Free Estimate Review / Sanity-Check Checklist for Construction

The 15-point second-reviewer gate that catches the errors living inside a number that looks right from the outside.

ExcelWordPDF

The 15-point second-reviewer gate every principal, senior estimator, and pre-construction manager runs on a completed estimate before it becomes a proposal. Catching the errors that live inside a number that looks right from the outside.

Why construction estimates need a second-reviewer sanity check

The estimate is done. Your lead estimator spent three weeks on it. The number is in the summary sheet, the markup is applied, and the cover page has the project name on it. And now you’re about to put your name on it and send it to a client.

Before you do: when was the last time you found something in a finished estimate that changed your number?

Not “adjusted the markup slightly.” Found something. A missed trade, a wrong unit cost, a general conditions line that was built for a 12-month project that the schedule calls for in 18 months, a material cost that was priced off a quote that expired four months ago. The kind of thing that, if you hadn’t caught it, would have cost you real money six months into the job.

The problem is that estimate review is the step everyone thinks they’re doing when they open the spreadsheet and look at the total. That’s not a review. That’s a sanity check on the output without touching the inputs. A real estimate review goes into the source data: the unit costs, the quantities, the labor productivities, the sub bids, the general conditions assumptions, and the contract terms that change what’s actually required.

This checklist is organized around the categories of errors that actually appear in construction estimates. Not conceptual errors, operational ones. The sub bid that was used as a placeholder but never confirmed. The concrete unit cost that was accurate last year before rebar went up 18%. The general conditions that was copy-pasted from a similar project without adjusting for the fact that this project requires two superintendents, not one. The escalation factor that was discussed and then never made it into the summary.

These errors share a common feature: they’re not visible from the output. The total looks reasonable. The markup looks right. The project type matches the budget history. The error lives in a cell four levels deep in the detail, where nobody goes unless they’re specifically looking.

The 15 items on this checklist are specific enough to actually find those errors. They’re written for a second reviewer. Someone who didn’t build the estimate and is seeing it fresh. That’s intentional. The person who built the estimate will not find their own systematic errors no matter how carefully they review their own work. Second-reviewer review is not a luxury; it’s the only mechanism that works.

Who this checklist is for

  • Principals and project executives signing off on estimates before they become proposals. This checklist is the verification step that happens before the signature
  • Senior estimators reviewing estimates produced by junior team members or brought in from a branch office
  • Pre-construction managers validating owner’s estimates, design-phase budgets, and GMP proposals before presenting to the client
  • Estimating managers building a consistent review process across multiple estimators in a growing department

The 15-point estimate review checklist

The checklist covers 15 things a second reviewer must verify before an estimate becomes a proposal:

  1. Verify the estimate is based on the current drawing set and addendum log. Confirm the drawing revision numbers in the estimate match the most recent issued set, and that all issued addenda are acknowledged and incorporated. Estimates built on superseded drawings produce numbers that don’t match the current scope, and the owner won’t know that’s the reason for your number until you’re in a scope-gap argument post-award.
  2. Confirm every trade has a source for its number. Sub bid, in-house estimate, or documented allowance. Pull the source document for the top 10 line items by dollar value. For each one, verify there’s a real source: a written sub bid with a scope, a unit-cost database reference with a date, or a documented allowance with a basis. “PM’s gut feel” and “similar to last project” are not sources. They’re assumptions that belong in an allowance column with a contingency applied.
  3. Check sub bid coverage. Are all major trades covered, and are the bids current? For any trade with a received sub bid as the source, confirm: the bid is in writing, the bid covers the full scope, and the bid hasn’t expired. A verbal sub number that hasn’t been confirmed in writing is a liability. An expired sub bid may not be honored. A sub bid that covers only part of the scope while you’ve allocated the full trade budget to it is a gap.
  4. Reconcile sub bid scope inclusions and exclusions to your scope assumption. Read the exclusions on every major sub bid. Subs exclude things constantly. Bond premiums, permit fees, owner-furnished equipment installation, commissioning labor, temporary services, final cleaning, and hoisting are the most common. If a sub excluded something you need in the base bid, you either need another line item covering it or an explicit exclusion in your proposal. Unreconciled sub bid exclusions become post-award claims.
  5. Verify unit costs are current. Dated within the last 12 months or confirmed with a supplier quote. Flag any unit cost in the estimate that’s older than 12 months and hasn’t been confirmed with a current supplier quote or current RS Means data. Materials pricing has moved significantly in the past three years. Concrete, steel, lumber, copper, and HVAC equipment have all had double-digit swings. An estimate using 2023 unit costs in a 2026 market is wrong before the first number is reviewed.
  6. Check labor productivity assumptions. Are they sourced from your firm’s actual job history or an external database? For each major self-perform scope, identify the labor productivity assumption (man-hours per unit). Verify it’s based either on your firm’s historical production records for the same scope type or on a published source (RS Means, NECA, MCAA) with any site-specific adjustments documented. A productivity assumption carried forward from a different project type or a different market is a hidden labor risk.
  7. Review general conditions for project-specific accuracy. Duration, staffing level, and site-specific requirements. Open the general conditions detail and verify: (a) the project duration matches the current schedule, not the schedule from when the estimate was started; (b) the superintendent and PM allocation matches the actual project complexity and size; (c) site-specific costs are captured (remote site per diem, multiple site locations, winter conditions, traffic control, etc.). General conditions is the line most frequently copy-pasted without adjustment; it’s also one of the largest lines on the estimate.
  8. Verify escalation is applied to materials and equipment on long-duration projects. For projects with a construction period longer than 12 months, or projects where procurement will happen 6+ months after the bid date, verify that escalation has been applied to materials and equipment costs. The escalation factor should be sourced (ENR construction cost index, published escalation forecasts, or supplier guidance) and should be applied to the exposed portion of the budget, not to lump-sum sub bids where the sub is absorbing the escalation risk.
  9. Confirm the owner-furnished, owner-installed (OFOI) deductions are correct and signed off. If the owner is furnishing equipment or materials that the GC installs, or furnishing and installing items that come out of the GC’s scope entirely, verify the deduction amounts are correct and that the owner has confirmed the scope in writing. Wrong OFOI deductions overstate or understate the GC’s scope. Both create problems at award.
  10. Check the contingency allocation. Is it sized appropriately for the project phase and risk profile? Verify the contingency percentage against the project’s design completion level (schematic = 15–20%, design development = 10–15%, 100% CDs = 5–8% for standard commercial) and the project’s specific risk profile (site conditions, long-lead equipment, new construction type, difficult owner). A 5% contingency on a schematic estimate is not a contingency. It’s a wish. An 18% contingency on a 100% CD estimate signals the estimator doesn’t trust their own number.
  11. Verify overhead and markup are applied consistently and at the correct rate. Check the markup rate against your firm’s bid authority matrix for this project type and client relationship. Verify the markup is applied to the correct cost base. Some estimating systems apply markup to all costs including sub bids; others apply a split markup (smaller margin on subs, larger on self-perform). Verify the formula in the estimate matches your firm’s intended method. A transposed rate or wrong formula base is an invisible error.
  12. Review alternates and unit prices for internal consistency with the base estimate. If the proposal includes alternates or unit prices, verify they’re internally consistent with the base estimate unit costs. A unit price that’s significantly higher or lower than the unit cost implied by the base bid creates a contract-level risk. The owner will use the unit price for change orders, and an anomalous unit price becomes an expensive precedent.
  13. Confirm allowances are sized appropriately and match the owner’s required amounts if specified. For each allowance in the estimate, verify: the amount is appropriate for the scope it’s covering (not a placeholder that’s 10x or 1/10x the actual exposure), and if the owner specified the allowance amount in the bid documents, the estimate uses the owner’s number, not your own. Some bid forms require specific allowance amounts to keep bids apples-to-apples; using your own figure when the owner specified one can disqualify the bid.
  14. Check the bid form. Does your total match the bid form entries, and are all required fields complete? Pull the bid form that goes to the owner and verify the number on the bid form matches the number in your estimate summary. Transcription errors between the estimate and the bid form happen under deadline pressure. Also verify all required bid form fields are complete. Project number, addendum acknowledgments, alternate pricing, unit prices, bond amount, legal entity name, officer signature authority.
  15. Run the arithmetic. Spot-check three major subtotals by hand against source data. Pick the three largest line items or trade sections and recalculate the subtotal from source data, outside of the estimating software. Spreadsheet formula errors are rare but real, especially in complex estimates with multiple linked sheets. Manual spot-checks on the three largest sections catch the errors that software validation misses.

How to run the estimate review

Run this checklist after the estimate is complete and before the proposal is submitted. Ideally 24 to 48 hours before the deadline so findings can be addressed. Assign the review to someone who didn’t build the estimate. For each item, mark it OK, Flag (note required), or Stop (must fix before submission). Items marked Stop require the lead estimator to correct the source and re-run the summary before the second reviewer signs off. Archive the completed checklist with the estimate in the project record.

Stop letting estimate errors make it to the proposal

The errors this checklist catches are not estimating failures. They’re process failures. A team that builds a good estimate and then doesn’t review it before submission is leaving money on the table through missed scope, wrong unit costs, and unchecked sub bids. Contracts Connected’s platform keeps your estimate sources, sub bids, and scope matrices in one place so the second reviewer has everything they need to run a real review, not a look at the output and a hope that the inputs were right.

For educational purposes. These templates, checklists, and trackers are operator-built starting points designed to help you move faster on the kind of work that usually drowns construction admins in email chains. They are not legal, insurance, accounting, or tax advice. Each project, jurisdiction, and contract has its own quirks. Review the document, refine the language, and consult your attorney, broker, CPA, or compliance officer before relying on it for a live project decision.

Frequently asked questions about estimate review

How long does a proper estimate review take?

For a well-organized estimate on a typical commercial project ($5M–$25M), expect 90 minutes to 3 hours for a thorough second-reviewer review. Larger, more complex estimates take longer proportionally. If the review consistently takes less than 30 minutes, the reviewer isn’t going deep enough. They’re looking at the output, not the inputs. Budget the time before bid day, not as an afterthought at 10 PM.

What’s the difference between an estimate review and a value engineering session?

An estimate review is a quality check on the existing estimate. Finding errors, confirming sources, and verifying accuracy. A value engineering session is a scope-modification exercise. Finding ways to reduce cost by changing materials, systems, or methods. They’re different exercises with different purposes. This checklist is for estimate review. VE happens separately, typically with the design team, and produces a different version of the estimate rather than a corrected version of the existing one.

Should the estimate review happen before or after the markup is applied?

Before. The markup should be applied after the cost estimate is confirmed correct. Reviewing a marked-up estimate makes the math harder to follow and tempts the reviewer to treat markup as a buffer against errors rather than a planned return. Review the cost estimate, confirm it’s right, then apply markup as a separate final step.

Who should perform the estimate review on a small team with one estimator?

On a single-estimator team, the principal or project executive becomes the second reviewer. They won’t have the technical depth of a senior estimator, but they can verify sources (are there written sub bids behind these numbers?), check the general conditions for project-specific accuracy, confirm the markup is correct, and spot-check the arithmetic. A non-estimator’s review is better than no second review, especially on the items that require source verification rather than technical judgment.

How do I handle an estimate review when there’s no time. The bid is due in two hours?

Triage. If there are only two hours, run items 1, 2, 8, 14, and 15 of this checklist. Those are the five items that catch the most damaging errors in the shortest time. Document that the full review was not completed and why. Then use the experience to change the process for next time: the review window needs to be built into the bid schedule from day one, not treated as something that happens if there’s time at the end.

What do I do if I find a material error during the review. Do I pull the bid?

Depends on the size of the error and the time remaining. A 2–3% error on a competitive hard bid is within normal rounding; decide whether to correct it or absorb the risk. A 10%+ error on a GMP proposal needs to be corrected before submission. Submitting a number you know is wrong creates both a financial and an ethical problem. If the correction requires more time than you have, talk to the owner’s rep about an extension or submission of a clarifying letter. Most sophisticated owners would rather have the right number than a fast wrong one.

Where this document lives in the system
Contract Operations · Contracts Connected
Product bridge

Contracts Connected tracks every document a vendor owes you against the contract, reads what comes back, and shows who can mobilize, who is compliant on site, and who can be paid. Construction compliance.

More in Bidding / estimating

All Bidding / estimating templates