The 13 checks every federal prime contractor must run on every pay-app cycle, covering proper invoice, interest accrual tracking, and 7-day sub flow-down, so the Act works for you instead of against you.
Why federal primes leave Prompt Payment interest uncollected, and why that stops today
Federal prime contractors get paid on a schedule defined by statute, 41 U.S.C. §§ 3901–3907, the federal Prompt Payment Act, not by the contracting officer’s workload or the agency’s cash position. The Act requires federal agencies to pay prime contractors within 14 calendar days of receiving a proper invoice for construction contracts, and it requires primes to flow that payment down to subcontractors within 7 days of receiving it from the agency. Miss the window and the government automatically owes interest. That sounds like the contractor’s benefit, and on agency-to-prime payments, it is. But the flow-down obligation works in the other direction too: a prime that holds sub payments past the 7-day window owes the sub automatic interest under the same statute. Most primes do not know this until the first dispute.
The practical problem is that “proper invoice” is a defined term under FAR 52.232-27, not a judgment call. An invoice is proper only if it includes the contractor’s name, address, and invoice number; the contract number; a description of the services performed; the payment terms; and the amount payable. Many primes fail to submit proper invoices on the first attempt, not because the underlying work is disputed but because a required field is missing or the invoice format does not match the agency’s requirements. Every rejection resets the 14-day payment clock to the date the proper invoice is received, not the date the defective one was submitted.
The interest accrual mechanics are more complex than most PMs realize. Interest accrues automatically from the day after the payment due date at the Treasury Department’s published ratchet rate. But the interest does not get added to the final invoice automatically; someone has to track the overdue days, calculate the accrual, and include it in the subsequent invoice. Most contractors do not do this, leaving money on the table every time an agency is slow to pay.
The team behind this checklist spent 15 years running federal construction projects and watching prime contractors miss their own interest claims because nobody tracked the payment clock, and watching subs get short-paid because the prime held the 7-day flow-down payment while sorting out an internal dispute. This checklist is the administrative layer that prevents both failures. 13 checks that run alongside every pay-app cycle to confirm the invoice is proper, the payment clock is documented, the interest accrual is tracked, and the sub flow-down happens on time with the right documentation.
Who this checklist is for
- Federal general contractors managing pay applications on USACE, NAVFAC, GSA, VA, Air Force, or Federal Highway projects
- Prime contractors on any federally-funded construction contract above $150,000 with the Prompt Payment Act flowing through the contract clauses
- Project managers who own the pay-app submission and payment-tracking workflow
- Accounting staff reconciling payment receipt dates, interest accrual, and sub disbursement timing
- Compliance officers preparing for DCAA audit or contracting officer review of payment documentation
If you are on a commercial project without federal funding, the federal Prompt Payment Act does not apply, but most states have their own prompt payment statutes. For the federal retention-specific release timing overlay, see also the retention release tracker.
The 13-item pay-app-cycle compliance checklist
The checklist covers 13 things every federal prime must verify on every pay-app cycle.
- Verify the invoice meets the “proper invoice” definition under FAR 52.232-27. FAR 52.232-27 (Prompt Payment for Construction Contracts) defines a proper invoice as one that includes the contractor’s name and address, invoice date, contract number, description of services performed, payment terms, amount payable, and name and address of the designated billing office. Review every submitted invoice against this checklist before submission, not after. An improper invoice returned by the contracting officer resets the 14-day payment clock to the date the proper invoice is received, not the date the defective one was submitted.
- Confirm the invoice is addressed to the correct designated billing office. FAR requires invoices to be submitted to the “designated billing office” identified in the contract, specifically in Section G. Not to the contracting officer’s address, not to the project manager’s inbox, not to the agency’s general accounts-payable email. Many primes submit invoices to the wrong address and are surprised when the payment clock does not start. Verify the designated billing office address at the beginning of every project; agency billing offices change and the Section G address supersedes any verbal instruction from the field.
- Document the date of actual invoice receipt by the contracting officer. The 14-day payment window starts on the date the contracting officer’s designated billing office receives a proper invoice, not the date the prime submitted it, not the postmark date, and not the date the contracting officer reviewed it. For electronic submission, this is the timestamp of the agency’s confirmation email. For mail submission, it is the certified-mail delivery date. Record this date in the pay-app log the day confirmation arrives. A week’s difference in the receipt date changes whether a payment is timely or triggers interest.
- Calculate the payment due date and log it in the pay-app tracker. Once the receipt date is confirmed, calculate the payment due date as 14 calendar days from receipt (not 14 business days). Mark this date in the pay-app tracker and the project calendar. The payment due date is the threshold for interest accrual. One day past it and interest starts running automatically. Primes that do not track the due date never know whether to include interest in the subsequent invoice and never capture what the Act entitles them to collect.
- Track interest accrual from the day after the payment due date. If payment has not arrived by the due date, begin tracking interest accrual at the current applicable Treasury rate published quarterly at the Bureau of the Fiscal Service. The interest formula under 41 U.S.C. §3902: (amount overdue) × (Treasury rate ÷ 360) × (days overdue). This amount must be included as a line item in the subsequent invoice or in a separate interest invoice submitted when the overdue principal is eventually paid. Most primes do not do this. The interest entitlement does not require negotiation. It is automatic by statute.
- Verify the agency has not issued a “notice of defect” that justifies the delay. The agency may return a payment with a written notice of defect identifying a specific problem with the invoice or the underlying work. A valid notice of defect stops the interest clock. The payment due date resets to 7 days after the prime cures the defect and resubmits a proper invoice. Review every notice of defect before accepting it as a valid clock reset: the notice must identify a specific, documented defect, not a general objection. Disputes about the work itself do not excuse late payment under the Act.
- Confirm payment received and log the actual receipt date. Log the date the payment actually hits the prime’s account, not the date it was issued by the agency, not the date the check was in the mail. The actual receipt date is the starting point for the sub flow-down 7-day clock. It is also the date from which you measure whether the agency met its 14-day obligation. Use bank confirmation, not agency notification, as the authoritative receipt date.
- Verify sub flow-down payment is initiated within 7 days of prime receipt. FAR 52.232-27 requires the prime to pay subcontractors within 7 days of receiving payment from the agency. The 7-day window is calendar days, not business days, and it runs from the date the prime actually receives payment, not from the date the prime’s accounting team processes it. Initiate sub payments via ACH or wire on the day of receipt or the day after; paper checks introduce processing delays that can push the disbursement past the 7-day window.
- Confirm sub payment amount matches the proportionate share of the prime’s received payment. The flow-down amount to each sub must be proportionate to that sub’s share of the pay application for which payment was received. If the agency pays 95% of the prime’s invoice, the prime passes 95% of each sub’s line item, not 100% of the sub’s invoiced amount and not a different percentage that the prime’s accounting system calculated on a different basis. Incorrect proportioning is a Prompt Payment Act violation even if the payment arrives within 7 days.
- Verify sub payment includes pass-through interest if prime received interest from the agency. If the agency paid interest to the prime for a late payment, the prime must pass through a proportionate share of that interest to each sub whose work was included in the overdue invoice. The interest pass-through is required under FAR 52.232-27 and most primes do not do it. Document the total interest received, the applicable sub shares, and the pass-through disbursement in the payment log. Missing this step is both a compliance violation and leaves the sub short-paid.
- Confirm sub payment documentation includes invoice and payment reference. Every sub payment disbursement should be accompanied by a remittance document that identifies: the prime’s invoice number, the agency’s payment reference, the sub’s contract number, the applicable pay-app period, and the total amount being released including any interest pass-through. The remittance document creates the paper trail that a DCAA auditor or contracting officer review can follow when auditing sub flow-down compliance. Lump-sum wire transfers with no remittance documentation are a red flag in every federal payment audit.
- Log any sub disputes or payment holds with a documented contractual basis. If a sub’s payment is being withheld, for punch list work, disputed quantities, or a back-charge, the hold must be documented with a specific contractual basis and a copy sent to the sub in writing within the 7-day window. A prime cannot hold a sub’s Prompt Payment share to cover an unrelated dispute from a previous pay application. The withholding must be specific to the current pay-app period and documented as such. Undocumented holds are Prompt Payment Act violations regardless of the underlying dispute.
- Archive the complete pay-app cycle record for each period. The complete record for each pay-app cycle includes: the invoice as submitted, the agency receipt confirmation, the payment due date calculation, the actual receipt date, the sub disbursement confirmations with remittance details, any interest calculations and pass-throughs, and any notices of defect received and cured. This archive is what the contracting officer’s review, DCAA audit, or sub dispute needs to resolve questions about payment timing. Without it, the prime cannot demonstrate compliance and cannot collect interest it is statutorily entitled to.
How to run this checklist on every pay-app cycle
Run this checklist on every pay-app cycle, not just when a payment is late. The value of the checklist is in catching improper invoices before submission, tracking the payment clock before it expires, and ensuring sub flow-down happens within the 7-day window every time.
- Before submitting the invoice: verify items 1 and 2 (proper invoice, correct billing office).
- On submission day: log the submission method and document the expected receipt confirmation timeline (item 3).
- On receipt confirmation: log the actual receipt date and calculate the payment due date (items 3 and 4).
- On the payment due date plus 1: if payment has not arrived, begin tracking interest accrual (item 5).
- When the agency responds (payment or defect notice): log the actual receipt date or review the defect notice (items 6 and 7).
- On the day payment is received: initiate sub disbursements (items 8 and 9). If interest was received, calculate and pass through proportionate shares (item 10).
- With every sub disbursement: send the remittance document (item 11). Document any holds with a contractual basis (item 12).
- End of cycle: archive the complete record (item 13).
Stop running Prompt Payment compliance from memory
The Prompt Payment Act is automatic. The obligations run whether or not anyone in your project team is tracking them. The primes that capture their interest entitlements and stay out of flow-down disputes are the ones whose pay-app cycle is documented start to finish: receipt date logged, due date calculated, sub disbursements initiated within 7 days, and the remittance confirmation archived before the next invoice goes out. Contracts Connected’s Approval Workflows builds that documentation layer directly into the pay-app cycle. Every receipt date captured, every sub payment triggered on the correct clock, every interest accrual calculated and surfaced for the next invoice. The Act works for you or against you. The documentation is what decides which.
For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.
Frequently asked questions about the prompt Payment Act compliance checklist
What is the federal Prompt Payment Act and who does it cover?
The federal Prompt Payment Act (41 U.S.C. §§ 3901–3907) is a federal statute that requires federal agencies to pay contractors within defined windows, 14 calendar days from receipt of a proper invoice for construction contracts, and that flows payment obligations down through the prime-to-sub chain. FAR 52.232-27 implements the Act’s construction-contract provisions. The Act applies to every federal construction contract regardless of dollar value, though the required flow-down clause (FAR 52.232-27) is typically included only in contracts above the simplified acquisition threshold ($250,000). Below that threshold, the Act’s interest provisions still apply to the agency-prime relationship even if the flow-down clause is absent.
What happens if the federal agency pays late?
Interest accrues automatically from the day after the payment due date at the Treasury Department’s ratchet rate (published quarterly). The prime does not need to request the interest or send a separate demand. It is owed as a matter of statute. However, the prime does need to include the interest amount in a subsequent invoice or a standalone interest invoice to actually receive it. Many primes never collect this interest because they do not track the payment clock or include the interest line on subsequent invoices. The interest amount is real money on large pay applications. On a $500,000 invoice paid 30 days late at a 5% Treasury rate, the interest accrual is approximately $2,083.
What counts as a “proper invoice” under FAR 52.232-27?
A proper invoice under FAR 52.232-27 must include: contractor’s name, address, and invoice number; contract number and order number (if applicable); description of services and the applicable contract line item; payment terms; amount payable; and the name and address of the designated billing office specified in the contract. For construction contracts, it must also include the contractor’s progress payment schedule or schedule of values reference. Invoices missing any required field are not proper invoices and the 14-day clock does not start until the corrected invoice is received.
Does the 7-day flow-down requirement apply to all subcontractors?
FAR 52.232-27 requires the prime to pay each subcontractor for “satisfactory performance” within 7 days of receiving payment from the agency. The requirement applies to all first-tier subcontractors on the prime contract. FAR 52.232-5 (Payments Under Fixed-Price Construction Contracts) further requires the prime to include a flow-down clause in every subcontract requiring the sub to pay its tier-2 subs within 7 days of receiving payment from the prime. The 7-day obligation cascades through every tier of the payment chain. A prime that pays first-tier subs on time but fails to require and verify the 7-day flow-down to tier-2 subs may still face compliance exposure on a DCAA audit.
Can a prime withhold a sub’s Prompt Payment share due to a dispute?
A prime may withhold a payment to a sub if there is a “bona fide dispute” between the prime and the sub about the amount owed. The prime must notify the sub in writing of the specific basis for the withholding within the 7-day window. A general “dispute pending” hold is not sufficient. The withheld amount must be specifically tied to the current pay-app period and the specific work in dispute; the prime cannot hold the current period’s payment to offset an unrelated dispute from a previous period. Interest continues to accrue on any improperly withheld amount even during a dispute.
What records should the prime retain for Prompt Payment Act compliance?
At minimum: the invoice as submitted with the date-stamped submission confirmation; the agency’s receipt confirmation or billing-office-stamped copy; the payment due date calculation worksheet; the actual payment receipt date confirmed by bank statement; the sub disbursement ACH or wire confirmations with remittance details; any interest calculations and pass-through documentation; any notices of defect received and the cured invoice; and any sub payment hold notifications with the contractual basis. Retain for the contract’s FAR 4.703 retention period (6 years 3 months for construction contracts) or longer if specified in the contract.