The full verification chain: subcontract requirement, CG 25 03 or CG 25 04 endorsement, project schedule, dedicated-limit reconciliation, and renewal re-check, before the limit you required turns out to be shared across jobs you will never see.
Why per-project aggregate verification matters
Here is the situation that should keep a risk manager up at night. Your sub hands you a certificate. The general aggregate reads $2,000,000. Your subcontract required $2,000,000. The box matches the requirement, so your contract admin checks it off and the sub mobilizes.
What the certificate does not tell you is that the same $2,000,000 is the only general aggregate that sub carries across every job it is running. Five other projects, three other GCs, all drawing from the same single limit. That number on your certificate is not reserved for your project. It is shared.
Now play it forward. Six months in, that sub has a bad loss on someone else’s job. A warehouse it built across town has a foundation failure, and the claims start landing on its general liability policy. Those claims erode the general aggregate. By the time anything goes wrong on your project, the limit you were counting on has already been spent on a job you have never heard of, for a GC you have never met. You required $2,000,000 of protection. You have whatever is left after everyone else’s claims clear, which on a bad year can be close to nothing.
That is the trap a per-project aggregate is built to close. A standard commercial general liability policy carries one General Aggregate Limit that, by default, applies to all of the insured’s operations and projects combined. The per-occurrence limit caps what the policy pays on any single claim. The general aggregate caps what it pays in total across the whole policy period, for every job the sub touches. Without a per-project aggregate endorsement, your project is sharing that ceiling with every other job in the sub’s book.
The fix is an endorsement that resets and segregates the general aggregate so it applies separately to each designated construction project. The two standard ISO forms that do this are CG 25 03, the Designated Construction Project(s) General Aggregate Limit, and CG 25 04, the Designated Location(s) General Aggregate Limit. When one is attached and your project is correctly scheduled, your project gets its own full aggregate that no other job can drain.
Here is the part most reviews miss. The ACORD 25 certificate does not show whether either endorsement is on the policy. It does not show the limit structure at all beyond the dollar amounts in the limits boxes. A certificate can read $2,000,000 general aggregate whether that limit is shared across forty jobs or dedicated to yours alone. The only way to know is to pull the endorsement form and the project schedule. This checklist runs that verification end to end, the way the gap actually surfaces in a claim.
Who this checklist is for
- Federal general contractors whose prime contracts require subs to carry a per-project general aggregate so the government’s project is not exposed to claims on the sub’s other work
- Mid-market general contractors managing a sub roster across several concurrent jobs, where one sub’s bad loss elsewhere can quietly drain the limit protecting an active project
- Prime contractors who write the insurance requirements into the subcontract and need to confirm the sub actually bought the structure the contract demands
- Risk managers and compliance officers auditing COI packages for limit structure, not just limit amounts, across an entire portfolio
- Project administrators verifying at sub onboarding and renewal that the per-project aggregate endorsement is attached and that this specific project is scheduled on it
The 14-point per-project aggregate verification
The checklist covers 14 verification points every prime should confirm before accepting a sub’s general aggregate as adequate protection for the project:
- The subcontract states a per-project aggregate requirement in writing, not just a general aggregate dollar amount. A requirement that reads “$2,000,000 general aggregate” does not get you a dedicated limit. The clause has to require that the general aggregate apply on a per-project basis to this project specifically. If the subcontract only names a number, the sub satisfies it with a shared limit, and you have no contractual basis to demand the endorsement. Verify the words “per project” or “per location” appear in the insurance requirements, not just the figures.
- A per-project or per-location aggregate endorsement is physically attached to the policy. The certificate cannot confirm this. You need the endorsement document itself. The two ISO standard forms are CG 25 03, Designated Construction Project(s) General Aggregate Limit, and CG 25 04, Designated Location(s) General Aggregate Limit. If the carrier uses a manuscript endorsement instead, read the actual text and confirm it does the same thing: a separate general aggregate that applies to your designated project and is not eroded by claims on other work.
- You confirm which form is attached, CG 25 03 or CG 25 04, and that it matches how the work is described. The two forms segregate the aggregate differently. CG 25 03 designates specific construction projects. CG 25 04 designates specific locations. For most subcontracts the project-based form is the right fit, but some scopes are tied to a location rather than a named project. Read which form is on the policy and confirm the basis it uses lines up with how your project is identified. A location-based endorsement that designates a different address does nothing for your job.
- This project is correctly listed on the endorsement’s schedule. Both forms work by scheduling the designated projects or locations the separate aggregate applies to. An endorsement that is attached but does not name your project, or names it with the wrong address or a stale project number, leaves you sharing the general aggregate after all. Verify the schedule lists your project by the same name, number, or address used in the subcontract. Treat a blank or “per schedule on file” reference as unverified until you see the actual schedule.
- You understand the difference between the per-occurrence limit, the general aggregate, and the products-completed-operations aggregate. These are three separate ceilings. The per-occurrence limit caps a single claim. The general aggregate caps total payouts across the policy period. The products-completed-operations aggregate is a separate ceiling for claims arising from completed work, and a per-project general aggregate endorsement generally does not segregate it. Confirm you know which limit the contract requirement is actually pointing at, because a dedicated general aggregate does not automatically buy you a dedicated completed-operations aggregate.
- The per-project aggregate amount meets or exceeds the contract requirement on a per-project basis. Read the dedicated amount on the endorsement, not the policy-wide aggregate on the certificate. The endorsement may set the per-project aggregate equal to the general aggregate, or it may set a different, sometimes lower, dedicated figure. If the contract requires $2,000,000 per project and the endorsement designates a $1,000,000 per-project aggregate, the sub is short on the limit that actually protects your job even though the certificate’s general aggregate reads $2,000,000.
- The products-completed-operations aggregate is verified separately for completed-work exposure. Construction claims surface after the work finishes, sometimes years later. Those claims draw on the products-completed-operations aggregate, which is its own shared ceiling across all the sub’s jobs and is usually not segregated by CG 25 03 or CG 25 04. On any project with meaningful completed-operations exposure, confirm the products-completed-operations aggregate amount and understand it remains shared unless a separate endorsement addresses it.
- The certificate’s general aggregate figure is reconciled against the endorsement’s dedicated figure. The limits box on the ACORD 25 reports the policy’s general aggregate. It does not report the per-project dedicated amount. When an endorsement is in place, those two numbers can differ. Pull both, line them up, and confirm the dedicated per-project figure, not the policy-wide figure, is the one that satisfies your requirement. A reviewer reading only the certificate box will accept a shared limit as if it were dedicated.
- “Blanket” per-project wording is read carefully, not assumed to cover this project. Some endorsements use blanket language that applies a separate aggregate to “each construction project” without naming them individually. Blanket wording can be acceptable and is often preferable to a scheduled list that has to be updated. But blanket forms vary, and some apply the separate aggregate only to projects meeting specific conditions. Read the actual blanket language and confirm your project falls inside its definition, rather than assuming “blanket” means “automatically yours.”
- The endorsement’s separate aggregate is confirmed as not eroded by claims on the sub’s other projects. The entire point of the form is isolation. Confirm the endorsement language actually establishes a freestanding aggregate for your designated project that operates independently of the policy’s overall general aggregate and of every other designated project. Some manuscript or poorly drafted endorsements blur this and leave a path for cross-project erosion. The standard ISO forms handle it correctly, which is one more reason to insist on a known form number rather than an unfamiliar manuscript.
- The interplay with the additional insured endorsement is confirmed. A per-project aggregate protects the size of the limit. It does not by itself make you an additional insured or give you any rights under the sub’s policy. Those come from the additional insured endorsements, typically CG 20 10 for ongoing operations and CG 20 37 for completed operations. Confirm the additional insured endorsements are present alongside the per-project aggregate, because a dedicated limit you have no standing to claim against does not protect you.
- The endorsement edition and form number are recorded and flagged for currency. ISO revises its endorsement forms periodically, and the edition date printed on the form, the small two-digit month and year following the form number, tells you which version is in force. Record the full form number and edition exactly as printed. Do not assume a specific edition year. If the contract or your standard requires a particular edition, confirm the attached form matches, and route any older or unfamiliar edition to your broker to confirm the language still segregates the aggregate as expected.
- The policy expiration and project duration are aligned so the dedicated aggregate survives the full job. A per-project aggregate endorsement only operates while the policy is in force. If the project runs past the policy term, the sub renews, and the renewal must carry the same per-project endorsement with this project still scheduled. Renewals routinely drop endorsements or re-paper schedules. Verify expiration dates at onboarding and build a renewal re-verification requirement into the subcontract so the dedicated limit does not quietly disappear mid-project.
- The endorsement copy and the completed checklist are retained in the project COI file. The certificate is a summary. The endorsement is the evidence that the limit is actually dedicated. For coverage disputes, claim defense, and audit, the physical endorsement form and project schedule need to be on file alongside the completed verification checklist. A certificate showing a clean general aggregate with no endorsement backup is an incomplete file, and the gap surfaces at the worst possible moment, when a claim on another job has already eaten the limit.
How to run the verification
Run this checklist at sub onboarding, before work begins, and again at every policy renewal. Start with the subcontract language. If the insurance requirements name only a dollar figure and never say “per project,” the rest of the verification has no contractual teeth, so fix the template first. Then pull the certificate plus the actual endorsement form and project schedule, and work the 14 points in order. Mark each item OK, Flag, or Reject. Flagged items go back to the sub’s broker for correction before mobilization. Rejections stop work until the deficiency is fixed and documented in writing.
When you request documents from the broker, name the form. A request for “a copy of the policy” is easy to deflect. A request for “the CG 25 03 endorsement and its project schedule, or the equivalent manuscript form” is harder to ignore and signals you will notice if it is missing. The Excel version of this checklist includes a per-item status column with OK / Flag / Reject, a notes field for the form number and edition you actually saw, and a =COUNTIF(D2:D15,TRUE)/14 compliance percentage formula that rolls up across every sub on the project so you can see at a glance which COI files are complete and which are still carrying a shared limit you have not closed.
Stop accepting shared limits as if they were dedicated
A certificate showing a clean general aggregate tells you almost nothing about whether that limit is reserved for your project or shared across forty jobs you will never see. Confirming it by hand means pulling endorsement forms, reading CG 25 03 and CG 25 04 schedules, reconciling the dedicated figure against the certificate box, and re-checking every one of those at renewal, for every sub on every project. That is exactly the manual review that breaks down at scale. Contracts Connected’s COI Analyzer reads every ACORD 25 the moment it arrives, flags where the limit structure cannot be confirmed from the certificate alone, tracks which subs have a verified per-project aggregate with this project scheduled, and alerts you when a renewal needs re-verification. The checklist tells you what to look for. CC does the looking.
For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.
Frequently asked questions about the per-project aggregate limits checklist
What is a per-project aggregate and why does it matter?
A standard commercial general liability policy carries one General Aggregate Limit that applies to all of the insured’s operations and projects combined for the policy period. That means a sub working five jobs shares a single aggregate ceiling across all five. A claim on any one of those jobs erodes the limit available to every other job, including yours. A per-project aggregate is an endorsement that resets the general aggregate so a separate, dedicated limit applies to each designated construction project. With it in place, a loss on the sub’s other work cannot drain the limit protecting your project. Without it, the number on your certificate is a shared pool you do not control.
What is the difference between the per-occurrence limit and the general aggregate?
They cap different things. The per-occurrence limit is the most the policy will pay for any single claim or occurrence. The general aggregate is the most the policy will pay in total across the entire policy period, no matter how many separate claims arise. A policy with a $1,000,000 per-occurrence limit and a $2,000,000 general aggregate will pay up to $1,000,000 on one claim and up to $2,000,000 across all claims combined for the period. The general aggregate is the number a per-project endorsement segregates, because that is the shared ceiling at risk of being drained by claims on the sub’s other jobs.
Which ISO endorsement creates a per-project aggregate?
The two standard ISO forms are CG 25 03, the Designated Construction Project(s) General Aggregate Limit, and CG 25 04, the Designated Location(s) General Aggregate Limit. CG 25 03 establishes a separate general aggregate for each designated construction project. CG 25 04 does the same for each designated location. For most subcontracts the project-based form is the right one, but the location-based form fits scopes tied to a specific site rather than a named project. The exact edition date printed on the form tells you which revision is in force, so record it as printed and confirm it matches any edition your contract specifies rather than assuming a particular year.
Why doesn’t the ACORD 25 certificate show whether a per-project aggregate is in place?
The ACORD 25 is a summary document. It reports the policy’s limits in its limits boxes, but it does not report the policy’s limit structure and it does not list endorsements. A certificate can show a $2,000,000 general aggregate whether that limit is shared across the sub’s entire book of work or dedicated to your project alone. The certificate has no field that distinguishes the two. The only way to confirm a dedicated per-project aggregate is to obtain the endorsement form itself, CG 25 03 or CG 25 04 or an equivalent manuscript, and the project schedule that names your job. Reviewing only the certificate is how shared limits get accepted as dedicated.
Does a per-project aggregate also protect completed-operations claims?
Generally no, and this trips up a lot of reviews. Completed-operations claims, the ones that surface after the work is finished, draw on the products-completed-operations aggregate, which is a separate ceiling from the general aggregate. The standard CG 25 03 and CG 25 04 endorsements segregate the general aggregate, not the products-completed-operations aggregate. So even with a per-project general aggregate in place, the completed-operations limit usually remains shared across all the sub’s jobs. On any project with meaningful completed-operations exposure, confirm the products-completed-operations aggregate amount separately and understand it stays shared unless a specific endorsement addresses it.
What happens at policy renewal, and why re-verify?
A per-project aggregate endorsement only works while the policy that carries it is in force. Insurance policies renew annually, each renewal is effectively a new policy, and carriers are not obligated to carry forward every endorsement or every scheduled project from the prior term. A sub can hold a proper per-project endorsement with your project scheduled in year one, then renew with a leaner package that drops the form or re-papers the schedule without your job on it. If your onboarding review was thorough but your renewal review is a rubber stamp, the dedicated limit can vanish mid-project without anyone noticing until a claim lands. Build a renewal re-verification requirement into the subcontract and treat every incoming renewal certificate and endorsement as a fresh review.