Federal Contracting

FAR flow-down clauses by subcontract tier

A clause-by-clause reference for federal construction primes: what flows down by its own terms, what flows down only because the prime contract says so, and which clauses switch off below a dollar threshold.

On this page
  1. What is a FAR flow-down clause, and why does the subcontract tier matter?
  2. What are the three kinds of FAR flow-down obligations?
  3. How does the commercial-item flow-down limitation at FAR 52.244-6 work?
  4. Which FAR clauses must flow down into a federal construction subcontract?
  5. Which flow-downs actually reach every tier, and which stop at the first?
  6. What dollar thresholds switch a FAR flow-down clause on or off?
  7. What changed in 2025 and 2026 that most flow-down guides still get wrong?
  8. What flows down on a DoD construction subcontract that does not on a civilian one?
  9. How do small business flow-downs work differently from the rest?
  10. What does this page not cover?
  11. How does Contracts Connected help with flow-down compliance?
  12. Frequently asked questions

A flow-down clause is a provision of a federal prime contract that the prime contractor must insert into its subcontracts, so an obligation the government placed on the prime also binds the subcontractor. Federal construction flow-down is not one list. It is three separate mechanisms with different triggers, and they reach different tiers.

That distinction is the whole subject. A prime that treats flow-down as a single block of text either under-flows and takes on liability the subcontractor should have carried, or over-flows and hands the subcontractor a defense. Neither shows up until something goes wrong, which is usually years later.

What is a FAR flow-down clause, and why does the subcontract tier matter?

A FAR flow-down clause is a prime contract provision the prime is required to insert into its subcontracts, and the tier matters because most flow-down obligations stop after one level unless the clause explicitly says otherwise. Some clauses reach the first-tier subcontractor and go no further. Others are written to repeat themselves down the chain indefinitely.

The mechanism that makes a clause reach every tier is usually self-reference. FAR 52.222-11, the labor standards flow-down clause for construction, is included in its own required insertion list, so the first-tier subcontractor is obligated to put the same package into its own subcontracts, and so on down. FAR 52.244-6 does the same thing at paragraph (d): the contractor includes the terms of the clause, including that paragraph, in subcontracts awarded under the contract. Without that self-reference, the obligation dies at the tier where it was inserted.

This matters more in construction than in most federal work because construction subcontracting is deep. The Department of Defense, estimating the reach of its cybersecurity rule in the Federal Register, assumed five subcontractors behind every prime contractor offer, which produced a total estimate of 337,968 affected entities against 28,164 unique prime contract awardees (90 FR 43560, September 10, 2025). A rule that reaches all tiers touches roughly twelve times as many companies as one that stops at the prime.

What are the three kinds of FAR flow-down obligations?

There are three: clauses that are mandatory by their own terms, clauses that are mandatory only because the prime contract requires them, and conditional clauses that switch off when a threshold or condition is not met. Every clause in the matrix below belongs to one of those three categories, and the category determines what a contract administrator has to check.

Mandatory by their own terms. The clause carries its own subcontracts paragraph. FAR 52.204-25, the Section 889 telecommunications prohibition, is the cleanest example: it directs the contractor to insert the substance of the clause “in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products or commercial services.” No dollar threshold, no carve-out, no discretion. FAR 52.203-17 and FAR 52.232-40 work the same way within their own scope.

Mandatory because the prime contract requires it. Some clauses have no flow-down paragraph at all. FAR 52.219-8, Utilization of Small Business Concerns, contains no self-executing instruction to insert it downward. It reaches subcontracts because FAR 52.244-6(c)(1)(x) and FAR 52.212-5(e)(1)(viii) tell the prime to insert it, and because the prime contract says so. If the prime contract is silent and no listing clause applies, there is nothing making that clause a subcontract obligation.

Conditional and self-deleting. A large share of the FAR 52.244-6 list is conditional on its face. Several entries read “if flow down is required in accordance with paragraph (x) of FAR clause y,” which means the prime has to open the referenced clause and check. FAR 52.203-13 flows down only to subcontracts that exceed the FAR 3.1004(a) threshold and have a performance period of more than 120 days. Clauses like these appear in the prime contract in full, then delete themselves for any subcontract that fails the condition. Treating them as unconditional is the most common over-flow error.

How does the commercial-item flow-down limitation at FAR 52.244-6 work?

FAR 52.244-6 caps what a prime may require from a commercial subcontractor: only the clauses listed in that clause are required in subcontracts for commercial products or commercial services, regardless of what else appears in the prime contract. The FAR states the rule directly at 44.402(b):

“The clause at 52.244-6, Subcontracts for Commercial Products and Commercial Services, implements the policy in paragraph (a) of this section. Notwithstanding any other clause in the prime contract, only those clauses identified in the clause at 52.244-6 are required to be in subcontracts for commercial products or commercial services.”

FAR 44.402(b), acquisition.gov, FAC 2026-01

The October 2025 version of 52.244-6 lists 24 clauses at paragraph (c)(1). That is the ceiling, not the floor. Paragraph (c)(2) permits a prime to add “a minimal number of additional clauses necessary to satisfy its contractual obligations,” which is permission, not license. The parallel rule for a commercial prime contract sits at FAR 52.212-5(e)(1), which says the contractor “is not required to flow down any FAR clause, other than those in this paragraph (e)(1), in a subcontract for commercial products or commercial services.”

For construction this limitation bites at the supply end of the chain. Structural steel, elevators, HVAC equipment, and most manufactured building products are bought as commercial products. A prime that pushes its full federal clause package onto a commercial supplier is asking for a clause the FAR says the supplier does not have to accept, and the supplier’s refusal is not a compliance failure.

Note the direction of the exemption. It protects the subcontract, not the prime. The prime still owes the government every clause in its own contract. The contract clause prescription itself sits at FAR 44.403.

Which FAR clauses must flow down into a federal construction subcontract?

The matrix below lists the clauses a federal construction prime is most likely to owe downward, the tier each one reaches, the dollar threshold that switches it on, and why it matters. Thresholds are as of FAC 2026-01, effective March 13, 2026, and the inflation-adjusted ones move.

ClauseTitleWhich tier it reachesThresholdWhy it matters
Labor standards (construction)
52.222-11Subcontracts (Labor Standards)All tiers. Self-referencing: it is in its own insertion listPrime in excess of $2,000The carrier clause. It is what drags the other ten Davis-Bacon clauses down the chain
52.222-6Construction Wage Rate RequirementsAll tiers, via 52.222-11Prime in excess of $2,000Prevailing wage and fringe by classification for laborers and mechanics on site
52.222-7Withholding of FundsAll tiers, via 52.222-11In excess of $2,000Authorizes withholding from the prime for a lower-tier underpayment
52.222-8Payrolls and Basic RecordsAll tiers, via 52.222-11In excess of $2,000Weekly certified payroll and the three-year retention clock
52.222-9Apprentices and TraineesAll tiers, via 52.222-11In excess of $2,000Registered-program ratios. Paragraph (c) is removed under the 2025 equal opportunity deviations
52.222-10Compliance with Copeland Act RequirementsAll tiers, via 52.222-11In excess of $2,000Governs payroll deductions and kickback of wages
52.222-12Contract Termination, DebarmentAll tiers, via 52.222-11In excess of $2,000The consequence clause behind the wage rules
52.222-13Compliance with Construction Wage Rate Requirements and Related RegulationsAll tiers, via 52.222-11In excess of $2,000Incorporates 29 CFR parts 1, 3, and 5
52.222-14Disputes Concerning Labor StandardsAll tiers, via 52.222-11In excess of $2,000Routes wage disputes to the DOL process, not the contract Disputes clause
52.222-15Certification of EligibilityAll tiers, via 52.222-11In excess of $2,000Debarment certification by the signing party
52.222-4Contract Work Hours and Safety Standards, Overtime CompensationAll tiers, via 52.222-11Not used at or below $200,000 (FAR 22.305)Overtime past 40 hours for laborers and mechanics
Integrity and ethics
52.203-7Anti-Kickback ProceduresSubcontracts exceeding the FAR 3.502-2(i) threshold$200,000, non-commercialProhibits subcontractor kickbacks to obtain favorable treatment
52.203-13Contractor Code of Business Ethics and ConductSubcontracts over the threshold and over 120 days$7.5M (FAR 3.1004(a))Mandatory disclosure and internal control program
52.203-17Contractor Employee Whistleblower RightsAll subcontracts, no thresholdNoneCivilian agencies only. FAR 3.906 excludes DoD, NASA, Coast Guard, intel
52.203-19Prohibition on Requiring Certain Internal Confidentiality AgreementsPer 52.244-6 listingNone statedBars NDAs that block employees from reporting to the government
Supply chain and cyber
52.204-21Basic Safeguarding of Covered Contractor Information SystemsSubcontracts where the sub may hold federal contract information, excluding COTSNoneFifteen baseline safeguards. Requirement-based, not dollar-based
52.204-25Prohibition on Certain Telecommunications and Video SurveillanceAll subcontracts, including commercialNoneSection 889. Covers jobsite cameras and network gear
52.204-23Prohibition on Kaspersky Lab Covered EntitiesPer 52.244-6 listingNoneNamed-entity prohibition
52.204-27Prohibition on a ByteDance Covered ApplicationPer 52.244-6 listingNoneDevice-level prohibition reaching field staff
52.204-30Federal Acquisition Supply Chain Security Act OrdersPer 52.244-6 listing, with Alternate INoneExclusion orders under FASCSA
Labor and workforce
52.222-35Equal Opportunity for VeteransPer clause$200,000 or more (FAR 22.1310)Statutory under 38 U.S.C. 4212. Survived the 2025 revocations
52.222-36Equal Opportunity for Workers with DisabilitiesPer clauseExceeds $20,000 (FAR 22.1408)Statutory under 29 U.S.C. 793. Survived the 2025 revocations
52.222-37Employment Reports on VeteransTravels with 52.222-35$200,000 or moreVETS-4212 reporting
52.222-40Notification of Employee Rights Under the NLRAEvery subcontract exceeding the threshold, performed wholly or partly in the USExceeds $10,000Posting obligation, easy to miss at lower tiers
52.222-50Combating Trafficking in PersonsAll subcontracts and all contracts with agentsNone for the clause; certification only above $700,000 for overseas workThe compliance-plan certification is the conditional part, not the clause
52.222-54Employment Eligibility Verification (E-Verify)Subcontracts for construction or services performed in the USSubcontract more than $3,500; prime exceeding $150,000The $3,500 subcontract trigger is far lower than most primes assume
52.222-26Equal OpportunityEvery non-exempt subcontract, per (c)(11)Historically $10,000Under class deviation since Feb 2025. See the section below
52.222-21Prohibition of Segregated FacilitiesWith 52.222-26With 52.222-26Under class deviation
52.222-27Affirmative Action Compliance Requirements for ConstructionWith 52.222-26In excess of $10,000 (FAR 22.810(f))Under class deviation
Small business
52.219-8Utilization of Small Business ConcernsSubcontracts offering further subcontracting opportunities; lower tiers if above the FAR 19.702(a) thresholdPrime above the SAT ($350,000)No self-executing flow-down. It reaches subs through 52.244-6 and the prime contract
52.219-9Small Business Subcontracting PlanLarge-business subs with further subcontracting possibilities must adopt their own plan$900,000, or $2M for construction of a public facility (FAR 19.702)The plan obligation replicates, it does not merely pass through
Payment
52.232-40Providing Accelerated Payments to Small Business SubcontractorsAll subcontracts with small business concerns, including commercialNone15 days after the prime receives an accelerated payment
Domestic preference
52.225-9Buy American, Construction MaterialsApplies to construction material regardless of who buys itConstruction under $6,683,000 (FAR 25.1102)Domestic content test applies to the material, not the tier
52.225-11Buy American, Construction Materials under Trade AgreementsSame$6,683,000 or moreTrade agreement thresholds are set by USTR and are not inflation-indexed under FAR 1.109(c)
Commercial subcontracts
52.244-6Subcontracts for Commercial Products and Commercial ServicesAll tiers, via paragraph (d)In contracts other than those for commercial products or servicesThe ceiling clause. Lists the only 24 clauses required in a commercial subcontract
DoD only (DFARS)
252.204-7012Safeguarding Covered Defense Information and Cyber Incident ReportingAny subcontract involving covered defense information or operationally critical support, including commercial, without alterationNone. Requirement-based72-hour reporting. Reaches suppliers by subject matter, not contract value
252.204-7021Contractor Compliance with CMMC Level RequirementsSubcontracts including commercial, excluding COTS, that process, store, or transmit FCI or CUIPhased under 32 CFR 170The prime must confirm the sub's CMMC status before subcontract award

For the two working documents behind this reference, see the FAR clause flow-down map, prime to sub→ and the federal subcontract flow-down clauses checklist→.

Which flow-downs actually reach every tier, and which stop at the first?

The clauses that reach every tier are the ones written to repeat themselves, and in federal construction that is a short and predictable list: the Davis-Bacon package carried by FAR 52.222-11, FAR 52.244-6 through its paragraph (d), FAR 52.203-17 and FAR 52.204-25 through their all-subcontracts language, and FAR 52.222-50. Most of the rest reach the tier where they were inserted and depend on the next contract down to carry them further.

FAR 52.222-11 also does something the other clauses do not: it makes the prime answerable for the chain. The clause states that the prime is responsible for compliance by any subcontractor or lower tier subcontractor with the labor standards clauses, and it requires a Standard Form 1413 for each subcontract, with the subcontractor’s acknowledgment that the clauses were included. That is an affirmative proof obligation, not just an insertion obligation. The clause prescriptions for the construction wage package sit at FAR 22.407.

The Department of Labor’s Wage and Hour Division closed 641 Davis-Bacon and Related Acts compliance actions in fiscal year 2025 and recovered $26,754,050 in back wages for 5,812 employees, up from $14,115,932 the prior year. Prevailing wage recoveries nearly doubled year over year while the number of concluded actions fell, which means the average case got substantially larger.

For the certified payroll side of that obligation, see certified payroll software for construction→.

What dollar thresholds switch a FAR flow-down clause on or off?

Most statutory thresholds adjust for inflation every five years, and as of FAC 2026-01 the simplified acquisition threshold is $350,000 and the micro-purchase threshold is $15,000. Both moved upward in the most recent adjustment, which is why guidance written before 2026 citing $250,000 and $10,000 is now wrong.

FAR 1.109 sets the mechanism, and its exclusions are the more useful half of the rule. The statute does not permit escalation of thresholds established by 40 U.S.C. chapter 31, subchapter III (Bonds) or subchapter IV (Wage Rate Requirements, Construction), or by 41 U.S.C. chapter 67 (Service Contract Labor Standards). That is the reason the Davis-Bacon trigger has sat at $2,000 for decades while everything around it drifted upward. The same logic appears in the definition of micro-purchase threshold at FAR 2.101, which is $15,000 generally but $2,000 for construction subject to the wage rate statute.

FAR 1.109(d) adds a detail that catches long construction projects: an adjusted threshold applies to contracts and subcontracts without regard to the date of award, so a changed threshold applies for the remaining term of an existing contract. A multi-year federal project can cross a threshold change mid-performance, and the new number governs going forward.

Three thresholds are worth committing to memory because they are lower than people expect: E-Verify flows down to construction subcontracts over $3,500, the NLRA notice clause flows down over $10,000, and the disability clause at 52.222-36 applies at just over $20,000.

What changed in 2025 and 2026 that most flow-down guides still get wrong?

Three things changed: the equal opportunity clauses stopped being enforced, several dollar thresholds moved, and FAR Part 44 itself is being rewritten. Any flow-down list that predates 2025 is now wrong in at least one of those directions.

Executive Order 14173 revoked Executive Order 11246 on January 21, 2025. Agencies then issued class deviations under FAR 1.404 telling contracting officers to stop applying the associated clauses. A HUD class deviation implementing the change puts it plainly in the notice it directs contracting officers to send:

“As of February 15, 2025, FAR clauses and provisions covered under E.O. 11246, Equal Employment Opportunity, will no longer be enforced. Therefore, contractors and their subcontractors will not be held accountable for applying the FAR clauses or provisions outlined in FAR subpart 22.8.”

HUD class deviation implementing E.O. 14173 and E.O. 14168, signed May 22, 2025

That deviation directs contracting officers not to include 52.222-21, 52.222-22, 52.222-23, 52.222-24, 52.222-25, 52.222-26, 52.222-27, 52.222-29, or paragraph (c) of 52.222-9. The Department of Defense issued its own version, Class Deviation 2025-O0003, on March 4, 2025.

The important structural point is which clauses survived. The deviation expressly does not affect FAR subpart 22.13 (veterans) or subpart 22.14 (workers with disabilities), because those rest on statute rather than on the executive order. Statutory flow-downs survive an administration change. Executive-order flow-downs do not. That is the single most useful sorting rule a contract administrator can apply to a clause list.

The FAR text itself has not caught up. FAR 22.810 and FAR 52.222-26 still appear in the current FAR, and 52.222-26 is still listed inside 52.244-6. A prime reading only the FAR would conclude the clause is live. A prime reading its agency’s deviations would not.

Meanwhile the government-wide FAR overhaul is rewriting the regulation to, in the FAR Council’s words, “return the FAR to its statutory roots, rewrite it in plain language, and remove most non-statutory rules.” Part 44, Subcontracting Policies and Procedures, received its overhaul text on September 4, 2025, and 27 agencies have posted their own Part 44 deviations. The overhaul text restates the commercial flow-down limitation in plainer terms at 44.402(b): do not require a contractor or subcontractor to apply a clause that is not listed in 52.244-6 to any division, subsidiary, affiliate, subcontractor, or supplier furnishing commercial products or services.

The practical consequence is that the flow-down rules governing a given subcontract now depend on which agency awarded the prime contract. Checking the FAR alone is no longer sufficient. For the wider compliance picture, see construction compliance software for federal GCs→.

What flows down on a DoD construction subcontract that does not on a civilian one?

DoD adds the DFARS cybersecurity clauses and subtracts the whistleblower clause. DFARS 252.204-7012 requires the contractor to include the clause, without alteration except to identify the parties, in subcontracts for operationally critical support or where performance will involve covered defense information, including subcontracts for commercial products and services. There is no dollar threshold. The trigger is subject matter, which is why it reaches design consultants and specialty suppliers that would otherwise sit below every dollar-based flow-down on the list.

DFARS 252.204-7021, effective November 10, 2025, adds the CMMC obligation and changes the nature of the duty. The prime must insert the substance of the clause into subcontracts that will process, store, or transmit federal contract information or controlled unclassified information, excluding commercially available off-the-shelf items, and then, before awarding the subcontract, confirm the subcontractor holds a current CMMC status at the appropriate level under 32 CFR 170.23. Most flow-downs are satisfied by inserting text. This one is not satisfied until the prime has verified something about the subcontractor.

DoD estimated the population affected at 337,968 unique entities including prime contractors and subcontractors, of which 229,818, or 68 percent, are small entities (90 FR 43560).

Running the other direction, FAR 3.906 prescribes the whistleblower rights clause at 52.203-17 for all solicitations and contracts except those of DoD, NASA, the Coast Guard, and applicable elements of the intelligence community. A clause that flows down to every subcontract on a civilian job is simply absent on a DoD one. For scoping the cybersecurity side, see CMMC compliance software for contractors→.

How do small business flow-downs work differently from the rest?

Small business flow-downs replicate an obligation rather than merely passing text down, which is why they behave unlike every other clause on the list. FAR 52.219-9 requires the prime to obtain assurances that subcontractors receiving subcontracts above the FAR 19.702(a) threshold, with further subcontracting possibilities, will themselves adopt a subcontracting plan complying with the same clause. The first-tier subcontractor does not just accept a clause. It takes on the prime’s own reporting and goal-setting duty.

The thresholds moved here too. FAR 19.702(a) now requires a subcontracting plan above $900,000, or $2 million for construction of a public facility, replacing the $750,000 and $1.5 million figures still quoted in older guidance.

This is also the flow-down with the clearest published scoreboard. Per the SBA’s small business procurement scorecard, with subcontracting data retrieved January 30, 2026, federal small business subcontracting achievement for fiscal year 2025 was 32.65 percent, or $93.7 billion, against a 33.34 percent goal. The socioeconomic categories missed by wider margins: HUBZone achievement was 1.54 percent against a 3 percent goal, and service-disabled veteran-owned achievement was 2.42 percent against a 5 percent goal. Subcontracting is where the government’s small business goals are hardest to hit, and the clause package is the mechanism it uses to try.

For the tracking side of subcontractor obligations, see subcontractor compliance automation→.

What does this page not cover?

This page is a reference on which FAR clauses flow down and at which tier. It is not a substitute for reading your actual prime contract, and it cannot tell you what your specific contract requires.

Several limits are worth stating directly:

  • Your prime contract governs. The clause list in your contract, including any agency supplement and any incorporated by reference, controls. A clause can be required in your subcontracts because your prime contract says so even when nothing in the FAR compels it. This page cannot see your contract.
  • Agency supplements are not covered here. DFARS is addressed only for the two cybersecurity clauses. VAAR, GSAR, DOE, and other agency regulations add their own flow-downs and are outside this page’s scope.
  • Deviation status changes. The equal opportunity position described above reflects class deviations in effect as of July 29, 2026. Deviations are rescinded or absorbed into the FAR over time, and the government-wide FAR overhaul is actively renumbering and rewriting the parts this page cites. Confirm against your contracting officer and your agency’s current deviation list before relying on any clause status here.
  • Dollar thresholds move. Every figure on this page is stated as of FAC 2026-01, effective March 13, 2026. Statutory thresholds adjust for inflation on a five-year cycle under FAR 1.109, and trade agreement thresholds are reset separately by the U.S. Trade Representative.
  • This is not legal advice. Whether a particular clause is required in a particular subcontract, and what happens if it was omitted, is a legal question. Flow-down disputes turn on contract interpretation, and the answer can depend on facts this page has no access to. Talk to counsel or your contracting officer.

We have also deliberately left out the question of what happens when a required clause was omitted from an executed subcontract. That doctrine is unsettled as applied to subcontracts, and a page that flattened it into a rule would be doing you a disservice.

How does Contracts Connected help with flow-down compliance?

Contracts Connected doesn’t read your prime contract, build your flow-down list or check each subcontract clause by clause. It handles the contract side of the job. Every subcontract fills from your own template, so the clauses you flow down go out in every one. Your people approve the package before it goes out, and if a vendor marks up a clause, the change shows in the contract for you to accept, reject or revise. The signed copy is filed with who approved it and when.

That matters for the proof this page has been about. Flow-down failures are rarely failures to know the rule. They are failures to show, months or years later, that a specific clause made it into the paper a specific subcontractor signed. When every subcontract starts from the same template and the signed copy is on file, that answer starts in one place instead of a search through email.

Frequently asked questions

Do all FAR clauses in a prime contract flow down to subcontractors?

No. A FAR clause reaches a subcontractor only if something requires it: the clause’s own subcontracts paragraph, an express requirement written into the prime contract, or FAR 52.244-6 for commercial subcontracts. Copying the prime’s entire clause list into a subcontract is a common mistake. It creates obligations the government never imposed, and it gives the subcontractor an argument that the whole clause package was boilerplate.

Which FAR clauses flow down to every tier of a construction subcontract?

The Davis-Bacon labor standards clauses reach every tier. FAR 52.222-11 requires the prime to insert 52.222-6 through 52.222-15 into construction subcontracts, and because that list includes 52.222-11 itself, each subcontractor must repeat the insertion downward. FAR 52.203-17 and FAR 52.204-25 also reach all subcontracts with no dollar threshold, and FAR 52.244-6 carries its own terms down at every tier.

What is the commercial-item flow-down limitation at FAR 52.244-6?

FAR 44.402(b) states that only the clauses identified in 52.244-6 are required in subcontracts for commercial products or commercial services, notwithstanding any other clause in the prime contract. The October 2025 version of 52.244-6 lists 24 clauses. If a clause is not on that list, a prime cannot require a commercial subcontractor or supplier to accept it as a federal flow-down obligation.

What dollar thresholds turn FAR flow-down clauses on or off?

Thresholds vary by clause, and most statutory ones adjust for inflation every five years under FAR 1.109. As of FAC 2026-01, the simplified acquisition threshold is $350,000 and the micro-purchase threshold is $15,000. Davis-Bacon is the exception. FAR 1.109(c) bars escalation of the construction wage statute’s thresholds, which is why the $2,000 construction trigger has never moved.

Did FAR 52.222-26 Equal Opportunity stop flowing down?

Executive Order 14173 revoked Executive Order 11246 on January 21, 2025, and agencies issued class deviations directing contracting officers not to include 52.222-26, 52.222-21, and 52.222-27. The FAR text still contains those clauses, so they appear in contracts awarded earlier. The veterans and disability clauses at 52.222-35, 52.222-36, and 52.222-37 rest on statute rather than the executive order and are unaffected.

What flows down on a DoD construction subcontract that does not on a civilian one?

DFARS 252.204-7012 flows down to any subcontract involving covered defense information or operationally critical support, without alteration except to identify the parties. DFARS 252.204-7021 adds the CMMC requirement and obligates the prime to confirm the subcontractor’s CMMC status before awarding the subcontract. FAR 52.203-17 runs the other direction: FAR 3.906 excludes DoD, NASA, the Coast Guard, and parts of the intelligence community.

Contracts Connected is the Back-Office System (BOS) for construction.

See what it would take off your plate.

SOC 2 Type II · U.S. hosted · AI optional
Book a demo