  "title": "Change Order Statistics for Construction",
  "url": "https://contractsconnected.com/data/change-order-statistics",
  "publisher": "Contracts Connected",
  "license": "https://creativecommons.org/licenses/by/4.0/",
  "license_name": "CC BY 4.0",
  "reviewed": "November 2026",
  "checked_on": "2026-11-03",
  "note": "Curated and source-checked compilation of published figures. Not Contracts Connected customer data.",
  "downloads": {
    "csv": "https://contractsconnected.com/data/change-order-statistics.csv",
    "json": "https://contractsconnected.com/data/change-order-statistics.json"
  },
  "figures": 14,
  "claim_checks": 3,
  "rows": [
    {
      "id": "gao-1994-gsa-contracts-cost-growth-10-percent",
      "title": "Federal building contracts with cost growth of 10 percent or more, 1994",
      "section": "How much change orders add to cost",
      "kind": "figure",
      "statistic": "43%",
      "wording": "In a 1994 review of 437 completed federal building contracts, the Government Accountability Office (then the General Accounting Office) found that 43% had cost growth of 10 percent or more, and over 50% of the new construction and repair contracts had cost growth above the 5 percent and 7 percent GSA budgets for changes.",
      "limit": "This is a 1994 review of federal buildings only. It measures all cost growth on the contract, not only owner-requested changes.",
      "source_publisher": "U.S. General Accounting Office (now GAO)",
      "source_title": "GGD-94-145, General Services Administration: Better Data and Oversight Needed to Improve Construction Management (June 1994)",
      "source_url": "https://www.gao.gov/assets/ggd-94-145.pdf",
      "source_year": "1994",
      "sample_or_method": "GSA data on 100 new construction and 337 repair and alteration contracts substantially completed fiscal year 1988 through the first half of fiscal year 1993",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#gao-1994-gsa-contracts-cost-growth-10-percent",
      "cite_as": "Cite as: Contracts Connected, \"Federal building contracts with cost growth of 10 percent or more, 1994,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#gao-1994-gsa-contracts-cost-growth-10-percent. Original source: U.S. General Accounting Office (now GAO), GGD-94-145, General Services Administration: Better Data and Oversight Needed to Improve Construction Management (June 1994), 1994. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "missouri-auditor-2002-100-change-orders-12-million",
      "title": "What 100 reviewed change orders added to eight Missouri highway projects",
      "section": "How much change orders add to cost",
      "kind": "figure",
      "statistic": "$12 million on $118.4 million",
      "wording": "Missouri's State Auditor reviewed 100 change orders on 8 Department of Transportation projects, issued over 18 months in 2000 and 2001. The projects were expected to cost $118.4 million and the 100 change orders increased costs by $12 million.",
      "limit": "Eight projects in one state in 2000 to 2001. The auditors' sample is not the state average.",
      "source_publisher": "Missouri Office of State Auditor (Claire McCaskill)",
      "source_title": "Missouri Department of Transportation Contract Change Orders (performance audit, 2002)",
      "source_url": "https://auditor.mo.gov/press/2002-96.pdf",
      "source_year": "2002",
      "sample_or_method": "Auditors' review of 100 change orders on 8 construction projects, 2000 to 2001; not a random sample of all projects",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-100-change-orders-12-million",
      "cite_as": "Cite as: Contracts Connected, \"What 100 reviewed change orders added to eight Missouri highway projects,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-100-change-orders-12-million. Original source: Missouri Office of State Auditor (Claire McCaskill), Missouri Department of Transportation Contract Change Orders (performance audit, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "west-virginia-legislature-2002-jail-change-orders-51-95-percent",
      "title": "How much change orders raised one West Virginia jail contract",
      "section": "How much change orders add to cost",
      "kind": "figure",
      "statistic": "51.95%",
      "wording": "A West Virginia legislative audit found change orders of $3,399,309 were added to the $6,543,000 Eastern Regional Jail construction contract, a total increase of 51.95%. Later jail contracts stayed under a 5% increase.",
      "limit": "One project, 1997 to 1999, in a memo from a state audit office. It does not show what is typical.",
      "source_publisher": "West Virginia Legislature, Legislative Post Audit Division",
      "source_title": "Follow-up Review of the Change Orders Issued for Regional Jail Construction Contracts (memo dated July 11, 2002)",
      "source_url": "https://www.wvlegislature.gov/legisdocs/reports/agency/PA/PA_2002_90.pdf",
      "source_year": "2002",
      "sample_or_method": "Review of one agency's construction contracts; the 51.95% is one facility for the period July 1, 1997 to December 31, 1999",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#west-virginia-legislature-2002-jail-change-orders-51-95-percent",
      "cite_as": "Cite as: Contracts Connected, \"How much change orders raised one West Virginia jail contract,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#west-virginia-legislature-2002-jail-change-orders-51-95-percent. Original source: West Virginia Legislature, Legislative Post Audit Division, Follow-up Review of the Change Orders Issued for Regional Jail Construction Contracts (memo dated July 11, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "west-virginia-legislature-2002-three-contracts-change-orders",
      "title": "How much change orders raised three later West Virginia contracts",
      "section": "How much change orders add to cost",
      "kind": "figure",
      "statistic": "4.14%, 1.96%, 2.74%",
      "wording": "In the 2002 follow-up, West Virginia auditors found change orders raised the North Central Regional Jail contract by 4.14%, the Lakin Correctional Center contract by 1.96% and the Western Regional Jail contract by 2.74%.",
      "limit": "Two of the three contracts were unfinished, so the final shares may be higher.",
      "source_publisher": "West Virginia Legislature, Legislative Post Audit Division",
      "source_title": "Follow-up Review of the Change Orders Issued for Regional Jail Construction Contracts (memo dated July 11, 2002)",
      "source_url": "https://www.wvlegislature.gov/legisdocs/reports/agency/PA/PA_2002_90.pdf",
      "source_year": "2002",
      "sample_or_method": "Three general construction contracts; Lakin was 95% complete and Western about 50% complete when reviewed",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#west-virginia-legislature-2002-three-contracts-change-orders",
      "cite_as": "Cite as: Contracts Connected, \"How much change orders raised three later West Virginia contracts,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#west-virginia-legislature-2002-three-contracts-change-orders. Original source: West Virginia Legislature, Legislative Post Audit Division, Follow-up Review of the Change Orders Issued for Regional Jail Construction Contracts (memo dated July 11, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "missouri-auditor-2002-modot-3-percent-change-order-rate",
      "title": "Missouri DOT's own change order rate, and three neighboring states",
      "section": "How many change orders agencies issue",
      "kind": "figure",
      "statistic": "3 percent",
      "wording": "Missouri Department of Transportation officials told auditors their 3 percent change order rate was comparable or better than neighboring states: Kansas 2 to 5 percent, Iowa 5.4 percent and Illinois 4 to 7 percent.",
      "limit": "This is the department's own claim about itself and three other states, from 2002. It is not an audit finding.",
      "source_publisher": "Missouri Office of State Auditor (Claire McCaskill)",
      "source_title": "Missouri Department of Transportation Contract Change Orders (performance audit, 2002)",
      "source_url": "https://auditor.mo.gov/press/2002-96.pdf",
      "source_year": "2002",
      "sample_or_method": "Department officials' statement quoted in the audit summary; not an audit finding",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-modot-3-percent-change-order-rate",
      "cite_as": "Cite as: Contracts Connected, \"Missouri DOT's own change order rate, and three neighboring states,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-modot-3-percent-change-order-rate. Original source: Missouri Office of State Auditor (Claire McCaskill), Missouri Department of Transportation Contract Change Orders (performance audit, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "minnesota-auditor-2023-southwest-light-rail-change-orders",
      "title": "Change orders on the Southwest light rail civil construction contract",
      "section": "How many change orders agencies issue",
      "kind": "figure",
      "statistic": "$224,093,394",
      "wording": "Minnesota's Legislative Auditor found that from March 2019 to October 2022, 550 of 658 civil construction change orders on the Southwest light rail project increased cost, by a total of $224,093,394. 44 decreased cost and 64 had no cost effect, for a net total impact of $219,452,031.",
      "limit": "One very large transit project. It shows the dollars and counts, not a share of contract value.",
      "source_publisher": "Minnesota Office of the Legislative Auditor, Program Evaluation Division",
      "source_title": "Southwest Light Rail Transit Construction: Metropolitan Council Oversight of Contractors (June 2023)",
      "source_url": "https://www.auditor.leg.state.mn.us/ped/pedrep/swlrtco.pdf",
      "source_year": "2023",
      "sample_or_method": "Auditor's analysis of Metropolitan Council data for one civil construction contract, March 2019 to October 2022 (Exhibit 2.1)",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#minnesota-auditor-2023-southwest-light-rail-change-orders",
      "cite_as": "Cite as: Contracts Connected, \"Change orders on the Southwest light rail civil construction contract,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#minnesota-auditor-2023-southwest-light-rail-change-orders. Original source: Minnesota Office of the Legislative Auditor, Program Evaluation Division, Southwest Light Rail Transit Construction: Metropolitan Council Oversight of Contractors (June 2023), 2023. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "caltrans-2024-change-orders-in-one-quarter",
      "title": "Caltrans change orders in one quarter, October to December 2023",
      "section": "How many change orders agencies issue",
      "kind": "figure",
      "statistic": "1,253 change orders, $346.9 million",
      "wording": "Caltrans says its 12 districts issued 1,253 change orders worth $346.9 million, including supplemental change orders, from October to December 2023. For July to September 2023 it reported 1,187 change orders worth $285.1 million.",
      "limit": "Counts and dollars for single quarters, not a percent of contract value, so it cannot be turned into a share.",
      "source_publisher": "California Department of Transportation",
      "source_title": "Change (order) is a fact of life in Construction, Mile Marker 2024 Issue 1",
      "source_url": "https://dot.ca.gov/programs/public-affairs/mile-marker/2024-01/change-orders",
      "source_year": "2024",
      "sample_or_method": "Agency's quarterly count of change orders across its districts",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#caltrans-2024-change-orders-in-one-quarter",
      "cite_as": "Cite as: Contracts Connected, \"Caltrans change orders in one quarter, October to December 2023,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#caltrans-2024-change-orders-in-one-quarter. Original source: California Department of Transportation, Change (order) is a fact of life in Construction, Mile Marker 2024 Issue 1, 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "wsdot-2024-large-change-orders-fourth-quarter",
      "title": "WSDOT change orders of $500,000 or more, fourth quarter 2024",
      "section": "How many change orders agencies issue",
      "kind": "figure",
      "statistic": "9 change orders of $500,000 or more",
      "wording": "The Washington State Department of Transportation says it tracked nine change orders of $500,000 or more in the fourth quarter of 2024, and it posts all such change orders each month.",
      "limit": "Counts only large change orders, not all of them, and no contract value share is given.",
      "source_publisher": "Washington State Department of Transportation",
      "source_title": "Gray Notebook, Change orders",
      "source_url": "https://wsdot.wa.gov/about/data/gray-notebook/gnbhome/stewardship/advertisement/changeorders.htm",
      "source_year": "2024",
      "sample_or_method": "Agency's count of large change orders ($500,000 or more) by quarter, 2020 Q1 through 2024 Q4",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#wsdot-2024-large-change-orders-fourth-quarter",
      "cite_as": "Cite as: Contracts Connected, \"WSDOT change orders of $500,000 or more, fourth quarter 2024,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#wsdot-2024-large-change-orders-fourth-quarter. Original source: Washington State Department of Transportation, Gray Notebook, Change orders, 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "cii-1991-scope-modification-most-common-source-of-change",
      "title": "The most common source of change and the highest-impact cause of overruns, 1991",
      "section": "Why change orders happen and whether they can be avoided",
      "kind": "figure",
      "statistic": "Qualitative",
      "wording": "A 1991 Construction Industry Institute report says scope modification is the most common source of change, and that poor scope definition is the highest-impact cause of projects running over budget.",
      "limit": "Qualitative findings from the report's abstract page only, published in 1991. The abstract page gives no sample size or percentages.",
      "source_publisher": "Construction Industry Institute (CII)",
      "source_title": "Construction Changes and Change Orders: Their Magnitude and Impact (Publication SD-66, April 1, 1991, 125 pages)",
      "source_url": "https://www.construction-institute.org/construction-changes-and-change-orders-their-magnitude-and-impact",
      "source_year": "1991",
      "sample_or_method": "Research report; the page gives no sample size or percentages (those are in Chapter 5 and Appendix B, not shown)",
      "geography": "Not stated",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#cii-1991-scope-modification-most-common-source-of-change",
      "cite_as": "Cite as: Contracts Connected, \"The most common source of change and the highest-impact cause of overruns, 1991,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#cii-1991-scope-modification-most-common-source-of-change. Original source: Construction Industry Institute (CII), Construction Changes and Change Orders: Their Magnitude and Impact (Publication SD-66, April 1, 1991, 125 pages), 1991. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "missouri-auditor-2002-avoidable-change-order-line-items",
      "title": "Missouri change order line items the auditors called avoidable",
      "section": "Why change orders happen and whether they can be avoided",
      "kind": "figure",
      "statistic": "330 of 796 line items",
      "wording": "Missouri auditors counted 796 line items in the 100 change orders they reviewed, called 59% of the line items necessary and unforeseen before the contract was awarded, and found the department could have avoided 330 of them, totaling $5.8 million.",
      "limit": "Auditor's opinion on a small sample. 'Avoidable' means officials could have handled the project properly before it went to bid.",
      "source_publisher": "Missouri Office of State Auditor (Claire McCaskill)",
      "source_title": "Missouri Department of Transportation Contract Change Orders (performance audit, 2002)",
      "source_url": "https://auditor.mo.gov/press/2002-96.pdf",
      "source_year": "2002",
      "sample_or_method": "Same 100 change orders on 8 projects; auditors' judgment of necessity",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-avoidable-change-order-line-items",
      "cite_as": "Cite as: Contracts Connected, \"Missouri change order line items the auditors called avoidable,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-avoidable-change-order-line-items. Original source: Missouri Office of State Auditor (Claire McCaskill), Missouri Department of Transportation Contract Change Orders (performance audit, 2002), 2002. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "arcadis-2024-owner-directed-changes-rank-among-dispute-causes",
      "title": "Where owner-directed changes rank among causes of construction disputes",
      "section": "Why change orders happen and whether they can be avoided",
      "kind": "figure",
      "statistic": "Owner-directed changes: 4th",
      "wording": "Arcadis's 2024 North America disputes report, using 2023 survey results, ranks owner-directed changes as the fourth most common cause of construction disputes (fifth in 2022). The average dispute value was $43 million and the average length was 14.4 months.",
      "limit": "It ranks causes of disputes, not how often change orders happen. Covers North America, not the U.S. alone.",
      "source_publisher": "Arcadis",
      "source_title": "14th Annual Construction Disputes Report, North America 2024: Managing Construction Disputes in the Digital Age",
      "source_url": "https://www.arcadis.com/-/media/project/arcadiscom/com/expertise/global/contract-solutions/14th-annual-construction-disputes-report-2024.pdf",
      "source_year": "2024",
      "sample_or_method": "Survey by the Arcadis North America Contract Solutions team; only North American input; sample size not stated in the sections read",
      "geography": "US and Canada",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#arcadis-2024-owner-directed-changes-rank-among-dispute-causes",
      "cite_as": "Cite as: Contracts Connected, \"Where owner-directed changes rank among causes of construction disputes,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#arcadis-2024-owner-directed-changes-rank-among-dispute-causes. Original source: Arcadis, 14th Annual Construction Disputes Report, North America 2024: Managing Construction Disputes in the Digital Age, 2024. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "gao-2019-army-corps-changes-over-60-days",
      "title": "Army Corps contract changes that took more than 60 days to finalize",
      "section": "How long changes take and what they do to productivity",
      "kind": "figure",
      "statistic": "About 45%",
      "wording": "GAO reported that about 45% of completed construction contract changes at the Army Corps of Engineers from 2013 through 2018 took more than 60 days to finalize, and a little more than 3% took more than one year.",
      "limit": "This is time to process a change, not cost or how often changes happen. One agency's data, compiled ad hoc by USACE officials.",
      "source_publisher": "U.S. Government Accountability Office",
      "source_title": "GAO-19-500, Federal Construction: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes (July 2019)",
      "source_url": "https://www.gao.gov/assets/710/700108.pdf",
      "source_year": "2019",
      "sample_or_method": "USACE data on contract changes finalized January 2013 to August 2018, measured from the contractor's proposal to the finalized change; excludes terminations, claims, options and administrative modifications",
      "geography": "US",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#gao-2019-army-corps-changes-over-60-days",
      "cite_as": "Cite as: Contracts Connected, \"Army Corps contract changes that took more than 60 days to finalize,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#gao-2019-army-corps-changes-over-60-days. Original source: U.S. Government Accountability Office, GAO-19-500, Federal Construction: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes (July 2019), 2019. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "gao-2019-gsa-could-not-provide-change-timing-data",
      "title": "GSA could not provide data on how long its contract changes take",
      "section": "How long changes take and what they do to productivity",
      "kind": "figure",
      "statistic": "GSA could not provide data",
      "wording": "GAO found that the Army Corps reviews change data only on an ad hoc basis, and that the General Services Administration was unable to provide similar data on how long its construction contract changes take.",
      "limit": "Describes the data gap in 2019; agencies may have changed since.",
      "source_publisher": "U.S. Government Accountability Office",
      "source_title": "GAO-19-500, Federal Construction: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes (July 2019)",
      "source_url": "https://www.gao.gov/assets/710/700108.pdf",
      "source_year": "2019",
      "sample_or_method": "GAO review of Army Corps and GSA change processes and data",
      "geography": "US",
      "status": "Reviewed",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#gao-2019-gsa-could-not-provide-change-timing-data",
      "cite_as": "Cite as: Contracts Connected, \"GSA could not provide data on how long its contract changes take,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#gao-2019-gsa-could-not-provide-change-timing-data. Original source: U.S. Government Accountability Office, GAO-19-500, Federal Construction: Army Corps of Engineers and GSA Need to Improve Data on Contract Changes (July 2019), 2019. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "cii-1994-efficiency-on-changed-work",
      "title": "Labor efficiency on changed work, four sites over 151 weeks",
      "section": "How long changes take and what they do to productivity",
      "kind": "figure",
      "statistic": "70% of normal",
      "wording": "A 1994 Construction Industry Institute study of productivity data from four construction sites over 151 weeks found labor efficiency on changed work averaged about 70 percent of normal, and about a third of the days with changed work showed no loss.",
      "limit": "Small sample (four sites) and more than 30 years old; the page does not say the sites were in the U.S. It measures labor productivity on changed work, not project cost growth.",
      "source_publisher": "Construction Industry Institute (CII)",
      "source_title": "The Effects of Change on Labor Productivity: Why and How Much (Publication SD-99, August 1, 1994)",
      "source_url": "https://www.construction-institute.org/the-effects-of-change-on-labor-productivity-why-and-how-much",
      "source_year": "1994",
      "sample_or_method": "Productivity data from four active construction sites, 151 weeks",
      "geography": "Not stated",
      "status": "Reviewed, with limits",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#cii-1994-efficiency-on-changed-work",
      "cite_as": "Cite as: Contracts Connected, \"Labor efficiency on changed work, four sites over 151 weeks,\" Contracts Connected Data, https://contractsconnected.com/data/change-order-statistics#cii-1994-efficiency-on-changed-work. Original source: Construction Industry Institute (CII), The Effects of Change on Labor Productivity: Why and How Much (Publication SD-99, August 1, 1994), 1994. Reviewed November 2026. Compilation licensed under CC BY 4.0.",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "cii-1994-30-percent-productivity-loss-claim-check",
      "title": "Claim check: \"Change orders cause a 30 percent productivity loss\"",
      "section": "Claim checks: where widely repeated figures came from",
      "kind": "claim_check",
      "statistic": "'Change orders cause a 30 percent productivity loss'",
      "wording": "Change orders cut labor productivity by about 30 percent",
      "limit": "It does not show a 30 percent loss across whole projects or on all change orders, and it is a small sample.",
      "source_publisher": "Construction Industry Institute (CII)",
      "source_title": "The Effects of Change on Labor Productivity: Why and How Much (Publication SD-99, August 1, 1994)",
      "source_url": "https://www.construction-institute.org/the-effects-of-change-on-labor-productivity-why-and-how-much",
      "source_year": "1994",
      "sample_or_method": "Four construction sites, 151 weeks.",
      "geography": "",
      "status": "Claim check: not cited as a finding",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#cii-1994-30-percent-productivity-loss-claim-check",
      "cite_as": "",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "missouri-auditor-2002-no-national-change-order-share-claim-check",
      "title": "Claim check: a single national \"average change order share\"",
      "section": "Claim checks: where widely repeated figures came from",
      "kind": "claim_check",
      "statistic": "No national 'average change order share'",
      "wording": "A single industry-wide figure for change orders as a share of contract value",
      "limit": "No source in our review supports one national number.",
      "source_publisher": "Missouri Office of State Auditor (Claire McCaskill)",
      "source_title": "Missouri Department of Transportation Contract Change Orders (performance audit, 2002)",
      "source_url": "https://auditor.mo.gov/press/2002-96.pdf",
      "source_year": "2002",
      "sample_or_method": "",
      "geography": "",
      "status": "Claim check: not cited as a finding",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#missouri-auditor-2002-no-national-change-order-share-claim-check",
      "cite_as": "",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    },
    {
      "id": "nnbw-2002-nevada-change-orders-claim-check",
      "title": "Claim check: Nevada road projects, 2002, 731 change orders",
      "section": "Claim checks: where widely repeated figures came from",
      "kind": "claim_check",
      "statistic": "Nevada 2002: 98 projects, $447 million to $487 million, 731 change orders",
      "wording": "Change orders added $40 million to Nevada Department of Transportation road projects over 30 months, a rate of nearly 9 percent",
      "limit": "The figures are second-hand and 24 years old. We did not find the audit, so they are unverified.",
      "source_publisher": "Northern Nevada Business Weekly",
      "source_title": "News report, March 14, 2002, on an Executive Branch Audit Committee hearing",
      "source_url": "https://nnbw.com/news/2002/mar/14/ndot-change-orders-cost-state-40-million",
      "source_year": "2002",
      "sample_or_method": "Second-hand news report of a state audit of 98 road projects, January 1, 1999 to June 30, 2001.",
      "geography": "",
      "status": "Claim check: not cited as a finding",
      "checked_on": "2026-11-03",
      "canonical_url": "https://contractsconnected.com/data/change-order-statistics#nnbw-2002-nevada-change-orders-claim-check",
      "cite_as": "",
      "license": "https://creativecommons.org/licenses/by/4.0/",
      "changelog": [
        {
          "date": "2026-11-03",
          "type": "Added",
          "note": "Checked against the original source."
        }
      ]
    }
  ]
}