurance, which is the form built to carry property limits, loss-payee status, and the structure of property coverage. If someone hands you an ACORD 25 to prove builder’s risk, the form physically cannot carry that proof. You need property evidence, and ideally the policy declarations and endorsements behind it.
Who should be named on a builder’s risk policy?
Typically the owner, the general contractor, and the subcontractors and sub-subcontractors who have an interest in the work, plus any construction lender as loss payee or mortgagee. Industry guidance favors showing the subs as actual named or additional insureds rather than relying on loose “as their interests may appear” language, which can limit what a sub recovers after a loss. Confirm every party with a real stake in the physical work has standing to collect, and confirm the lender is named exactly as the loan documents require.
What are the LEG clauses, and why do they matter?
LEG refers to the London Engineering Group defects wordings, which govern how a builder’s risk policy treats loss tied to defective design, workmanship, or materials. LEG 1 is the most restrictive and excludes essentially all loss related to a defect. LEG 2 excludes the cost of fixing the defective part itself but covers the resulting damage. LEG 3 is the broadest and covers the resulting damage while excluding only the cost to improve the original work. The clause that applies can be the difference between a covered claim and a denial, so identifying it is a core verification step, not a footnote.
What is the difference between completed value and reporting form?
They are two ways of setting the limit. On a completed-value policy, the limit is the full projected completed value of the project, set at inception, with no periodic reporting required. On a reporting form, the insured reports the in-place values periodically as the work progresses, and the premium and the available limit track those reports. The risk with a reporting form is underreporting, which can trigger a penalty that reduces what the policy pays at claim time. Confirm which basis applies and that the values reflect the true cost of the work.
When does builder’s risk coverage end?
Usually at a defined trigger, and on many forms that is the earliest of substantial completion, owner occupancy or beneficial occupancy, acceptance, or policy expiration. The exact trigger is form-specific, so some policies run differently, including forms that end a set number of days after occupancy or run to final completion. The common trap is occupancy. Moving in or putting the building to use can suspend or void coverage unless a permission-to-occupy endorsement is added. Confirm the end trigger, confirm coverage survives until your scope is actually complete, and confirm any early occupancy is covered by endorsement.