Construction dispute data

Construction Dispute Statistics 2026

Arcadis reports that the average claimed value of a North American construction dispute was $60.1 million in 2024, and that disputes took 12.5 months on average to resolve. Arcadis also says 80% of claims were worth $25 million or less, so a few very large claims pull the average up.

This page lists sourced figures on the value, length and causes of construction disputes, federal board caseload and the federal claim deadline. Each figure shows its publisher, year, sample and limit. Contracts Connected compiled and checked these figures. They are third-party figures, not Contracts Connected customer data.

Arcadis and HKA rank the causes of disputes differently because they draw on different groups and measure different things. The table below shows how they differ. The federal figures cover one board and one statute.

Last reviewed: November 2026. 18 reviewed figures. 2 claim checks. Compilation licensed under CC BY 4.0.

Section A 5 figures

How much disputes are worth and how long they last

Arcadis's annual North America survey. Values are what the contractor claimed, not what was awarded.

$60.1 million

Average claimed value of a North American construction dispute, 2024

Arcadis surveyed construction professionals in North America. They reported an average dispute value of $60.1 million for 2024, up from $43.0 million in 2023. That is the amount the contractor claimed, and a few very large claims pull the average up.

The limit. Claimed value, not an award, and a mean skewed by a few mega claims.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Average claimed value of a North American construction dispute, 2024," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-average-dispute-value-60-million. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
80%

Share of claims worth $25 million or less

Arcadis says 80% of the claims in its survey were worth $25 million or less, and almost half were worth less than $5 million. A small number of very large claims lift the average.

The limit. Survey of respondents, and the report does not publish the number of respondents.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Share of claims worth $25 million or less," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-claims-worth-25-million-or-less. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
$1.1 billion

Largest dispute reported in the 2025 Arcadis survey

The largest dispute reported by Arcadis respondents in its 2025 North American survey was worth US$1.1 billion.

The limit. One respondent's reported claim, so it is an outlier and not a typical case.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Largest dispute reported in the 2025 Arcadis survey," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-largest-dispute-reported. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
$43.0 million

Average claimed value of a North American dispute, 2023

Arcadis reported the average North American dispute was worth $43.0 million in 2023. It said the 2022 and 2023 results are double what its 2016 to 2019 surveys showed.

The limit. From the previous edition, covering 2023 disputes. Claimed value, not an award.

Year
2024
Sample and method
Arcadis North America annual survey; covers 2023 disputes; respondent count not stated
US or not
North America
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Average claimed value of a North American dispute, 2023," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2024-average-dispute-value-43-million. Original source: Arcadis, 14th Annual Construction Disputes Report: Managing Construction Disputes in the Digital Age (North America | 2024), 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
12.5 months

Average length of a North American construction dispute, 2024

Arcadis found the average North American construction dispute took 12.5 months to resolve in 2024, down from 14.4 months in 2023. Arcadis calls it the shortest time in the past decade.

The limit. Length runs from the formal claim to resolution or the end of the hearing, and rests on survey answers.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Average length of a North American construction dispute, 2024," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-average-dispute-length-12-5-months. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section B 3 figures

What causes disputes and how to avoid claims

Rankings from Arcadis respondents. They are opinion, with no percentages.

Rank 1 errors or omissions in contract documents

Most common cause of disputes in North America, 2024

Arcadis respondents ranked errors or omissions in the contract documents as the most common cause of disputes in North America in 2024. Failing to understand or comply with contract obligations ranked second, and owner-directed changes third.

The limit. A ranked list with no percentages, based on respondent opinion.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Most common cause of disputes in North America, 2024," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-top-cause-of-disputes. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Rank 1 contract and specification reviews

Most effective way to avoid claims, 2024

Arcadis respondents named contract and specification reviews as the most effective way to avoid claims in 2024. Good communication ranked second and risk management third.

The limit. Respondent opinion, not a measured result.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Most effective way to avoid claims, 2024," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-most-effective-way-to-avoid-claims. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Rank 1 owner and contractor willing to compromise

Most important factor in resolving a dispute early, 2024

Arcadis respondents said the owner and contractor being willing to compromise was the most important factor in resolving a dispute early. Accurate, timely schedules ranked second, and contractor transparency of cost data behind a claim ranked third.

The limit. Respondent opinion, ranked list only.

Year
2025
Sample and method
Annual Arcadis North America Contract Solutions team survey of construction industry respondents, North America input only; respondent count not stated in the report; covers 2024 disputes
US or not
North America
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Most important factor in resolving a dispute early, 2024," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#arcadis-2025-most-important-factor-in-early-resolution. Original source: Arcadis, 15th Annual Construction Disputes Report: Construction Disputes in Motion (North America | 2025), 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section C 4 figures

What HKA found on major projects worldwide

HKA's review of 2,410 major construction and engineering projects in 122 countries. These are large capital projects, not US contractors in general.

Two-thirds and a third

Claims as a share of schedule and budget on major projects

HKA reviewed 2,410 major construction and engineering projects in 122 countries. Claims averaged about two-thirds of the contract schedule and about a third of the budget.

The limit. Large capital projects worldwide, not US contractors in general. These are claimed amounts, not awards.

Year
2026
Sample and method
HKA consultants' first-hand investigations of claims and disputes on 2,410 capital and infrastructure projects in 122 countries, worth $2.56 trillion combined
US or not
Global, with Americas breakout
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Claims as a share of schedule and budget on major projects," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#hka-2026-claims-as-share-of-schedule-and-budget. Original source: HKA, CRUX Insight ninth annual report, Powering through Uncertainty (summary page), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
33.4%

Projects where scope change was blamed for disputes

HKA found scope change was blamed for disputes on 33.4% of the projects in its dataset.

The limit. Major capital projects worldwide, from HKA's own case files.

Year
2026
Sample and method
HKA consultants' first-hand investigations of claims and disputes on 2,410 capital and infrastructure projects in 122 countries, worth $2.56 trillion combined
US or not
Global, with Americas breakout
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Projects where scope change was blamed for disputes," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#hka-2026-scope-change-behind-disputes. Original source: HKA, CRUX Insight ninth annual report, Powering through Uncertainty (summary page), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
10 percentage points

Drop in incomplete design and scope change on newer projects

HKA says incomplete design and scope change were down by almost 10 percentage points on projects scheduled to finish from 2020 onward, compared with earlier projects.

The limit. Global dataset of large projects. HKA says technology may be helping but the industry has not yet absorbed the benefit of AI.

Year
2026
Sample and method
HKA consultants' first-hand investigations of claims and disputes on 2,410 capital and infrastructure projects in 122 countries, worth $2.56 trillion combined
US or not
Global, with Americas breakout
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Drop in incomplete design and scope change on newer projects," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#hka-2026-design-and-scope-change-down-almost-10-points. Original source: HKA, CRUX Insight ninth annual report, Powering through Uncertainty (summary page), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section D 2 figures

What HKA found in the Americas

The Americas include Latin America, so these figures are not US only.

20.1%

Americas: claims triggered by workmanship and physical conditions

HKA reports that in the Americas, deficient workmanship (20.1%) and unforeseen physical conditions (17.4%) triggered more claims than in other regions.

The limit. Americas includes Latin America and is not US only. Percentages are shares of projects in HKA's dataset.

Year
2026
Sample and method
HKA consultants' first-hand investigations of claims and disputes on 2,410 capital and infrastructure projects in 122 countries, worth $2.56 trillion combined
US or not
Global, with Americas breakout
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Americas: claims triggered by workmanship and physical conditions," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#hka-2026-americas-workmanship-and-physical-conditions. Original source: HKA, CRUX Insight ninth annual report, Powering through Uncertainty (summary page), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
31.8%

Americas: claimed cost and time on projects scheduled from 2020

On projects scheduled to finish from 2020 onward, HKA says claimed costs in the Americas edged up to 31.8% of budgets, while time claims dropped to 44.2% of schedules.

The limit. Claimed amounts on large projects, across the Americas, not the US alone.

Year
2026
Sample and method
HKA consultants' first-hand investigations of claims and disputes on 2,410 capital and infrastructure projects in 122 countries, worth $2.56 trillion combined
US or not
Global, with Americas breakout
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Americas: claimed cost and time on projects scheduled from 2020," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#hka-2026-americas-claimed-cost-and-time. Original source: HKA, CRUX Insight ninth annual report, Powering through Uncertainty (summary page), 2026. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Section E 4 figures

Federal contract appeals and the federal claim deadline

One federal board and one statute. They do not measure all construction disputes.

371

Cases docketed by the Armed Services Board of Contract Appeals, fiscal year 2025

The Armed Services Board of Contract Appeals docketed 371 cases in fiscal year 2025. The Corps of Engineers was the largest single source, with 104.

The limit. Appeals from defense agencies, NASA, the CIA and the Washington Metropolitan Area Transit Authority, and not all of them are construction. Counts one board's caseload, not all US disputes.

Year
2025
Sample and method
Government annual report of Board caseload, dated October 30, 2025
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Cases docketed by the Armed Services Board of Contract Appeals, fiscal year 2025," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#asbca-2025-cases-docketed. Original source: Armed Services Board of Contract Appeals (U.S. Department of Defense), ASBCA FY2025 Annual Report, 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
67%

Board decisions that found merit in whole or in part, fiscal year 2025

Of the 140 cases the Armed Services Board decided on the merits in fiscal year 2025, 67% found merit in whole or in part.

The limit. Only appeals that reached a decision. Contractors that settle or drop a claim are not counted.

Year
2025
Sample and method
Government annual report of Board caseload, dated October 30, 2025
US or not
US
Status
Reviewed, with limits
Reviewed
November 2026

Cite as: Contracts Connected, "Board decisions that found merit in whole or in part, fiscal year 2025," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#asbca-2025-share-of-decisions-finding-merit. Original source: Armed Services Board of Contract Appeals (U.S. Department of Defense), ASBCA FY2025 Annual Report, 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
748

Cases pending at the Board, October 2025

The Armed Services Board of Contract Appeals had 748 cases pending in October 2025, down from 954 in October 2021.

The limit. One federal board. Not a measure of all construction disputes.

Year
2025
Sample and method
Government annual report of Board caseload, dated October 30, 2025
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Cases pending at the Board, October 2025," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#asbca-2025-cases-pending. Original source: Armed Services Board of Contract Appeals (U.S. Department of Defense), ASBCA FY2025 Annual Report, 2025. Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
6 years to submit a claim; certify over $100,000

Federal deadline to submit a contract claim

Under 41 U.S.C. 7103, a federal contract claim must be submitted within 6 years after it accrues. A contractor must certify any claim over $100,000.

The limit. Federal contracts only. State and local public contracts and private contracts set their own notice and claim deadlines.

Year
n/a (statute)
Sample and method
Statute text
US or not
US
Status
Reviewed
Reviewed
November 2026

Cite as: Contracts Connected, "Federal deadline to submit a contract claim," Contracts Connected Data, https://contractsconnected.com/data/construction-dispute-statistics#congress-41-usc-7103-claims-within-6-years. Original source: U.S. Congress (41 U.S.C. 7103, via Cornell Legal Information Institute), 41 U.S. Code 7103, Decision by contracting officer, n/a (statute). Reviewed November 2026. Compilation licensed under CC BY 4.0.

Change log
  • 2026-11-03. Added. Checked against the original source.
Original analysis

Why dispute cause rankings differ

Arcadis and HKA both report what causes disputes, and they name different top causes. They draw on different groups and measure different things.

Quote each figure with its source and group. The table shows who was asked or reviewed, and what each figure measures, using only what each source states.

SurveyFigurePopulationQuestion or measurePeriod
Arcadis, 15th Annual Construction Disputes ReportErrors or omissions in the contract documents ranked firstConstruction industry respondents in North America. The report does not state the number of respondents.Most common cause of disputes. A ranked list based on respondent opinion, with no percentages.2024 disputes
HKA, CRUX Insight ninth annual reportDesign-related failures behind disputes on 40.5% of projects2,410 capital and infrastructure projects in 122 countries, from HKA consultants' own investigationsShare of projects in the dataset where design-related failures were behind disputesReport published 2026
HKA, CRUX Insight ninth annual reportScope change blamed on 33.4% of projects2,410 capital and infrastructure projects in 122 countriesShare of projects in the dataset where scope change was blamed for disputesReport published 2026
HKA, CRUX Insight ninth annual report, AmericasDeficient workmanship 20.1%, unforeseen physical conditions 17.4%Projects in the Americas, which include Latin AmericaShare of projects in the dataset where these causes triggered claimsReport published 2026
Section F 2 checks

Claim checks: two statements that go further than the sources

These two statements are common in dispute articles. For each one, we show what the original source says.

$60.1 million

Claim check: "The average construction dispute in the U.S. is $60.1 million"

The claim as repeated. the new average value of a construction dispute in the U.S. is $60.1 million

Where it came from. An article by a contract software vendor on a trade publisher's partner ebook site says Arcadis found this. The same page's chart says North America. The source is Arcadis, 15th Annual Construction Disputes Report, North America | 2025, covering 2024 disputes.

What it shows. Arcadis reported an average claimed dispute value of $60.1 million for 2024 across North America.

What it does not show. The Arcadis figure covers North America, not only the US. It is the claimed value, and Arcadis says 80% of claims were $25 million or less and almost half under $5 million, so the average is driven by a few mega claims.

Verdict. The number is real, but it describes North America and claimed value, not the US or what is awarded.

Safe wording. "Arcadis reported that the average claimed value of a North American construction dispute was $60.1 million in 2024."

Do not cite this as a measured finding.

Year
2025
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
Ranked first

Claim check: "Contract documents are the top cause of construction disputes"

The claim as repeated. Contract documents are the top cause of construction disputes

Where it came from. Commonly stated as a flat fact in dispute articles. Arcadis ranks 'errors and/or omissions in the contract documents' first in North America for 2024, and it has been tied or in the top two for three years. HKA ranks design-related failures first by share of projects.

What it shows. Arcadis ranks errors or omissions in the contract documents first for 2024 in North America, and HKA ranks design-related failures first by share of projects.

What it does not show. Both are respondent or case-file data from a consultancy with a claims practice, and neither measures how many disputes a clause change would remove.

Verdict. Both rankings are real. They are rankings in two studies, not a count of what causes most disputes.

Safe wording. "Errors or omissions in the contract documents ranked first in the Arcadis survey."

Do not cite this as a measured finding.

Year
2025
Status
Claim check: not cited as a finding
Reviewed
November 2026
Change log
  • 2026-11-03. Added. Checked against the original source.
Method

How we check figures

  1. Find the original publisher. We trace each figure to the organization that first published it, not to a page that repeats it.
  2. Fetch the page. We open the original page or file and read the figure there.
  3. Read the sample and method. We note who was counted, how, and when.
  4. State the limit. We write what the figure does not show, next to the figure.

Every figure on this page was re-read at its original source on 2026-11-03. The date of each check sits in the card's change log.

Questions

Frequently asked questions

What is the average value of a construction dispute?

Arcadis reports an average claimed value of $60.1 million for North American disputes in 2024, up from $43.0 million in 2023. Arcadis says 80% of claims were worth $25 million or less.

How long does a construction dispute take to resolve?

Arcadis found the average North American dispute took 12.5 months to resolve in 2024, down from 14.4 months in 2023. Arcadis calls it the shortest time in the past decade.

Is the average dispute in the US $60.1 million?

The $60.1 million is Arcadis's figure for North America, not the US alone. It is the claimed value, and a few very large claims pull the average up.

What causes the most construction disputes?

Arcadis respondents ranked errors or omissions in the contract documents first in 2024. HKA found design-related failures behind disputes on 40.5% of its projects. These are a ranking and a case-file share.

What helps contractors avoid claims?

Arcadis respondents named contract and specification reviews as the most effective way to avoid claims in 2024. Good communication ranked second and risk management third. This is respondent opinion.

How long does a contractor have to submit a federal claim?

Under 41 U.S.C. 7103, a federal contract claim must be submitted within 6 years after it accrues. A contractor must certify any claim over $100,000.

Can I cite these figures?

Yes. You can quote, chart and republish them under CC BY 4.0 with credit to Contracts Connected. The numbers belong to the publishers, so cite the original source too. A link is welcome, never required.

Is this Contracts Connected customer data?

No. These are third-party figures that Contracts Connected compiled and checked against each original source. None of them is Contracts Connected customer data.

Cite our data

How to cite this page

You can quote, chart and republish any figure here. The Contracts Connected compilation (our wording, the notes and the layout) is licensed under Creative Commons Attribution 4.0 (CC BY 4.0). The numbers themselves belong to the organizations that published them, so cite the original source too.

Short credit. Source: Contracts Connected

Full credit. Contracts Connected, "Construction Dispute Statistics 2026," https://contractsconnected.com/data/construction-dispute-statistics, reviewed November 2026, CC BY 4.0.

Linking. A link back is welcome and never required. If you link, any kind of link is fine, followed or not. Please use the name "Contracts Connected" or the page address as the link text.

Questions or corrections. support@contractsconnected.com. If a source changes a figure, we update it and record the change.

Downloads. CSV and JSON, with every figure and its change log.